This is PermitBase’s published record for Vail as of 2026-08-02. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Vail building permits

Verified

Vail, Colorado — as published 2026-08-02.

Verified 2026-07-06 · Source

Codes adopted

2024 International Building Code (IBC) — Town of Vail Building Department page (Adopted Building Codes list)2024 International Residential Code (IRC)2024 International Fire Code (IFC)2024 International Plumbing Code (IPC)2024 International Mechanical Code (IMC)2024 International Fuel Gas Code (IFGC)2024 International Energy Conservation Code (IECC)2024 International Existing Building Code (IEBC)2023 National Electrical Code (NEC)Note on document currency: the Town's downloadable 'Minimum Project Submittal Requirements' packets (Residential and Commercial/Multi-Family, both undated on-page) still footer-reference the prior code cycle ('The current adopted codes in the Town of Vail are 2021 IBC, IRC, IMC, IPC, IFGC, IECC, IEBC, IFC, and 2020 NEC, as amended') — the live Building Department webpage's 2024 IBC/IRC/IFC/IPC/IMC/IFGC/IECC/IEBC + 2023 NEC list is treated as the current, governing adopted-code list for this file since it is the department's actively maintained code-adoption page, not a static PDF handout.

Permit types & fees

Residential Building Permit (New Construction)

Required for new construction of single-family homes, duplexes, and townhomes in the Town of Vail. Reviewed under the 2024 IRC/IBC (as locally adopted) plus the Town's published Climatic and Geographic Design Criteria (145 psf ground snow load, 115 mph wind design speed, 48-inch frost depth, 100% ice barrier underlayment). Issued by the Community Development Department, Building Division, after Design Review Board approval of any exterior design elements.

Reviewed 2026-08-02 · Source

Requirements

  • Design Review Board (DRB) approval required before building permit submittal for any exterior work/design elements
  • Plans must comply with the 2024 IRC/IBC as adopted, and must meet the Town's Climatic and Geographic Design Criteria: 145 psf ground snow load, 115 mph wind design speed (Seismic Design Category B), 48-inch minimum frost depth, 100% ice barrier underlayment required
  • All plans must be prepared by a Colorado Registered Design Professional, stamped/signed/dated; plans marked 'Not for Construction,' 'Conceptual,' or 'Preliminary' are rejected
  • Asbestos test report by a registered Colorado Asbestos inspector required at submittal for all projects, per State of Colorado asbestos regulations
  • Statement of Special Inspection required; special inspections (steel, concrete, masonry, soils, deep foundations/piles, seismic resistance, spray-applied fire-resistive materials, epoxy dowels) performed by a Town of Vail-approved 3rd-party inspector per IBC Chapter 17
  • Fire Sprinkler Retrofit Checklist required for all residential permits
  • All contractors must hold a current Town of Vail Contractor Registration (Vail Town Code 4-7-2) in addition to any required Colorado state trade license
  • Applications submitted via the Town's OpenGov online customer portal; electronic plan sets uploaded to ProjectDox after a completeness review

Required documents

  • RequiredBuilding Permit Application (Construction Permit — Building, Plumbing & Mechanical)Submitted through the Town of Vail OpenGov portal
  • RequiredMinimum Project Submittal Requirements — Residential PacketTitle page/code analysis, energy code compliance, survey/site plan, civil plan, soils report, foundation plan(s), structural calculations, floor/framing/roof plans, elevations, cross sections/details, schedules, electrical/mechanical/plumbing plans, statement of special inspection
  • RequiredAsbestos Test ReportBy a registered Colorado Asbestos inspector, required for all projects including shower/bath enclosures with new tile
  • RequiredDRB ApprovalRequired prior to building permit submittal for any exterior changes

