Inspection sequence, scheduling, and re-inspection fees for building permits in Murrieta, California.

Verified 2026-09-20 · Source

How to schedule

Inspections are requested through the building department below.

Address
1 Town Square, Murrieta, CA 92562
Phone
951-461-6062 (Building & Safety); fax 951-698-4509; 951-304-2489 (City Hall)
Office hours
The division publishes "Phone Hours 8am-5pm" rather than counter hours, and City Hall hours are Monday through Friday 8 a.m. to 5 p.m. Permit status is checked by calling 951-461-6062 "between 8am-5pm or Email Building Permits". Note that submittal appointments are not a walk-up service - they are booked with the permit technician assigned to your project. The city also publishes its 2026 closure dates: 2/16, 5/25, 7/3, 9/7, 11/11, 11/26 and 11/28, 12/24 and 12/25, 12/31 and 1/1/2027.

Published scheduling rules

  • THE 4:00 PM CUT-OFF IS NEW AND DATED: "Effective January 1, 2026, inspection requests will be cut-off times at 4:00 PM each day." Anyone working from pre-2026 habits has lost the late-afternoon booking window, and the city spells out the consequence - a request after 4:00 PM "will not be scheduled for the following business day." (General)
  • THE CITY PUBLISHES ITS 2026 CLOSURE DATES IN FULL - 2/16, 5/25, 7/3, 9/7, 11/11, 11/26 and 11/28, 12/24 and 12/25, 12/31 and 1/1/2027. Worth reading against the inspection cut-off, since a request on a non-working day does not buy the next business day. (General)

Inspection sequence

Applies to: Building Permit

  1. 1

    Online only - the phone and counter routes were withdrawn

    "All Inspection Requests must be submitted online; inspections are no longer scheduled over the phone or at the counter. Inspections will need to be scheduled through the Customer Self-Service Portal (CSS Portal)." A fallback exists: "If you are unable to submit your request for an inspection through the CSS Portal, fill out and submit the online Building Inspection Request form."

  2. 2

    A 4:00 PM cut-off, introduced on a named date

    "Effective January 1, 2026, inspection requests will be cut-off times at 4:00 PM each day. Please know that if requested after 4:00PM, or on a non-working day, inspections will not be scheduled for the following business day." Restated plainly elsewhere: "If you are requesting an inspection for the next business day, the request must be submitted no later than 4pm the previous day."

  3. 3

    AM and PM windows, published on a daily run sheet

    "Inspections are Monday - Friday 8:00 AM to 4:00 PM." The city publishes a run sheet - "To see if you have an Inspection today or to see what time your inspection is" - where "AM listed on the run sheet - inspections will be performed between 8:00 AM-12:00 PM" and "PM listed on the run sheet- inspections will be performed between 12:00 PM-4:00 PM."

  4. 4

    Solar is always a morning job

    "All Solar inspections will be conducted during the AM hours." Not a preference - a rule, and it removes the choice for photovoltaic work.

  5. 5

    The time you ask for is only a request

    Stated twice on the same page, in capitals: "REQUESTING AN AM OR PM TIME IS ONLY A REQUEST AND NOT GUARANTEED", and "the requested dates and times are NOT guaranteed."

  6. 6

    Three failures on a residential job cost money

    "On residential inspections only: 3 failed inspections or late same-day cancellations will result in a re-inspection fee." The rule is scoped to residential work, and a late same-day cancellation counts the same as a failure.

  7. 7

    Booking is online but cancelling on the day is a phone call

    "To cancel the inspection the day of call the Building Department (951) 461-6062." The portal takes the booking; the telephone takes the same-day cancellation - and cancelling late is itself one of the events that can trigger a re-inspection fee.

  8. 8

    Paperwork closes before the final

    "All final project documents must be submitted digitally before final inspections." The documents are a precondition of the final inspection, not something to hand over at it.

Re-inspection fees

Building PermitResidential re-inspection fee · "On residential inspections only: 3 failed inspections or late same-day cancellations will result in a re-inspection fee." The amount was not transcribed for this record.
Triggered by a third failure or by late same-day cancellations.

Murrieta building permits

Get alerts for Murrieta

We'll email you when Murrieta's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.