You are viewing the permanent link for the record currently in effect, published 2026-07-07.
Golden building permits
VerifiedGolden, Colorado — as published 2026-07-07.
Verified 2026-07-05 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for construction of new single-family homes and other one- and two-family dwellings within the City of Golden. Reviewed under the 2024 IRC/IBC (as locally amended) plus Golden's own Structural Design Criteria (snow, wind, frost depth) and, if the property is within a designated Wildland-Urban Interface area, the Golden Wildfire Resiliency Code (GWRC). Issued and inspected by the City of Golden Building Department.
Verified 2026-07-05 · Source
Requirements
- Plans must comply with the 2024 IRC/IBC as adopted, including Appendix BE (Radon Control) and Appendix CD (Piping Standards)
- Must meet Golden's Structural Design Criteria: Ground Snow Load Pg 69/76/83 psf by Risk Category II/III/IV, minimum 30 psf flat roof snow load, Wind Load Vult 150/157/164 mph by Risk Category (Exposure C), and 36-inch minimum frost depth
- If the property is within Golden's designated Wildland-Urban Interface (WUI) area (see the Official Golden Wildfire Map), the project must also comply with the Golden Wildfire Resiliency Code (GWRC, Ordinance 2290 / Municipal Code Chapter 15.80), which sets fire-resistant construction standards for Class I (low fire intensity) or Class II (medium/high fire intensity) hazard areas; enforcement begins June 10, 2026
- Valuation = cost of labor and materials; for owner-performed work, valuation is calculated as materials cost times two
- All contractors working on the project must hold a current City of Golden Contractor License (Chapter 15.01) in addition to any required state license, and must be identified on the permit before issuance
- Applications, contractor licensing, and inspection requests are submitted via the City's Accela-based Online Permitting Portal
Required documents
- RequiredBuilding Permit Application (Online Permitting Portal)Submitted through the City's Accela Citizen Access portal
- RequiredConstruction DrawingsFull plan set reflecting Golden's Structural Design Criteria (snow, wind, frost depth) and, if applicable, GWRC hazard-classification requirements
- RequiredSite PlanProperty lines, setbacks, and all existing/proposed structures
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — valuation $1.00 to $500.00 | $25.85 | Building Permit Fee Table, Effective 05/01/11, adopted by City Council Resolution #1097 as modified by Resolution #1648 and #2121 — the City's current published fee schedule as of this review |
| Building Permit Fee — valuation $501.00 to $2,000.00 | $25.85 for the first $500.00 plus $3.36 for each additional $100.00 or fraction thereof, to and including $2,000.00 | — |
| Building Permit Fee — valuation $2,001.00 to $25,000.00 | $76.18 for the first $2,000.00 plus $15.40 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | — |
| Building Permit Fee — valuation $25,001.00 to $50,000.00 | $430.38 for the first $25,000.00 plus $11.11 for each additional $1,000.00 or fraction thereof, to and including $50,000.00 | — |
| Building Permit Fee — valuation $50,001.00 to $100,000.00 | $708.13 for the first $50,000.00 plus $7.70 for each additional $1,000.00 or fraction thereof, to and including $100,000.00 | — |
| Building Permit Fee — valuation $100,001.00 to $500,000.00 | $1,093.13 for the first $100,000.00 plus $6.16 for each additional $1,000.00 or fraction thereof, to and including $500,000.00 | — |
| Building Permit Fee — valuation $500,001.00 to $1,000,000.00 | $3,557.13 for the first $500,000.00 plus $5.23 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00 | — |
| Building Permit Fee — valuation $1,000,001.00 and up | $6,169.63 for the first $1,000,000.00 plus $4.02 for each additional $1,000.00 or fraction thereof | — |
| Plan Review Fee | 65% of the Permit Fee | When a sub-permit (electrical/mechanical/plumbing) is associated with a valid Building Permit and its valuation is included in the total building permit valuation, no separate sub-permit plan review fee is charged |
| Building Use Tax | 3% of building materials valuation (estimated at 1.5% of total project valuation for calculation purposes) | Prepaid as part of the building permit fee at issuance; see City of Golden Taxes & Fees page |
Residential Addition / Remodel Permit
VerifiedRequired for room additions, patio enclosures, screened porches, basement finishes, and structural modifications to existing one- and two-family dwellings in Golden. Reviewed under the 2024 IRC as locally amended, plus Golden's Structural Design Criteria and, if within the WUI map, the Golden Wildfire Resiliency Code for significant additions/remodels.
Verified 2026-07-05 · Source
Requirements
- Permit required for: Room Additions, Patio Enclosures, Screened Porches; Basement Finishes; Structural Modifications; Decks 30 inches or more above lowest grade within 6 ft of the deck edge, or decks exceeding 200 sq ft regardless of height
- Decks NOT exceeding 200 sq ft in area, not more than 30 inches above grade at any point, and not located in a Historic District generally do not require a permit (verify against current setback rules)
- Golden Wildfire Resiliency Code (GWRC) applies to 'significant additions, repairs, and remodels' within designated WUI areas — check the Official Golden Wildfire Map before scoping the project
- Valuation = labor + materials cost (materials x2 for owner-performed work)
- All contractors must hold a current City of Golden Contractor License and be listed on the permit
Required documents
- RequiredBuilding Permit Application (Online Permitting Portal)Submitted via Accela Citizen Access; select the appropriate residential alteration/addition project type
- RequiredConstruction DrawingsPlans showing the addition/remodel scope, structural connections to the existing structure, and design-criteria compliance
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (same valuation-based Fee Table as new construction) | $25.85 minimum, scaling per the valuation tiers in the Building Permit Fee Table | Effective 05/01/11, Resolution #1097/#1648/#2121 |
| Plan Review Fee | 65% of the Permit Fee | Waived separately for sub-permits (electrical/mechanical/plumbing) whose valuation is already included in the building permit valuation |
| Building Use Tax | 3% of building materials valuation (est. 1.5% of total project valuation) | — |
Electrical Permit
VerifiedRequired for installation, alteration, or repair of electrical systems in Golden. Governed by the 2023 NEC as adopted, with 2024 IBC Appendix K (Administrative Provisions for the NEC). Electrical contractors must hold a Colorado Electrical Board (DORA) state license AND a separate City of Golden Contractor License.
Verified 2026-07-05 · Source
Requirements
- Permit required for any electrical work: installing, altering, or fixing electrical systems, per the Required Building Permits Guide
- Contractors must hold a current Colorado Electrical Board (DORA) license AND a City of Golden Contractor License (Municipal Code Chapter 15.01) with its own annual registration fee
- All contractors must be identified on the permit before issuance
- Governed by the 2023 NEC plus 2024 IBC Appendix K administrative provisions
Required documents
- RequiredElectrical Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the electrical permit type
- RequiredCity of Golden Contractor LicenseRequired registration under Municipal Code Chapter 15.01, separate from the state DORA electrical license
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee — when NOT attached to a valid Building Permit | Calculated per the Building Permit Fee Table valuation tiers ($25.85 minimum) | Building Permit Fee Table, Effective 05/01/11 |
| Plan Review Fee | Waived when the sub-permit is attached to a valid Building Permit and its valuation is included in the total building permit valuation; otherwise 65% of the permit fee | Building Permit Fee Table footnote ** |
| Reinspection Fee | $50.00 | — |
Plumbing Permit
VerifiedRequired for installation, alteration, or repair of plumbing systems in Golden. Governed by the 2024 International Plumbing Code (IPC) plus Appendix CD (Piping Standards for Various Applications). Plumbing contractors must hold a Colorado Plumbing Board (DORA) state license AND a separate City of Golden Contractor License.
Verified 2026-07-05 · Source
Requirements
- Permit required for plumbing installation, alteration, or repair, including water heater installation/replacement (listed separately under Interior Projects in the Required Building Permits Guide) and gas piping
- Golden uses the IPC, not the Uniform Plumbing Code (UPC)
- Contractors must hold a current Colorado Plumbing Board (DORA) license AND a City of Golden Contractor License
- Lawn Sprinkler connection to the water supply (backflow) requires a permit, per the Required Building Permits Guide
Required documents
- RequiredPlumbing Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the plumbing permit type
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee — when NOT attached to a valid Building Permit | Calculated per the Building Permit Fee Table valuation tiers ($25.85 minimum) | Building Permit Fee Table, Effective 05/01/11 |
| Plan Review Fee | 65% of the permit fee (waived if attached to a valid Building Permit with valuation already included) | — |
Mechanical / HVAC Permit
VerifiedRequired for heating, cooling, ventilation, and fuel-gas equipment installation or replacement in Golden. Governed by the 2024 International Mechanical Code (IMC) as locally adopted.
Verified 2026-07-05 · Source
Requirements
- Permit required for: Air Conditioning Units, Attic Fans (whole house), Boiler Installation or Replacement, Furnace Installation or Replacement, Gas Logs Installation or Replacement, Swamp Coolers, Water Heater Installation or Replacement — per the Required Building Permits Guide
- Governed by the 2024 IMC as adopted by the City
- Contractors must hold applicable state licensure (where required) plus a City of Golden Contractor License
Required documents
- RequiredMechanical Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the mechanical permit type
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee — when NOT attached to a valid Building Permit | Calculated per the Building Permit Fee Table valuation tiers ($25.85 minimum) | Building Permit Fee Table, Effective 05/01/11 |
| Plan Review Fee | 65% of the permit fee (waived if attached to a valid Building Permit with valuation already included) | — |
Roofing Permit (Reroof)
VerifiedRequired for roofing and re-roofing work on residential and commercial buildings in Golden, unless the work is a minor repair/replacement of 10% or less. Governed by 2024 IRC/IBC local roofing amendments, with detailed local rules on ice barrier, overlay limits, fire rating, and mid-roof inspection.
Verified 2026-07-05 · Source
Requirements
- Permit required for Roofing/Re-Roofing (exterior projects list, Required Building Permits Guide); Minor Roof or Siding Repairs or replacement of 10% or less do NOT require a permit
- If a repair exceeds 25% of the total roof area, the ENTIRE roof must be replaced (not just the damaged section) — IEBC 2021/2024 Section 1501.2.1 per the City's roofing rules
- Reroofing must include removal of ALL existing layers of roof covering down to the roof deck — IRC 2024 R908.3 / IBC 2024 1512.2
- Only one overlay is allowed on existing asphalt or wood shingles; T-Lock shingles cannot be overlaid at all
- Ice barrier required for ALL new and re-roofing applications (not a minimum-elevation trigger) — must extend from the lowest roof edge to at least 24 inches inside the exterior wall line, per IRC 2024 R905.1.2 / IBC 2024 (equivalent section)
- Wood shakes and shingles must meet minimum Class A fire rating; all other roofing materials must meet at least Class C fire rating
- Roof and attic ventilation must comply with IRC Section R806 and manufacturer guidelines
- Commercial ballasted roofs must undergo an engineering evaluation for load capacity; structural roof components must meet IEBC 2021 Section 1501.2.1 standards
- Mid-roof inspection required when 25% to 65% of new roof covering has been installed; a ladder must be secured and extended to at least 3 feet above the roofline for inspector access — failure to provide access may trigger reinspection fees
Required documents
- RequiredRoofing Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the roofing/reroof permit type
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee — valuation-based (Building Permit Fee Table) | $25.85 minimum, scaling per valuation tiers | Building Permit Fee Table, Effective 05/01/11 |
| Reinspection Fee | $50.00 | Applies if a required inspection (e.g., mid-roof) cannot be completed due to inadequate access |
Solar PV Permit
VerifiedRequired for installation of solar panel systems in Golden. The City holds a Silver SolSmart designation for streamlined solar permitting, but does not publish solar-specific fees, forms, or a dedicated review timeline separate from the general Building Permit Process — solar follows the standard building/electrical permit path.
Verified 2026-07-05 · Source
Requirements
- Solar Panels are listed as requiring a permit under the Required Building Permits Guide's exterior projects list
- No solar-specific application, checklist, or fee schedule is published on the City's Solar Energy Systems page; applicants are directed to the general Building Permit Process page
- Follow standard building-permit valuation and, where applicable, electrical-permit requirements (state DORA electrical license plus City of Golden Contractor License)
Required documents
- RequiredBuilding/Electrical Permit Application (Online Permitting Portal)Apply via Accela Citizen Access; no separate solar-specific application form is published
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee — valuation-based (Building Permit Fee Table) | $25.85 minimum, scaling per valuation tiers | No solar-specific flat fee is published; solar systems are billed under the same Building Permit Fee Table as other valuation-based work |
EV Charger / Electric Vehicle Charging Station Permit
VerifiedInstalling a Level 2 (240V) home or commercial EV charging circuit in Golden requires a City of Golden Electrical Permit -- confirmed via the City's own Required Building Permits Guide, which lists 'Electrical Modifications' among Interior Projects that require a permit. Like solar PV, there is no EV-specific application, fee schedule, or checklist published; an EV charger circuit is billed under the same valuation-based Building Permit Fee Table used for standalone electrical work generally ($25.85 minimum).
Verified 2026-07-20 · Source
Requirements
- 'Electrical Modifications' are listed as a Permit-Required Interior Project on the City's Required Building Permits Guide -- a new dedicated EV charger circuit falls under this category
- Electrical contractors must hold a current Colorado Electrical Board (DORA) state license AND a separate City of Golden Contractor License (Municipal Code Chapter 15.01) before a permit can be issued
- No EV-specific application, checklist, or fee schedule is published on the City's Solar Energy Systems page, Required Building Permits Guide, or Building Permit Process page; applicants follow the standard building/electrical permit path via the Accela Citizen Access online permitting portal
- If the electrical work is bundled into a larger building permit's total valuation (e.g., part of a garage remodel), a separate sub-permit plan review fee is avoided per the fee table's footnote
Required documents
- RequiredElectrical Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the electrical permit type; no separate EV-charger-specific application form is published
- RequiredCity of Golden Contractor LicenseRequired registration under Municipal Code Chapter 15.01, separate from the state DORA electrical license
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee -- valuation-based (Building Permit Fee Table) | $25.85 minimum, scaling per valuation tiers | No EV-charger-specific flat fee is published; EV charger circuits are billed under the same Building Permit Fee Table (Effective 05/01/11) as other valuation-based standalone electrical work, identical mechanism to this corpus's existing solar-pv-permit and electrical-permit entries for Golden |
| Plan Review Fee | Waived when the sub-permit is attached to a valid Building Permit and its valuation is included in the total building permit valuation; otherwise 65% of the permit fee | Building Permit Fee Table footnote ** |
| Reinspection Fee | $50.00 | — |
Accessory Dwelling Unit (ADU) Permit
VerifiedRequired for construction of an ADU (a separate living space with kitchen, full bathroom, and bedroom) in conjunction with a single-household detached dwelling in Golden. Governed by Golden Municipal Code Section 18.28.240 and Section 18.29; the underlying building permit follows the standard City of Golden Building Permit Process.
Verified 2026-07-05 · Source
Requirements
- ADUs allowed in conjunction with all single-household detached dwellings in residential zone districts R-E, R-1, R-1A, R-2, and R-3 — verify eligibility via the Residential Form Zone Map
- Property owner must occupy either the principal dwelling or the ADU as their primary residence; proof of primary residence required
- One (1) off-street parking space must be provided for the ADU
- No more than three (3) people may occupy an ADU
- Accessory structure lot coverage may not exceed 10% of total lot area
- New detached ADU construction requires fire sprinklers in the new space
- Utilities must connect back to the main house, except when converting an existing basement into the ADU
- ADU Deed Restriction form required for a separate dwelling unit; a Declaration of Use form applies instead if adding only a kitchen without creating a fully separate dwelling (no new bedroom/bathroom)
- Governed by Golden Municipal Code Section 18.28.240 and Section 18.29
Required documents
- RequiredADU Deed Restriction formRequired for a separate ADU dwelling unit
- OptionalDeclaration of Use formAlternative form when adding a kitchen without creating a separate dwelling unit
- RequiredBuilding Permit Application (Online Permitting Portal)Standard City of Golden building permit process applies to the ADU construction itself
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (same valuation-based Fee Table as new construction) | $25.85 minimum, scaling per the valuation tiers in the Building Permit Fee Table | No ADU-specific fee variance is published; standard Building Permit Fee Table and 3% use tax apply |
Demolition Permit
VerifiedRequired for demolition of structures in Golden, listed as an interior/structural project requiring a permit in the Required Building Permits Guide. Fees are tiered by scope (interior non-structural, partial structural, or total structure removal) under the City's Building Permit Fee Table.
Verified 2026-07-05 · Source
Requirements
- Demolitions require a permit — listed under interior projects requiring a permit in the Required Building Permits Guide
- Fee scope determined by whether the work is interior non-structural, partial structural, or total structure removal
- All contractors must hold a City of Golden Contractor License
Required documents
- RequiredDemolition Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the demolition permit type
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Building Permit — Interior Non-Structural | $25.00 | Building Permit Fee Table, Effective 05/01/11, Resolution #1097/#1648/#2121 |
| Demolition Building Permit — Partial Structural | $50.00 | — |
| Demolition Building Permit — Total Structure Removal | $75.00 | — |
Fence / Retaining Wall Permit
VerifiedRequired for fences over 7 feet tall, fences in a front yard/corner lot/Historic District, and masonry walls or screens over 4 feet tall above finished grade in Golden. Fences 7 feet or under (outside those special locations) do not require a permit.
Verified 2026-07-05 · Source
Requirements
- Permit required for: Fences greater than 7 ft tall, OR located in the front yard, on a corner lot, or in a Historic District
- Permit required for: Masonry Walls or Screens over 4 ft tall above finished grade
- Fences 7 ft tall or less generally do NOT require a permit UNLESS located in the front yard, on a corner lot, or in a Historic District (check applicable zoning setback requirements separately)
- Retaining walls requiring engineering are separately noted as needing a permit in the Required Building Permits Guide's exterior projects list
Required documents
- RequiredFence/Wall Permit Application (Online Permitting Portal)Apply via Accela Citizen Access under the applicable exterior permit type
- RequiredSite PlanShowing fence/wall location relative to property lines, front yard, and corner-lot or Historic District status
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee — valuation-based (Building Permit Fee Table) | $25.85 minimum, scaling per valuation tiers | No fence/wall-specific flat fee is published; billed under the general Building Permit Fee Table |
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Golden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.