Fee schedule

Fee typeAmountNotes
Building Permit Fee — valuation $1.00 to $500.00$50.002026 Schedule of Permit Fees, Town of Vail
Building Permit Fee — valuation $501.00 to $2,000.00$50.00 for the first $500 plus $3.05 for each additional $100 or fraction thereof, to and including $2,000.00
Building Permit Fee — valuation $2,001.00 to $25,000.00$95.75 for the first $2,000 plus $14.00 for each additional $1,000 or fraction thereof, to and including $25,000.00
Building Permit Fee — valuation $25,001.00 to $50,000.00$417.75 for the first $25,000 plus $10.10 for each additional $1,000 or fraction thereof, to and including $50,000.00
Building Permit Fee — valuation $50,001.00 to $100,000.00$670.25 for the first $50,000 plus $7.00 for each additional $1,000 or fraction thereof, to and including $100,000.00
Building Permit Fee — valuation $100,001.00 to $500,000.00$1,020.25 for the first $100,000 plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000.00
Building Permit Fee — valuation $500,001.00 to $1,000,000.00$3,620.25 for the first $500,000 plus $5.00 for each additional $1,000 or fraction thereof, to and including $1,000,000.00
Building Permit Fee — valuation $1,000,001.00 and up$6,120.25 for the first $1,000,000 plus $4.00 for each additional $1,000 or fraction thereof
Building Plan Review Fee65% of Building Permit Fee
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4%No use tax if total valuation is under $10,000.00
Recreation Fee (new square footage only)Varies by zone district, $0.10-$1.00 per sq ft addede.g. Single Family Residential $0.10/sq ft; Hillside Residential $0.15/sq ft; most commercial/mixed-use districts $1.00/sq ft
Transportation Impact Fee — new Single Family Dwelling$13,667 per new unit (1/1/2026 rate tier; phased increases through 1/1/2027)Resolution No. 27, Series 2025, Exhibit A
Will Call Inspection Fee$5.00 per work type (building, electrical, mechanical each billed separately)

Residential Addition / Interior Remodel Permit

Required for additions and interior remodels to existing single-family, duplex, and townhome structures in Vail. Reviewed under the 2024 IRC as locally adopted; scope and required documents differ meaningfully between an Addition and an Interior Remodel per the Town's own submittal matrix.

Reviewed 2026-08-02 · Source

Requirements

  • DRB approval required before building permit submittal if the project includes any exterior changes
  • Additions require: title page/code analysis, energy code compliance, survey/site plan, civil plan, soils report (open-hole report at excavation), foundation plan(s), structural calculations, floor/framing/roof plans, elevations, cross sections/details, schedules, electrical/mechanical/plumbing plans, statement of special inspection
  • Interior Remodels require a narrower document set: title page/code analysis, energy code compliance, floor plan(s), framing plan(s), structural calculations (only if walls are to be removed), electrical/mechanical/plumbing plans, statement of special inspection; survey/site plan, civil plan, soils report, and foundation plans are NOT required unless the scope triggers them
  • A Licensed Engineer report is required if any walls are proposed for removal, to determine if they are structural
  • Asbestos test report required at submittal for all projects, including shower/bath enclosures with new tile
  • All contractors must hold a current Town of Vail Contractor Registration

Required documents

  • RequiredBuilding Permit Application (Construction Permit)Submitted via the Town of Vail OpenGov portal
  • RequiredMinimum Project Submittal Requirements — Residential PacketApplicable columns for Addition or Interior Remodel scope
  • OptionalLicensed Engineer ReportRequired if the plans include removal of any walls, to determine if they are structural

Fee schedule

Fee typeAmountNotes
Building Permit Fee (same valuation-based schedule as new construction)$50.00 minimum, scaling per the valuation tiers in the 2026 Schedule of Permit FeesEffective per the 2026 fee schedule
Building Plan Review Fee65% of Building Permit Fee
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4% (no tax if valuation under $10,000)
Recreation Fee$0.10-$1.00 per sq ft, applies only to NEW square footage added by the additionNot applicable to interior remodels that add no new floor area

Electrical Permit

Required for installation, alteration, or repair of electrical systems in Vail. Governed by the 2023 NEC as adopted. Fees are set under a state-mandated schedule (CRS 12-23-117(3)) with the Town charging the maximum 15% surcharge allowed above the state base rate. Contractors must hold a Colorado Electrical Board (DORA) state license, verified contemporaneously by the Town, and a Town of Vail Contractor Registration (no fee for electrical contractors).

Reviewed 2026-08-02 · Source

Requirements

  • CRS 12-23-106 requires field verification of licensing and registration for all contractors performing electrical work
  • Governed by the 2023 NEC as adopted by the Town of Vail
  • Contractors must hold a current Colorado Electrical Board (DORA) license, contemporaneously verified by the Town per the Electrical Verification Policy, plus a Town of Vail Contractor Registration (no registration fee for Electrical contractors, unlike other trades)
  • Fee calculated under EITHER Section A (Residential, based on enclosed living area) OR Section B (All Other, based on installation valuation) — never both
  • Permit fees include two inspections only; additional inspections including re-inspections cost $105.00 each

Required documents

  • RequiredElectrical Permit ApplicationTown of Vail Electrical Permit Application, submitted via the OpenGov portal
  • RequiredTown of Vail Contractor RegistrationRequired for all contractors; no fee for Electrical contractors specifically

Fee schedule

Fee typeAmountNotes
Residential Electrical Fee — up to 1,000 sq ft living area$96.00 state fee, $110.40 total with 15% Town surcharge2026 Schedule of Permit Fees — Section A (Residential); per CRS 12-23-117(3)
Residential Electrical Fee — 1,001 to 1,500 sq ft$145.00 state fee, $166.75 total with 15% added
Residential Electrical Fee — 1,501 to 2,000 sq ft$194.00 state fee, $223.10 total with 15% added
Residential Electrical Fee — per 100 sq ft in excess of 2,000 sq ft$9.00 state fee, $10.35 total with 15% added
All Other Electrical Fee (Section B) — installation valuation not more than $2,000$96.00 state fee, $110.40 total with 15% addedApplies to non-living-area installations: garage, shop, photovoltaic, service connections, temporary meters, commercial
All Other Electrical Fee (Section B) — per $1,000 of valuation above $2,000$9.00 state fee, $10.35 total with 15% added
Electrical Plan Review Fee25% of the permit feeDistinct from the 65% rate used for Building/Plumbing/Mechanical
Additional/Re-inspection Fee$105.00 per inspectionPermit fee includes only two inspections
Will Call Fee$5.00 per electrical permit
Construction Use TaxSame formula as general Building schedule; applied only if electrical permit valuation exceeds $10,000

Plumbing Permit

Required for installation, alteration, or repair of plumbing systems in Vail, issued as part of the combined Construction Permit (Building, Plumbing & Mechanical). Governed by the 2024 International Plumbing Code (IPC) as adopted. Plumbing contractors must hold a Colorado Plumbing Board (DORA) license, contemporaneously verified by the Town, plus a Town of Vail Contractor Registration.

Reviewed 2026-08-02 · Source

Requirements

  • Issued under the Town's combined Construction Permit (Building, Plumbing & Mechanical) application
  • Governed by the 2024 IPC as adopted by the Town of Vail
  • Contractors must hold a current Colorado Plumbing Board (DORA) license, contemporaneously verified per the Town's Plumbing Verification Policy, plus a Town of Vail Contractor Registration ($67/year)
  • Plumbing plan(s) required as part of the Residential or Commercial/Multi-Family Minimum Project Submittal Requirements packet for New Construction, Addition, and Interior Remodel/Tenant Improvement scopes

Required documents

  • RequiredConstruction Permit Application (Building, Plumbing & Mechanical)Submitted via the Town of Vail OpenGov portal
  • RequiredTown of Vail Contractor RegistrationRequired in addition to Colorado DORA Plumbing license

Fee schedule

Fee typeAmountNotes
Plumbing Permit Fee (same valuation-based schedule as Building/Mechanical)$50.00 minimum, scaling per the valuation tiers in the 2026 Schedule of Permit Fees2026 Schedule of Permit Fees
Plumbing Plan Review Fee65% of Permit Fee
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4% (no tax if valuation under $10,000)
Will Call Fee$5.00 per work type

Mechanical / HVAC Permit

Required for heating, cooling, and ventilation equipment installation or replacement in Vail, issued as part of the combined Construction Permit (Building, Plumbing & Mechanical). Governed by the 2024 International Mechanical Code (IMC) and 2024 International Fuel Gas Code (IFGC) as adopted.

Reviewed 2026-08-02 · Source

Requirements

  • Issued under the Town's combined Construction Permit (Building, Plumbing & Mechanical) application
  • Governed by the 2024 IMC and 2024 IFGC as adopted by the Town of Vail
  • All contractors must hold a current Town of Vail Contractor Registration; applicable Colorado state trade licensure where required
  • Mechanical plan(s) required as part of the Minimum Project Submittal Requirements packet for New Construction, Addition, and Interior Remodel/Tenant Improvement scopes (not required for Deck/Balcony, Re-Roof, or Window Replacement scopes)

Required documents

  • RequiredConstruction Permit Application (Building, Plumbing & Mechanical)Submitted via the Town of Vail OpenGov portal
  • RequiredTown of Vail Contractor RegistrationRequired for all contractors performing mechanical work

