Murrieta building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Murrieta, California.
Verified 2026-09-20 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 1 Town Square, Murrieta, CA 92562
- Phone
- 951-461-6062 (Building & Safety); fax 951-698-4509; 951-304-2489 (City Hall)
- Office hours
- The division publishes "Phone Hours 8am-5pm" rather than counter hours, and City Hall hours are Monday through Friday 8 a.m. to 5 p.m. Permit status is checked by calling 951-461-6062 "between 8am-5pm or Email Building Permits". Note that submittal appointments are not a walk-up service - they are booked with the permit technician assigned to your project. The city also publishes its 2026 closure dates: 2/16, 5/25, 7/3, 9/7, 11/11, 11/26 and 11/28, 12/24 and 12/25, 12/31 and 1/1/2027.
- Website
- Official site
Published scheduling rules
- THE 4:00 PM CUT-OFF IS NEW AND DATED: "Effective January 1, 2026, inspection requests will be cut-off times at 4:00 PM each day." Anyone working from pre-2026 habits has lost the late-afternoon booking window, and the city spells out the consequence - a request after 4:00 PM "will not be scheduled for the following business day." (General)
- THE CITY PUBLISHES ITS 2026 CLOSURE DATES IN FULL - 2/16, 5/25, 7/3, 9/7, 11/11, 11/26 and 11/28, 12/24 and 12/25, 12/31 and 1/1/2027. Worth reading against the inspection cut-off, since a request on a non-working day does not buy the next business day. (General)
Inspection sequence
Applies to: Building Permit
- 1
Online only - the phone and counter routes were withdrawn
"All Inspection Requests must be submitted online; inspections are no longer scheduled over the phone or at the counter. Inspections will need to be scheduled through the Customer Self-Service Portal (CSS Portal)." A fallback exists: "If you are unable to submit your request for an inspection through the CSS Portal, fill out and submit the online Building Inspection Request form."
- 2
A 4:00 PM cut-off, introduced on a named date
"Effective January 1, 2026, inspection requests will be cut-off times at 4:00 PM each day. Please know that if requested after 4:00PM, or on a non-working day, inspections will not be scheduled for the following business day." Restated plainly elsewhere: "If you are requesting an inspection for the next business day, the request must be submitted no later than 4pm the previous day."
- 3
AM and PM windows, published on a daily run sheet
"Inspections are Monday - Friday 8:00 AM to 4:00 PM." The city publishes a run sheet - "To see if you have an Inspection today or to see what time your inspection is" - where "AM listed on the run sheet - inspections will be performed between 8:00 AM-12:00 PM" and "PM listed on the run sheet- inspections will be performed between 12:00 PM-4:00 PM."
- 4
Solar is always a morning job
"All Solar inspections will be conducted during the AM hours." Not a preference - a rule, and it removes the choice for photovoltaic work.
- 5
The time you ask for is only a request
Stated twice on the same page, in capitals: "REQUESTING AN AM OR PM TIME IS ONLY A REQUEST AND NOT GUARANTEED", and "the requested dates and times are NOT guaranteed."
- 6
Three failures on a residential job cost money
"On residential inspections only: 3 failed inspections or late same-day cancellations will result in a re-inspection fee." The rule is scoped to residential work, and a late same-day cancellation counts the same as a failure.
- 7
Booking is online but cancelling on the day is a phone call
"To cancel the inspection the day of call the Building Department (951) 461-6062." The portal takes the booking; the telephone takes the same-day cancellation - and cancelling late is itself one of the events that can trigger a re-inspection fee.
- 8
Paperwork closes before the final
"All final project documents must be submitted digitally before final inspections." The documents are a precondition of the final inspection, not something to hand over at it.
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-09-20.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Murrieta building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Murrieta building permits
Get alerts for Murrieta
We'll email you when Murrieta's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.