How to schedule
Inspections are requested through the building department below.
- Address
- Permit Center, Redding City Hall, 777 Cypress Avenue, 1st Floor, Redding, CA 96001 (mailing: City of Redding Permit Center, P.O. Box 496071, Redding, CA 96049-6071)
- Phone
- 530-225-4415 (Deputy Building Official); 530-510-6742 (Senior Building Inspector)
- Office hours
- THE COUNTER CLOSES BEFORE THE WORKING DAY DOES: Permit Center hours are "Monday-Friday 8 am-3 pm". Inspections run on a different and wider span - 7:00 AM to 3:00 PM - so inspectors are in the field an hour before the counter opens. Note that the two published direct numbers belong to named officers (a Deputy Building Official and a Senior Building Inspector); this record carries the roles and numbers rather than the individuals' names, because staff change and a name in a guide goes stale faster than a desk does.
- Website
- Official site
Published scheduling rules
- ANYONE WITH AN ACCOUNT CAN BOOK AN INSPECTION AGAINST YOUR PERMIT: "you do not need to be listed as a contact on the permit record to request an inspection." That is genuinely convenient on a multi-trade job where the electrician is not the permit holder - and it is worth knowing that the permit holder is not the only person who can move the schedule. (General)
- THE CITY IS HONEST THAT NEXT-DAY IS AN AIM, NOT A SERVICE LEVEL: "Inspection requests may be limited based on workload and staffing levels. Inspection capacity is generally set to accommodate next-day inspections whenever possible." Antioch withdrew its next-day guarantee on a named date; Redding never offered one and says why. (General)
Inspection sequence
Applies to: Building Permit
- 1
Inspections run earlier than the counter
"Building inspections are conducted Monday through Friday from 7:00 AM to 3:00 PM." The Permit Center itself opens at 8 am, so the first hour of the inspection day has no counter behind it.
- 2
No same-day requests, and next-day is an aim rather than a promise
"Same-day inspection requests are not accepted." On capacity the city is candid: "Inspection requests may be limited based on workload and staffing levels. Inspection capacity is generally set to accommodate next-day inspections whenever possible. Contractors should schedule inspections accordingly."
- 3
AM or PM is a preference only
"AM/PM inspection requests are noted as preferences only and cannot be guaranteed."
- 4
You do not have to be on the permit to book one
"An account is required to request inspections on our online portal. However, you do not need to be listed as a contact on the permit record to request an inspection." A subcontractor with their own account can book without being added to the record - unusual, and useful on a job with several trades.
- 5
Gate codes go in the request
The city's own step list ends: "Enter the requested inspection date and any comments or gate codes", then "Select 'Submit' to finalize the request. A confirmation email with a link to the inspection record will be sent within minutes." Cancelling follows the same path through the "Existing Inspections" table.
- 6
Somebody qualified, with the plans and the card
"Contractors are responsible for preparing the site for inspection. A qualified representative must be present on-site with approved plans and the permit/job card available for the inspector." Failing that, "Re-inspection fees may apply".
- 7
After-hours inspections need five working days' notice
"Requests for after-hours inspections must be submitted at least 5 working days before the requested inspection date", and they carry a 2-hour minimum charge. Anything beyond that minimum "must be submitted in writing."
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-09-20.
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Redding building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Redding building permits
Get alerts for Redding
We'll email you when Redding's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.