Fee schedule

Fee typeAmountNotes
Mechanical Permit Fee (same valuation-based schedule as Building/Plumbing)$50.00 minimum, scaling per the valuation tiers in the 2026 Schedule of Permit Fees2026 Schedule of Permit Fees
Mechanical Plan Review Fee65% of Permit Fee
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4% (no tax if valuation under $10,000)
Will Call Fee$5.00 per work type

Roofing Permit (Re-Roof)

Required for re-roofing work in the Town of Vail. Single Family/Duplex re-roofs are eligible for the Town's 'Expedited Permit' track (combined DRB + Building Permit process). Governed by the 2024 IRC/IBC as adopted, with Class A material and 100% ice barrier underlayment requirements per the Town's Design Criteria.

Reviewed 2026-08-02 · Source

Requirements

  • Single Family/Duplex re-roofs qualify for the Expedited Permit track, which combines DRB and Building Permit approval into one process — all submittal requirements are due at time of application to use this track
  • DRB approval is still required before starting the permit process even under the expedited track, since re-roofing is exterior work
  • Per the Town's Design Criteria chart, ice barrier underlayment is required at 100% (not a minimum-elevation trigger)
  • Per the Residential/Commercial Minimum Project Submittal Requirements packets, a Re-Roof submittal requires: roof plan(s), and schedules showing Class A material, underlayment, valleys, and material — but does NOT require title page/code analysis, energy code compliance (only if no existing insulation), survey/site plan, civil plan, soils report, foundation plans, structural calculations, floor/framing plans, elevations, cross sections, electrical/mechanical/plumbing plans, or statement of special inspection

Required documents

  • RequiredConstruction Permit Application (Building, Plumbing & Mechanical) — Re-Roof scopeSubmitted via the Town of Vail OpenGov portal; DRB approval attached
  • RequiredRoof Plan(s) and Material ScheduleClass A roofing material, underlayment, valleys, and material specifications per the Minimum Project Submittal Requirements packet

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based, same schedule as new construction)$50.00 minimum, scaling per the valuation tiers in the 2026 Schedule of Permit FeesNo separate flat re-roof fee is published; billed under the general valuation-based Building Permit Fee schedule
Building Plan Review Fee65% of Permit Fee
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4% (no tax if valuation under $10,000)

Solar Thermal / Photovoltaic Permit

Required for solar thermal and photovoltaic system installations in Vail. Explicitly listed as an 'Expedited Permit' category (combined DRB + Building Permit process) alongside re-roofs and water heater replacement. Electrical portions governed by the 2023 NEC as adopted; PV installation fees follow the general Section B (All Other) electrical fee schedule.

Reviewed 2026-08-02 · Source

Requirements

  • Listed under the Town's Expedited Permits category, combining DRB and Building Permit approval; all submittal requirements due at time of application
  • DRB approval required before starting the permit process, since solar installations are exterior work
  • Electrical work governed by the 2023 NEC as adopted
  • Photovoltaic installation valuation billed under Section B (All Other Fees) of the Electrical Permit fee schedule — based on total installation cost (labor + materials), not square footage
  • All contractors must hold a current Town of Vail Contractor Registration plus any required Colorado state trade license

Required documents

  • RequiredConstruction Permit / Electrical Permit Application — Solar Thermal/Photovoltaic scopeSubmitted via the Town of Vail OpenGov portal; DRB approval attached

Fee schedule

Fee typeAmountNotes
Electrical Fee (Section B, All Other) — installation valuation not more than $2,000$96.00 state fee, $110.40 total with 15% Town surcharge added2026 Schedule of Permit Fees — Section B explicitly names photovoltaic as an example of this category
Electrical Fee (Section B) — per $1,000 of valuation above $2,000$9.00 state fee, $10.35 total with 15% added
Electrical Plan Review Fee25% of the permit fee
Construction Use TaxApplied only if valuation exceeds $10,000, using the standard formula

Electric Vehicle (EV) Charging Station / EVSE Permit

The Town of Vail has no distinct EV charger/EVSE permit application or fee line. An EV charging station installation is permitted as ordinary electrical work through the Town's existing Electrical Permit, billed under Section B ('All Other' electrical fee, based on installation valuation) of the 2026 Schedule of Permit Fees -- the same category the Town's own fee schedule uses for garage, shop, photovoltaic, service-connection, temporary-meter, and commercial electrical work that is not enclosed-living-area wiring. Governed by the 2023 NEC as adopted by the Town, which includes Article 625 (Electric Vehicle Power Transfer System) provisions. Vail's population (~5,300) is well below the 10,000-person threshold that triggers 'covered municipality' status under Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act, effective 8/7/2024), so that statute's mandatory model-code/objective-standards adoption and 3-business-day decision-notification requirement do not apply here.

