This is PermitBase’s published record for Berthoud as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Berthoud building permits
VerifiedBerthoud, Colorado — as published 2026-07-06.
Verified 2026-07-06 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for new construction of single-family homes, duplexes, and townhomes in the Town of Berthoud. Reviewed under the 2024 IRC (Chapters 1-43 and Appendix AB) as locally amended, plus the Town's Climatic and Geographic Design Criteria (35 psf ground snow load, 115-140 mph ultimate wind speed, 30-inch frost depth). Issued by the Planning & Building Department; inspections performed under contract by SAFEbuilt/ProCode.
Verified 2026-07-06 · Source
Requirements
- Plans must comply with the 2024 IRC as locally amended and the Town's Climatic and Geographic Design Criteria: 35 psf ground snow load (30 psf minimum uniform design load), 115-140 mph ultimate design wind speed (Exposure C, Special Wind Region per the Colorado Front Range Gust Map or Larimer County Basic Design Wind Speed Map), Seismic Design Category B, 30-inch minimum frost depth, ice barrier underlayment required
- Foundation design and construction drawings must be stamped by a Colorado-registered design professional and based on an engineer's soils report; foundation drains must likewise be designed and inspected by a Colorado-registered design professional
- All new residential buildings must comply with the Town's 2024 IECC energy code, including Appendix RM (Colorado Model Electric and Solar Ready Code — Residential): a designated solar-ready zone (≥300 sq ft per dwelling unit, ≥150 sq ft for qualifying townhouses) on suitably oriented/low-slope roofs unless exempted, electric-ready provisions for combustion equipment (dedicated branch circuit and panel space reserved for future electric equipment), and EV-ready provisions (one EV-ready parking space per dwelling unit with a dedicated 8.3kVA branch circuit) for new buildings and major renovations/additions
- Applicant/contractor must hold a current Town of Berthoud contractor license (Residential General Contractor C class for new one- and two-family construction) per Ordinance No. 1376 (2026), with $1,000,000 general liability insurance and the Town named as Certificate Holder
- Applications submitted online via the Town's CommunityCore portal
Required documents
- RequiredBuilding Permit Application (CommunityCore)Submitted through the Town of Berthoud's CommunityCore online permitting portal
- RequiredNew Single Family Dwelling Submittal Requirements packetTown-published checklist of required plan sheets/documents for new single-family construction
- RequiredEngineered Soils Report and Stamped Foundation DrawingsPrepared by a Colorado-registered design professional
- RequiredTown of Berthoud Residential General Contractor C LicenseRequired per Ordinance No. 1376 (2026); $1,000,000 general liability insurance with Town as Certificate Holder
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Construction Permit Fee | Per the 2024 IRC Appendix AB valuation-based fee table | 2026 Schedule of Rates, Charges and Fees. A flat $50 Administration Fee and $50 Technology Fee are added to every building permit fee. |
| Plan Review Fee | 65% of the Permit Fee | — |
| Use Tax | 4% (Town) of construction materials/fixed equipment, based on 50% of total project valuation unless a specific cost breakdown is provided; PLUS an additional 1.05% Larimer County use tax | Confirmed from the Town's live 2026 fee schedule |
| Electrical Permit Fee (new living space, by square footage) | $100 (0-1,000 sq ft); $150 (1,001-1,500 sq ft); $200 (1,501-2,000 sq ft); +$10 per additional 100 sq ft over 2,000 sq ft | Added to any permit involving electrical work; Electrical Plan Review is 50% of the Electrical Permit Fee (residential) |
Residential Addition / Remodel / Basement Finish Permit
VerifiedRequired for additions, interior remodels, and basement finishes to existing one- and two-family homes and townhomes in Berthoud. