You are viewing the permanent link for the record currently in effect, published 2026-07-07.

Benson building permits

Verified

Benson, Arizona — as published 2026-07-07.

Verified 2026-07-06 · Source

Codes adopted

Arizona has no statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (Arizona Revised Statutes Title 9). The City of Benson independently adopts and administers its own construction codes through its Building Department. Source: Ordinance 645 (City of Benson, adopted April 13, 2026), whereas clause citing A.R.S. Title 9.2024 International Building Code (IBC), as amended by Exhibit A to Resolution 11-2026, adopted by reference in Benson City Code Chapter 7, Section 7-1-2 ('Building Codes Adopted'). Per Ordinance 645, all new permit applications received after May 13, 2026 (30 days after the April 13, 2026 adoption date) must comply with this code; plans already in review or approved before that date may remain on the previously adopted 2015 IBC cycle. Source: Ordinance 645, City of Benson (passed and adopted April 13, 2026).2024 International Residential Code (IRC), as amended by Exhibit B to Resolution 11-2026, adopted by reference in Benson City Code Chapter 7, effective for new applications received on/after May 13, 2026. Source: Ordinance 645, City of Benson.2024 International Mechanical Code (IMC), as amended by Exhibit D to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.2024 International Plumbing Code (IPC), as amended by Exhibit E to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.2024 International Fuel Gas Code (IFGC), as amended by Exhibit F to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.2024 International Existing Building Code (IEBC), as amended by Exhibit G to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.2024 International Swimming Pool and Spa Code (ISPSC), as amended by Exhibit H to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.2024 International Fire Code (IFC), as amended by Exhibit I to Resolution 11-2026, adopted by reference as the City's uniform fire code. Source: Ordinance 645, City of Benson.2024 International Property Maintenance Code (IPMC), as amended by Exhibit J to Resolution 11-2026, adopted by reference. Source: Ordinance 645, City of Benson.2023 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by reference as amended by Exhibit C to Resolution 11-2026 (one edition behind the 2024 ICC set, consistent with the standard NFPA/ICC release-cycle offset). Source: Ordinance 645, City of Benson.Immediately prior to Ordinance 645 (i.e., for plans submitted and approved before May 13, 2026), the City had adopted the 2015 editions of the International Building, Residential, Mechanical, Plumbing, Fuel Gas, Existing Building, Swimming Pool and Spa, and Property Maintenance Codes, plus the 2015 International Fire Code and 2014 NFPA 70 National Electrical Code, per the former Benson City Code Chapter 7, Section 7-1-1 (Resolution 36-2017). Source: City of Benson Building Department page (Wayback Machine capture, November 24, 2025) and City Code of the City of Benson, Arizona (posting updated April 2023).Manufactured homes, mobile homes, and factory-built buildings: the City of Benson has an Inspection Services Agreement with the Arizona Department of Housing (ADOH), effective May 3, 2021 for a five-year term, under which the City (as ADOH's local enforcement agency) monitors and enforces ADOH's installation standards (A.R.S. § 41-4004(A)(4); A.A.C. R4-34-102, R4-34-204, R4-34-606, R4-34-801) for manufactured home, mobile home, and factory-built building installations within city limits, including setback and tie-down inspections. Source: Resolution 11-2021 and attached Inspection Services Agreement Between Arizona Department of Housing and City of Benson.ICC A117.1-2017 Standard and Commentary (Accessible and Usable Buildings and Facilities) is referenced by the City as its accessibility standard, in addition to the federal ADA framework. Source: City of Benson Building Department page.

Permit types & fees

Residential Building Permit (New Single-Family / Duplex / Multi-Family Construction)

Verified

Required for new single-family, duplex, and multi-family residential construction in the City of Benson. Reviewed against the 2024 IRC and 2024 IBC as adopted by Ordinance 645 (effective for applications received on/after May 13, 2026; earlier submittals remain on the 2015 IRC/IBC cycle). Applications are submitted through the City's online iWorQ Building/Demolition Permit Application portal.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for new single-family, duplex, and multi-family dwelling construction within Benson city limits
  • Plans must comply with the 2024 IRC (or 2015 IRC for applications filed before May 13, 2026) as adopted and amended by the City of Benson via Ordinance 645 / Resolution 11-2026
  • One detached site plan (separate from the construction plan set) at 1"=20' scale (8.5x14 or 11x17 paper), showing lot dimensions, Tax Parcel ID, setbacks, street/driveway details, structure square footages, easements, and utility routing
  • Two complete sets of construction plans (11x17 at 1/8" scale computer-drawn, or 18x24 at 1/4" scale) plus a soils report at time of submittal; engineered design required for structural components retaining 4+ feet of earth; post-tension slabs (or equal) required due to unstable soil conditions City-wide
  • Signed A.R.S. Title 32 form required as part of the online application submittal
  • Hydrant system must be operational and subdivision roads paved (ingress/egress) before permit issuance; ADEQ Certificate of Completion required for water/sewer (model homes may receive Public Works sign-off without it if not yet connected)
  • HOA review verification required prior to submittal if the project is within an HOA-governed area
  • Permit valid 180 days from issue date; expires if no inspection progress for 6 consecutive months; one no-charge 6-month extension available within the initial 12-month period if significant progress (generally past framing) has been made

Required documents

  • RequiredOnline Building/Demolition Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net; all plans and supporting documents must be uploaded in PDF format (image files are not accepted)
  • RequiredA.R.S. Title 32 FormSigned form (may be digitally signed) required with every building permit application; a fillable PDF is provided by the Building Department
  • RequiredDetached Site PlanPer the Residential Building Permit Requirements (March 2018): lot dimensions, Tax Parcel ID, setback distances, street/driveway location, utility routing, and existing/proposed/future structure square footages
  • RequiredConstruction Drawings, Structural Calculations, and Soils ReportTwo complete sets, engineered design required for structural components retaining 4+ feet of earth; soils report required at time of submittal

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on Valuation$47.00 (valuation $1-$1,000); $47.00 + $4.00 per additional $100 to $2,000; $83.00 + $16.00 per additional $1,000 to $25,000; $466.00 + $12.00 per additional $1,000 to $50,000; $766.00 + $8.30 per additional $1,000 to $100,000; $1,181.00 + $6.70 per additional $1,000 to $500,000; $3,862.00 + $5.70 per additional $1,000 to $1,000,000; $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, as adopted by Resolution 16-2011 (codified in the City Code posting updated April 2023); no superseding fee resolution was found as of this review
Plan Review Fee (Single-Family Dwelling/Misc. Buildings, and All Other Buildings)65 percent of the calculated building permit feeCity Code of the City of Benson, Chapter 16, Building Division
Certificate of Occupancy / Housing Code Compliance Inspection$60.00 per dwelling unitCity Code of the City of Benson, Chapter 16

Residential Addition / Remodel / Accessory Structure Permit

Verified

Required for room additions, remodels, and accessory structures (stick-built or pre-built) to existing one- and two-family dwellings in Benson. Reviewed against the 2024 IRC as adopted by Ordinance 645 (2015 IRC for applications filed before May 13, 2026).

Verified 2026-07-06 · Source

Requirements

  • Building permit required for room additions, remodels, and accessory structures (garages, storage sheds, etc.), whether stick-built or pre-built (e.g., prefabricated sheds)
  • Site plan and construction plans required per the same submittal standards as new residential construction (detached site plan at 1"=20' scale; two sets of construction plans)
  • Pre-built accessory structures require setbacks, anchoring/tie-down, and foundation inspections in addition to any applicable electrical/plumbing rough-ins
  • Stick-built accessory structures follow the full framing/lath/sheetrock/final inspection sequence
  • HOA review verification required prior to submittal if applicable

Required documents

  • RequiredOnline Building Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every building permit application
  • RequiredSite PlanShowing existing structure, addition/accessory structure footprint, and setbacks

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on Valuation$47.00 (valuation $1-$1,000) up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000 (same valuation table as new residential construction)City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011
Plan Review Fee65 percent of the calculated building permit feeCity Code of the City of Benson, Chapter 16, Building Division

Electrical Permit

Verified

Required for electrical installation, alteration, or repair work in Benson, governed by the 2023 National Electrical Code (NEC) as adopted by Ordinance 645 (2014 NEC for applications filed before May 13, 2026).