Reviewed 2026-08-02 · Source

Requirements

  • No standalone EV charger/EVSE permit application exists; apply for the Town's standard Electrical Permit via the OpenGov portal
  • CRS 12-23-106 requires field verification of licensing and registration for all contractors performing electrical work, including EVSE installation
  • Fee calculated under Section B ('All Other,' based on installation valuation) of the 2026 Schedule of Permit Fees -- the same category used for photovoltaic, garage/shop, service-connection, and commercial electrical work, since an EV charger circuit is not enclosed-living-area wiring
  • Contractors must hold a current Colorado Electrical Board (DORA) license, contemporaneously verified by the Town, plus a Town of Vail Contractor Registration (no registration fee for Electrical contractors)
  • Governed by the 2023 NEC as adopted by the Town of Vail, which includes Article 625 (Electric Vehicle Power Transfer System) requirements for EVSE branch circuits and disconnects
  • Vail's population is below the 10,000-person threshold for 'covered municipality' status under Colorado HB24-1173, so the Act's mandatory EV-permitting-standards adoption and 3-business-day decision timeline do not apply as a legal requirement here

Required documents

  • RequiredElectrical Permit ApplicationTown of Vail Electrical Permit Application, submitted via the OpenGov portal; same application used for all electrical work including EV charger circuits
  • RequiredTown of Vail Contractor RegistrationRequired for all contractors; no fee for Electrical contractors specifically

Fee schedule

Fee typeAmountNotes
All Other Electrical Fee (Section B) — installation valuation not more than $2,000 (EV charger/EVSE circuit)$96.00 state fee, $110.40 total with 15% Town surcharge2026 Schedule of Permit Fees — Section B applies to non-living-area installations including photovoltaic, garage, shop, service connections, temporary meters, and commercial work; no distinct EV-charger line exists so this is the governing category
All Other Electrical Fee (Section B) — per $1,000 of valuation above $2,000$9.00 state fee, $10.35 total with 15% added
Electrical Plan Review Fee25% of the permit feeDistinct from the 65% rate used for Building/Plumbing/Mechanical
Additional/Re-inspection Fee$105.00 per inspectionPermit fee includes only two inspections

Commercial Building Permit (New Construction)

Required for new construction of commercial buildings (retail, restaurant, office, hotel/lodge, mixed-use) in the Town of Vail, applied for under the same combined 'Construction Permit' (Building, Plumbing & Mechanical) application used for all trades but reviewed against a genuinely distinct, heavier document set published in the Town's own 'Minimum Project Submittal Requirements — Commercial and Multi-Family' packet (New Commercial/Multi-Family column), which requires the full plan set (survey, civil, soils, foundation, structural, floor/framing/reflected-ceiling/roof plans, elevations, cross sections, schedules, MEP plans, statement of special inspection, energy code compliance details) with no scope-based exceptions. Reviewed under the 2024 IBC (as locally adopted). Issued by the Community Development Department, Building Division, after Design Review Board approval of exterior design elements.

Reviewed 2026-08-02 · Source

Requirements

  • Design Review Board (DRB) approval required before building permit submittal for any exterior work/design elements
  • Plans reviewed under the 2024 IBC as adopted, plus the Town's Climatic and Geographic Design Criteria chart (145 psf ground snow load, 115 mph wind design speed, Seismic Design Category B, 48-inch frost depth, 100% ice barrier underlayment)
  • Per the Commercial/Multi-Family Minimum Project Submittal Requirements matrix (New Commercial/Multi-Family column), ALL of the following are required with no scope exceptions: Title Page/Code Analysis, Survey/Site Plan, Civil Plan, Soils Report (prepared by a Town of Vail-approved 3rd-party Special Inspector), Foundation Plan(s), Structural Calculations, Floor Plan(s), Framing Plan(s), Reflected Ceiling Plan(s), Roof Plan(s), Elevations, Cross Sections/Details, Schedules, Electrical Plan(s), Mechanical Plan(s), Plumbing Plan(s), Statement of Special Inspection, and Energy Code Compliance Details
  • Title Page/Code Analysis must include Building Code Analysis (code(s) utilized, occupancy classification, type of construction, location on property, allowable floor area, height/stories, mixed-occupancy compliance method) and a Code Compliance Plan (occupant loads, means-of-egress design, path-of-travel measurements, plumbing fixture count, fire-resistive rated construction designation, suppression/alarm system)
  • All plans must be prepared by a Colorado Registered Design Professional, stamped/signed/dated (plans marked 'Not for Construction,' 'Conceptual,' or 'Preliminary' are rejected)
  • Asbestos test report by a registered Colorado Asbestos inspector required at submittal, per State of Colorado asbestos regulations
  • Statement of Special Inspection required; special inspections (steel/welds/high-strength bolting, concrete, masonry, soils, driven deep foundations/piles, seismic resistance, spray-applied fire-resistive materials, epoxy dowels) performed by a Town of Vail-approved 3rd-party inspector per IBC Chapter 17
  • COMcheck report recommended for Energy Code Compliance Details (insulation R-values, fenestration U-factors/SHGC, area-weighted U-factor calculations, mechanical/service water heating equipment, duct sealing, air sealing, building thermal envelope)
  • All contractors must hold a current Town of Vail Contractor Registration (Vail Town Code 4-7-2) in addition to any required Colorado state trade license
  • Minimum 2 paper plan sets if submitting paper (11x17 minimum, 24x36 recommended); electronic plan sets uploaded to ProjectDox after a completeness review
  • Applications submitted via the Town's OpenGov online customer portal — there is no separate 'commercial' application form; the same Construction Permit application is used for residential and commercial work, with the commercial document set governing what must be submitted

Required documents

  • RequiredConstruction Permit Application (Building, Plumbing & Mechanical)Submitted through the Town of Vail OpenGov portal; same application form used for residential and commercial work
  • RequiredMinimum Project Submittal Requirements — Commercial and Multi-Family Packet (New Commercial/Multi-Family column)Title page/code analysis, survey/site plan, civil plan, soils report, foundation plan(s), structural calculations, floor/framing/reflected ceiling/roof plans, elevations, cross sections/details, schedules, electrical/mechanical/plumbing plans, statement of special inspection, energy code compliance details
  • RequiredAsbestos Test ReportBy a registered Colorado Asbestos inspector, required for all projects
  • RequiredDRB ApprovalRequired prior to building permit submittal for any exterior changes

Fee schedule

Fee typeAmountNotes
Building Permit Fee (same shared valuation-based schedule used for Building/Plumbing/Mechanical on all project types)$50.00 minimum for $1-$500 valuation, scaling through $6,120.25 for the first $1,000,000 plus $4.00/$1,000 thereafter for $1,000,001+2026 Schedule of Permit Fees, Town of Vail — identical fee table to residential-building-permit; verified directly from the fee-schedule PDF
Building Plan Review Fee65% of Building Permit FeeDue at submittal per the fee schedule's instructions
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4%No use tax if total valuation is under $10,000.00
Recreation Fee (new square footage only) — commercial core/mixed-use zone districts$1.00 per sq ft in Commercial Core 1/2/3 (CC1/CC2/CC3), Lionshead Mixed Use 1/2 (LMU1/LMU2), Public Accommodation (PA), Arterial Business District (ABD), Commercial Service Center (CSC), Heavy Service (HS), Vail Village Townhouse (VVT), and High Density Multi-Family (HDMF); $0.70/sq ft in Ski Base/Recreation District (SB/RD)Town of Vail 2026 Schedule of Permit Fees, Recreation Fees table — full zone-district table read directly from the fee-schedule PDF
Transportation Impact Fee — Accommodation Unit (per new unit, e.g. hotel/lodge room)In Core Area: $8,410 (1/1/2026 tier) — tier schedule $5,066 (1/1/2017) / $6,738 (6/9/2025) / $8,410 (1/1/2026) / $10,132 (1/1/2027); Outside Core Area: $6,333 / $8,422 / $10,512 / $12,665 across the same four tiersResolution No. 27, Series 2025, Exhibit A — Core Area defined per Figure 1 of the Vail Transportation Impact Fee Study
Transportation Impact Fee — Facilities/Health Care (per net-new sq ft of floor area)$8.44 (1/1/2017 tier) / $11.23 (6/9/2025 tier) / $14.01 (1/1/2026 tier) / $16.88 (1/1/2027 tier)
RESOLVED 2026-08-02: read directly from Resolution No. Show full citation