Verified 2026-07-06 · Source

Requirements

  • Electrical permit required for new electrical service, panel work, and other hard-wired electrical installations
  • Governed by the 2023 NEC as adopted by the City of Benson (2014 NEC for applications submitted before May 13, 2026)
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form
  • New Meter Request supplemental form required for new water, gas, or sewer tap connections tied to electrical service work where applicable

Required documents

  • RequiredOnline Building/Electrical Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Electrical Permit — Based on ValuationSame Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — Benson's fee schedule does not publish a separate itemized electrical-only fee table; electrical work is billed under the same valuation-based Building Division fee schedule as other trade permits
Plan Review Fee65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division

EV Charger / EVSE Installation Permit

Verified

Benson has no separate EV charger/EVSE permit category or fee line. Installing a new dedicated 120V or 240V circuit for an EV charger is billed as a standard Electrical Permit under the same valuation-based Building Division fee schedule used for all other electrical work, governed by the 2023 NEC as adopted by Ordinance 645.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit required for a new dedicated 120V or 240V circuit installed for an EV charging station; a permit is generally NOT required if a UL-listed cord-and-plug charger is plugged into an existing 120V receptacle with no new wiring (consistent with neighboring Cochise/Pima County practice; not independently confirmed in a Benson-specific document)
  • Governed by the 2023 NEC as adopted by the City of Benson (2014 NEC for applications submitted before May 13, 2026)
  • No dedicated EV/EVSE fee line exists on the City Code's Chapter 16 fee schedule; billed under the same valuation-based Building Permit Fee table as all other electrical/trade work
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form

Required documents

  • RequiredOnline Building/Electrical Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format; no separate EV-specific application form is published
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Electrical Permit — Based on Valuation (covers EV charger circuit installation)Same Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — confirmed no separate itemized EV/EVSE fee line exists; electrical work of any kind, including EV charger circuits, is billed under the same valuation-based Building Division fee schedule
Plan Review Fee65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division

Plumbing Permit

Verified

Required for plumbing installation, alteration, or repair work in Benson, governed by the 2024 International Plumbing Code (IPC) as adopted by Ordinance 645 (2015 IPC for applications filed before May 13, 2026).

Verified 2026-07-06 · Source

Requirements

  • Plumbing permit required for installation, alteration, or repair of plumbing systems, fixtures, water heaters, and gas piping
  • Governed by the 2024 IPC as adopted by the City of Benson (2015 IPC for applications submitted before May 13, 2026)
  • Gas piping work is separately inspected under the Fire/Plumbing inspection categories (Gas Piping, 200# Test) per the Required Inspections List
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form

Required documents

  • RequiredOnline Building/Plumbing Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Plumbing Permit — Based on ValuationSame Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — Benson does not publish a separate itemized flat fee for plumbing-only permits; plumbing work is billed under the same valuation-based Building Division fee schedule
Plan Review Fee65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division

Mechanical / HVAC Permit

Verified

Required for heating, ventilation, and air conditioning installations in Benson, governed by the 2024 International Mechanical Code (IMC) as adopted by Ordinance 645 (2015 IMC for applications filed before May 13, 2026).

Verified 2026-07-06 · Source

Requirements

  • Mechanical permit required for installation, replacement, or relocation of HVAC equipment, furnaces, and ventilation systems
  • Governed by the 2024 IMC as adopted by the City of Benson (2015 IMC for applications submitted before May 13, 2026)
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form

Required documents

  • RequiredOnline Building/Mechanical Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Mechanical Permit — Based on ValuationSame Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — Benson does not publish a separate itemized flat fee (e.g., per-unit AC replacement) for mechanical permits; mechanical work is billed under the same valuation-based Building Division fee schedule
Plan Review Fee65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division

Re-Roofing Permit

Verified

Required for residential and commercial re-roofing in the City of Benson. Reviewed against the 2024 IBC/IRC roofing provisions as adopted by Ordinance 645 (2015 editions for applications filed before May 13, 2026).

Verified 2026-07-06 · Source

Requirements

  • Building permit required for re-roofing work within Benson city limits
  • Roof deck inspection required prior to final roof covering placement, per the City's Required Inspections List
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form

Required documents

  • RequiredOnline Building Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Roofing Permit — Based on ValuationSame Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — no separate itemized re-roofing fee is published; re-roofing is billed under the same valuation-based Building Division fee schedule
Plan Review Fee65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division

Residential Solar Photovoltaic (PV) Permit

Verified

Required for installation of rooftop residential solar photovoltaic systems in the City of Benson. Governed by the 2024 IRC and 2023 NEC as adopted by Ordinance 645 (2015 IRC / 2014 NEC for applications filed before May 13, 2026). Solar has its own dedicated inspection category on the City's Required Inspections List.

Verified 2026-07-06 · Source

Requirements

  • Building/electrical permit required for residential rooftop solar photovoltaic installation
  • Governed by the 2023 NEC (or 2014 NEC for applications filed before May 13, 2026) as adopted by the City of Benson for electrical interconnection work
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form and construction submittals (site plan, roof/racking layout, electrical diagram)

Required documents

  • RequiredOnline Building/Electrical Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format; construction submittals may include site plans, construction documents, specification/cut sheets, calculations, and engineering reports
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Solar PV Permit — Based on ValuationSame Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — no separate itemized flat fee for residential solar PV was found; solar is billed under the same valuation-based Building Division fee schedule
Plan Review Fee65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division

Demolition Permit

Verified

Required for demolition of any structure in Benson. Applications are submitted through the same online iWorQ portal used for building permits, and require a signed A.R.S. Title 32 form and an ADEQ Asbestos NESHAP form where applicable.

Verified 2026-07-06 · Source

Requirements

  • Building permit required before demolishing a structure within Benson city limits
  • Use the online Building/Demolition Permit Application (iWorQ Citizen Portal) — the same application covers Building Permits, Demolition Permits, Grubbing or Grading Permits, and Right-of-Way Construction Permits
  • Signed A.R.S. Title 32 form required as part of the application
  • ADEQ Asbestos NESHAP form (supplied on the Building Department's Document Center) must be submitted where applicable to the demolition scope

Required documents

  • RequiredOnline Building/Demolition Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every demolition permit application
  • OptionalADEQ Asbestos NESHAP FormAvailable from the City of Benson Building Department Document Center; required where asbestos abatement/NESHAP notification applies

Fee schedule

Fee typeAmountNotes
Demolition Permit — Based on ValuationSame Building Permit Fee valuation table as other trades: $47.00 (valuation $1-$1,000) scaling up to $6,712.00 + $4.40 per additional $1,000 above $1,000,000City Code of the City of Benson, Chapter 16 (Fees), Building Division, Resolution 16-2011 — no separate itemized flat demolition fee was found; demolition is billed under the same valuation-based Building Division fee schedule

Manufactured Home / Factory-Built Building Installation Permit

Verified

Required for installation of manufactured homes, mobile homes, and factory-built buildings in Benson. The City acts as the local enforcement agency for the Arizona Department of Housing (ADOH) under a five-year Inspection Services Agreement (effective May 3, 2021), enforcing ADOH's installation standards rather than a separately city-authored code.

Verified 2026-07-06 · Source

Requirements

  • Installation permit required for manufactured homes, mobile homes, and factory-built buildings placed within Benson city limits
  • The City enforces installation standards under A.R.S. § 41-4004(A)(4) and Arizona Administrative Code R4-34-102, R4-34-204, R4-34-606, and R4-34-801, per its Inspection Services Agreement with ADOH
  • Installer must affix a State Insignia of Approval per A.A.C. R4-34-802(A) and pay the ADOH-established fee under A.A.C. R4-34-501
  • City inspectors performing installation inspections must have at least one year of experience as a building code inspector or manufactured housing installation inspector and complete required ADOH training
  • Manufactured Home and Factory Built Building Application (supplemental form) must be submitted with the permit application
  • Setback, tie-down, and supports inspections are required per the City's Required Inspections List (Manufactured Homes category)

Required documents

  • RequiredManufactured Home and Factory Built Building ApplicationSupplemental form available on the City of Benson Building Department Document Center
  • RequiredOnline Building Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application

Fee schedule

Fee typeAmountNotes
Residential Manufactured Home Installation, Setback & Tie-Down Inspection$200.00City Code of the City of Benson, Chapter 16 (Fees), per the Intergovernmental Agreement with the Arizona Office of Manufactured Housing, Resolution 16-2011
Each Additional Inspection After Three$50.00City Code of the City of Benson, Chapter 16 (Fees)
Manufactured Building Permit Renewal$84.00City Code of the City of Benson, Chapter 16 (Fees)
Factory-Built Building Installation, Commercial$4.60 per linear foot per storyCity Code of the City of Benson, Chapter 16 (Fees) — residential FBB is billed the same as a manufactured home

Sign Permit (Commercial / Business Signage)

Verified

Required to erect, re-erect, construct, alter, relocate, or maintain most commercial/business signs in the City of Benson, per the City's Zoning Regulations, Section Fifteen (Sign Regulations), originally adopted by Ordinance 330 (12/18/1989) and subsequently amended (most recently by Ordinance 449, 8/19/2002); the currently posted Zoning Regulations document (fetched directly from bensonaz.gov) carries a cover-page revision date of 01/13/2025 but a filename indicating a further update via Ordinance 647 (6/8/2026). Signage has its own dedicated inspection category (Signage: Setbacks, Electrical if applicable, Final) on the City's Required Inspections List.