RESOLVED 2026-08-02: read directly from Resolution No. 27, Series 2025, Exhibit A (the actual phased fee-schedule table adopted by the Town Council 6/3/2025, Consent Agenda), not the general 2026 Schedule of Permit Fees worksheet PDF, whose Transportation Impact Fee section is a blank fill-in-the-dollar-amount table with no embedded figures — that blank-worksheet layout, not a text-extraction failure, is why these figures were previously unconfirmed. Source: https://legistarweb-production.s3.amazonaws.com/uploads/attachment/pdf/3390102/Resolution_27-2025_Exhibit_A_Fee_Schedule-Phased.pdf. For a permit issued after 1/1/2026, the $14.01/sq ft tier applies.

Transportation Impact Fee — Office & Other Services (per net-new sq ft of floor area)$5.27 (1/1/2017 tier) / $7.01 (6/9/2025 tier) / $8.75 (1/1/2026 tier) / $10.54 (1/1/2027 tier)RESOLVED 2026-08-02: Resolution No. 27, Series 2025, Exhibit A. For a permit issued after 1/1/2026, the $8.75/sq ft tier applies.
Transportation Impact Fee — Restaurant & Retail Establishments (per net-new sq ft of floor area)$11.82 (1/1/2017 tier) / $15.71 (6/9/2025 tier) / $19.61 (1/1/2026 tier) / $23.63 (1/1/2027 tier)
RESOLVED 2026-08-02: Resolution No. 27, Series 2025, Exhibit A. Show full citation

RESOLVED 2026-08-02: Resolution No. 27, Series 2025, Exhibit A. For a permit issued after 1/1/2026, the $19.61/sq ft tier applies. Fee schedule rates are stated as equivalent to $19,040 per net-new PM-peak-hour vehicular trip; Core Area is defined per Figure 1 of the Vail Transportation Impact Fee Study.

Will Call Inspection Fee$5.00 per work type (building, electrical, mechanical each billed separately)
Revisions$75.00/hour, 2-hour minimum
Re-inspections / after-hours inspections$105.00 per inspection/hour, 2-hour minimum for after-hours

Commercial Remodel / Tenant Improvement / Addition Permit

Required for tenant improvements (interior build-out of existing commercial space), commercial remodels, and commercial additions in the Town of Vail. The Town's own Minimum Project Submittal Requirements — Commercial and Multi-Family packet bundles these three scopes ('Commercial Remodel/TI/Addition') into a single document-requirement column, distinct from New Commercial/Multi-Family construction; the Title Page/Code Analysis instructions explicitly list 'Alteration/Renovation/Tenant Improvement' as one of three recognized 'type of work' designations alongside New Building and Building Addition. Applied for under the same combined Construction Permit application used for all Building/Plumbing/Mechanical work. Reviewed under the 2024 IBC as adopted.

Reviewed 2026-08-02 · Source

Requirements

  • Design Review Board (DRB) approval required before building permit submittal ONLY if the project includes exterior changes — the Commercial packet lists Elevations as 'Only if exterior changes' for this scope, unlike New Commercial/Multi-Family construction which always requires them
  • Per the Commercial/Multi-Family Minimum Project Submittal Requirements matrix (Commercial Remodel/TI/Addition column): Title Page/Code Analysis, Survey/Site Plan, Civil Plan, Structural Calculations, Floor Plan(s), Framing Plan(s), Reflected Ceiling Plan(s), Cross Sections/Details, Schedules, Electrical/Mechanical/Plumbing Plan(s), Statement of Special Inspection, and Energy Code Compliance Details are required
  • Soils Report and Foundation Plan(s) are required only 'if addition' (open-hole report at excavation for soils); Roof Plan(s) required only 'if addition'; Elevations required only if the project includes exterior changes — a pure interior tenant improvement with no addition and no exterior changes does not trigger these four items
  • EXCEPTION: tenant finishes and remodels that do NOT affect fire-resistive rated construction, structural items, means-of-egress components, plumbing systems, and/or electrical systems are NOT required to have stamped professional drawings (all other commercial/multi-family work requires drawings stamped, signed, and dated by a Colorado-licensed design professional)
  • A Licensed Engineer report is required if any walls are proposed for removal, to determine if they are structural
  • Asbestos test report by a registered Colorado Asbestos inspector required at submittal for all projects, per State of Colorado asbestos regulations
  • Statement of Special Inspection required per IBC Chapter 17, performed by a Town of Vail-approved 3rd-party Special Inspector
  • All contractors must hold a current Town of Vail Contractor Registration in addition to any required Colorado state trade license
  • Minimum 2 paper plan sets if submitting paper (11x17 minimum, 24x36 recommended); electronic plan sets uploaded to ProjectDox after a completeness review