Verified 2026-07-23 · Source

Requirements

  • A building permit from the Building Inspector is required to erect, re-erect, construct, repair, alter, relocate, or maintain any sign as defined in Zoning Regulations Section Fifteen, except for sign types specifically exempted
  • Exempt from a building permit: nameplate signs, home occupation signs, real estate/political/contractor/developer signs, non-illuminated wall signs not exceeding 50 square feet, repairs or repainting not exceeding $200.00 in value, and window signs
  • Application for a sign building permit must be accompanied by, at minimum, a site plan, construction plans, and written consent of the landowner
  • Permitted sign type, size, and height vary by zoning district (Residential, B-1 Neighborhood Business, B-2 General Business, Industrial, Rural Transitional) per Zoning Regulations Section Fifteen; e.g., B-1 districts authorize 50 sq ft of signage per building frontage (up to 75 sq ft aggregate based on frontage), B-2 districts authorize 75 sq ft (up to 150-200 sq ft aggregate depending on location), and Industrial districts authorize 100 sq ft (up to 300 sq ft aggregate)
  • Signs are additionally constructed/maintained per the Uniform Sign Code, Uniform Building Code, and National Electric Code as referenced in Section Fifteen; current structural/electrical work in the City is otherwise governed by the 2024 IBC/IRC and 2023 NEC as adopted by Ordinance 645 (2015 editions for applications filed before May 13, 2026) — no separate re-adoption of Section Fifteen's sign-specific code references was found alongside Ordinance 645
  • The Building Official may revoke a sign permit found to be in violation of its terms, and may approve a one-time extension (up to one year) of a sign's required removal date upon application and proof of need
  • A sign advertising a business no longer conducted, or products no longer sold, at that location must be removed by the owner/agent within 10 days of the business terminating; the City may remove it 30 days after written notice to the property owner, billing removal costs to the owner
  • For businesses fronting an Arizona Department of Transportation (ADOT) right-of-way (e.g., along I-10), a State of Arizona sign permit does not eliminate the need for a separate City of Benson sign permit

Required documents

  • RequiredOnline Building Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format; no distinct standalone 'sign permit application' form was found separate from the general Building Permit Application — signage is applied for as a building permit per Zoning Regulations Section Fifteen
  • RequiredSite Plan, Construction Plans, and Written Landowner ConsentMinimum submittal required per Zoning Regulations Section Fifteen ('Sign Permits, Fees, and Removal')
  • RequiredA.R.S. Title 32 FormSigned form required with every building permit application

Fee schedule

Fee typeAmountNotes
Non-Illuminated Wall Sign, or Non-Illuminated Wood Ground Sign (≤ 20 ft height)$15.00 flat building permit feeZoning Regulations, Section Fifteen ('Sign Permit Fees'); this flat-fee provision was adopted in 1989-2002 and no superseding fee resolution specific to signs was found — treated as still in force absent contrary evidence
All Other Signs (not covered by the $15 flat fee above)Billed as a standard building permit under the general valuation-based Building Permit Fee schedule, per Zoning Regulations Section Fifteen ('the building permit fee shall be as established in the Uniform Building Code')IMPORTANT CORPUS-WIDE FLAG: two different versions of this general valuation-based fee table were found during this research. (1) The City Code Chapter 16 compilation already cited throughout this file ('Website Posting updated 4-2023.pdf', Resolution 16-2011) uses a coarser formula (e.g., $83.00 at $2,000 valuation). (2) The 'Building Permit Fee Schedule' PDF currently linked from the live bensonaz.gov Building Department page (fetched and visually verified 2026-07-23) uses a more granular per-$100/$1,000 table with materially different low-end values (e.g., $99.00 at $2,000 valuation, not $83.00), though it converges to the same plan-review ratio (65%) and per-$1,000 marginal rates ($6.70/$5.70/$4.40) at higher valuations. No dated resolution number appears on the newer live schedule. This entry cites the general schedule by reference only (consistent with how electrical/plumbing/mechanical/roofing/solar/demolition permits are documented elsewhere in this file) — the controlling session should reconcile which schedule is authoritative across ALL trade-permit entries in this file, not just this one.
Plan Review Fee (signs billed under the general valuation schedule only; not applicable to the $15 flat-fee sign types)65 percent of the calculated permit feeCity Code of the City of Benson, Chapter 16, Building Division; confirmed as the same ratio on the live Building Permit Fee Schedule PDF

Fire Sprinkler System & Fire Alarm System Permit

Verified

Required for installation, alteration, or repair of automatic fire sprinkler (fire suppression) systems and fire alarm/detection systems in Benson, reviewed under the 2024 International Fire Code (IFC) as adopted by Ordinance 645 (2015 IFC for applications filed before May 13, 2026). The City of Benson operates its own municipal Fire Department (a combination full-time-Chief/volunteer department historically chartered as 'Benson Volunteer Fire Department Inc.') that performs its own fire-plan review, inspections, and annual business walk-throughs — confirmed NOT dependent on a separate Cochise County rural fire protection district for these functions within city limits.

Verified 2026-07-23 · Source

Requirements

  • A permit is required for installation, alteration, or repair of fire sprinkler (automatic fire suppression) systems and fire alarm/detection systems, governed by the 2024 IFC as adopted by the City of Benson via Ordinance 645 (2015 IFC for applications filed before May 13, 2026)
  • The City of Benson maintains its own Fire Department; it is not routed to an outside Cochise County rural fire district for plan review or inspection within city limits (confirmed via the City's live Fire Department page and City Code Chapter 4-3, Public Safety)
  • Fire inspection requests, including the annual business walk-through, are directed to the Fire Department at fireinspections@bensonaz.gov (per the live Building Department page)
  • Apply via the online iWorQ Building Permit Application portal with a signed A.R.S. Title 32 form
  • For new commercial development, the City's Commercial Checklist requires dedicated 'Fire Department Submittal Requirements': approved site and building plans showing hydrant and riser-room locations (8.5x11 sheets), plus a Hydrant Flow Test Report; the Commercial Project Closeout Checklist likewise requires formal Fire Marshal acceptance of hydrant installation/flow testing and sign-off on Fire Department requirements before project closeout
  • The City's Required Inspections List includes a dedicated 'Fire' inspection category covering Plumbing, Gas Piping, 200# Test, Fire Alarm, and Fire Suppression as distinct inspection items

Required documents

  • RequiredOnline Building/Fire Permit Application (iWorQ Citizen Portal)Submitted via bensonbuilding.portal.iworq.net in PDF format; no separate standalone fire-sprinkler- or fire-alarm-specific application form was found distinct from the general Building Permit Application
  • RequiredA.R.S. Title 32 FormSigned form required with every permit application
  • RequiredApproved Site/Building Plans (hydrant + riser room location) and Hydrant Flow Test ReportRequired for new commercial development per the City's Commercial Checklist, 'Fire Department Submittal Requirements' section

Fee schedule

Fee typeAmountNotes
Fire Sprinkler Plan Review Fee65 percent of the sprinkler permit feeCity Code of the City of Benson, Chapter 16 (Fees), Building Division — named as its own line item distinct from the general 'all other buildings' 65 percent plan-review ratio, implying sprinkler systems are valued and permitted as their own permit type; no separate flat base-fee table for the underlying 'sprinkler permit fee' itself was found, so it appears to be billed via the same general valuation-based Building Permit Fee schedule as other trades
Fire Alarm System Permit — fee basis not separately itemizedNot published as a distinct line item anywhere in City Code Chapter 16Unlike fire sprinklers (which get an explicit plan-review-ratio callout), no separate 'fire alarm permit fee' or plan-review ratio was found in Chapter 16, the live fee schedule, or the Zoning Regulations. Presumed billed under the same general valuation-based Building Permit Fee schedule as other electrical/trade work (consistent with how this file documents electrical, plumbing, and mechanical permits), but this is not independently confirmed by a fire-alarm-specific citation — flagged honestly rather than assumed
General Valuation-Based Building Permit Fee (applies to both sprinkler and alarm permits absent a dedicated line item)Same general schedule cited on this jurisdiction's other trade-permit entries (Chapter 16 / Resolution 16-2011)See the corpus-wide fee-schedule discrepancy flagged on this jurisdiction's Sign Permit entry (dated 2026-07-23) — a differently-formatted, more granular fee schedule is currently live on bensonaz.gov and should be reconciled against the Chapter 16 compilation across all trade-permit entries in this file