Required documents

  • RequiredConstruction Permit Application (Building, Plumbing & Mechanical)Submitted via the Town of Vail OpenGov portal; same application form used for New Commercial/Multi-Family, residential, and TI/remodel/addition work
  • RequiredMinimum Project Submittal Requirements — Commercial and Multi-Family Packet (Commercial Remodel/TI/Addition column)Title page marked 'Alteration/Renovation/Tenant Improvement'; floor/framing/reflected ceiling plans, structural calculations, schedules, MEP plans, statement of special inspection, energy code compliance details; survey/civil/soils/foundation/roof/elevations only if the specific project includes an addition or exterior changes
  • OptionalLicensed Engineer ReportRequired if the plans include removal of any walls, to determine if they are structural
  • RequiredAsbestos Test ReportBy a registered Colorado Asbestos inspector, required for all projects

Fee schedule

Fee typeAmountNotes
Building Permit Fee (same shared valuation-based schedule used for Building/Plumbing/Mechanical on all project types)$50.00 minimum for $1-$500 valuation, scaling through $6,120.25 for the first $1,000,000 plus $4.00/$1,000 thereafter for $1,000,001+2026 Schedule of Permit Fees, Town of Vail — identical fee table to residential and new commercial construction; verified directly from the fee-schedule PDF
Building Plan Review Fee65% of Building Permit FeeDue at submittal
Construction Use Tax(Valuation minus $10,000) / 2, multiplied by 4%No use tax if total valuation is under $10,000.00
Recreation Fee — commercial core/mixed-use zone districts$1.00 per sq ft of NEW floor area in most commercial/mixed-use zone districts (CC1/CC2/CC3, LMU1/LMU2, PA, ABD, CSC, HS, VVT, HDMF); $0.70/sq ft in SB/RDApplies only if the TI/remodel/addition adds new floor area; a pure interior tenant improvement that adds no square footage is not billed this fee, per the Town's fee-calculation instructions ('building permits adding new square footage only')
Transportation Impact Fee — Facilities/Health Care (per net-new sq ft of floor area)$8.44 (1/1/2017 tier) / $11.23 (6/9/2025 tier) / $14.01 (1/1/2026 tier) / $16.88 (1/1/2027 tier)
RESOLVED 2026-08-02: read directly from Resolution No. Show full citation

RESOLVED 2026-08-02: read directly from Resolution No. 27, Series 2025, Exhibit A — https://legistarweb-production.s3.amazonaws.com/uploads/attachment/pdf/3390102/Resolution_27-2025_Exhibit_A_Fee_Schedule-Phased.pdf. Applies only if the TI/remodel/addition adds net-new enclosed floor area; a pure interior TI adding no floor area is not billed this fee. For a permit issued after 1/1/2026, the $14.01/sq ft tier applies.

Transportation Impact Fee — Office & Other Services (per net-new sq ft of floor area)$5.27 (1/1/2017 tier) / $7.01 (6/9/2025 tier) / $8.75 (1/1/2026 tier) / $10.54 (1/1/2027 tier)RESOLVED 2026-08-02: Resolution No. 27, Series 2025, Exhibit A. Applies only if net-new floor area is added. For a permit issued after 1/1/2026, the $8.75/sq ft tier applies.
Transportation Impact Fee — Restaurant & Retail Establishments (per net-new sq ft of floor area)$11.82 (1/1/2017 tier) / $15.71 (6/9/2025 tier) / $19.61 (1/1/2026 tier) / $23.63 (1/1/2027 tier)RESOLVED 2026-08-02: Resolution No. 27, Series 2025, Exhibit A. Applies only if net-new floor area is added. For a permit issued after 1/1/2026, the $19.61/sq ft tier applies.
Will Call Inspection Fee$5.00 per work type
Revisions$75.00/hour, 2-hour minimum

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Vail building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-20)Later version (2026-08-14) →View current record →All versions →

Permalink: /colorado/eagle-county/vail/as-of/2026-08-02/

Snapshot date: 2026-08-02

Commit: 66a0895

Reproducible from PermitBase’s version-controlled dataset, commit 66a0895.