Occupancy Permit / Zoning Compliance Certificate (Change of Use)

Verified

Benson's local equivalent of a change-of-use / Certificate of Occupancy process, established in the City's Zoning Regulations, Section Twenty (Administration and Enforcement). A Zoning Compliance Certificate must be obtained from the Zoning Administrator before any change or extension of use of a lot, or any change in the use or occupancy type of a building or structure; an Occupancy Permit (or Temporary Occupancy Permit) is then issued by the Building Inspector following a final inspection confirming compliance. This is a genuinely distinct, separately named local process rather than a single 'change of use permit' product.

Verified 2026-07-23 · Source

Requirements

  • It is unlawful to commence excavation for, or the erection, alteration, enlargement, extension, or moving of, any building or structure, or to change/extend the use of any lot, or to change the use or type of occupancy of any building or structure, until a Zoning Compliance Certificate has been issued by the Zoning Administrator (Zoning Regulations, Section Twenty)
  • Application for a Zoning Compliance Certificate must be filed on standard forms, accompanied by duplicate scaled plans showing property dimensions/boundaries, existing building dimensions/uses, street/alley/easement widths and alignment, the size/height/position of buildings proposed to be erected or altered, and the proposed use(s) of buildings/structures/land including dwelling-unit counts
  • The Zoning Administrator must issue or refuse the Zoning Compliance Certificate within ten (10) days after filing; a refusal must be stated in writing with reasons, and copies of the marked/signed plans are retained by both the applicant and the Building Inspector
  • It is unlawful to use or occupy, or permit the use or occupancy of, any building or structure, or any changed/extended use of land, for which a Zoning Compliance Certificate has not been issued
  • Occupancy Permit: within ten (10) days after receiving notice that the building, structure, or premises (or part thereof) is complete and ready for use, the Building Inspector must perform a final inspection and issue the Occupancy Permit if construction conforms to the Zoning Regulations
  • A Temporary Occupancy Permit may be issued by the Building Inspector for a completed part of a building/structure/use prior to completion of the whole, provided that part is safe and suitable for use; it remains in force until the entire building/structure/use is completed, inspected, and a full Occupancy Permit is issued
  • An inspection fee must be paid to the City Clerk before a Zoning Compliance Certificate or Occupancy Permit is issued, per a fee schedule established by Council and posted in the office of the Building Inspector

Required documents

  • RequiredZoning Compliance Certificate ApplicationStandard form provided by the Zoning Administrator, accompanied by duplicate scaled plans (Zoning Regulations, Section Twenty); no standalone downloadable PDF version distinct from the Building/Commercial Development Application was found on the City's Document Center as of this review — apply through the Planning & Zoning or Building Department application channels and confirm the correct form with staff
  • OptionalOnline Building Permit Application (iWorQ Citizen Portal)Used where the occupancy/use change accompanies new construction, an addition, or a tenant improvement
  • RequiredA.R.S. Title 32 FormSigned form required with every building permit application

Fee schedule

Fee typeAmountNotes
Zoning Compliance Certificate / Occupancy Permit Inspection FeeNot published as a specific standalone dollar figureZoning Regulations, Section Twenty states only that the inspection fee 'shall be determined according to a schedule established by the Council, and posted in the office of the Building Inspector' — no such posted schedule was located online as of this review; omitted rather than invented, per corpus data-integrity policy
Residential Certificate of Occupancy / Housing Code Compliance Inspection$60.00 per dwelling unitCity Code of the City of Benson, Chapter 16 — already documented on this jurisdiction's Residential Building Permit entry; applies where the property being certified is a dwelling unit
Commercial Site Plan Review Fee (precedes/accompanies initial zoning compliance review for new commercial projects)$500 plus $50 per acreCity Code of the City of Benson, Chapter 16 — already documented in this jurisdiction's tipsAndGotchas; a standalone commercial change-of-use with no new site work was not found to have its own distinct fee beyond the general inspection-fee provision above

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Benson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-06)View current record →All versions →

Permalink: /arizona/cochise-county/benson/as-of/2026-07-07/

Snapshot date: 2026-07-07

Commit: 371a356

Reproducible from PermitBase’s version-controlled dataset, commit 371a356.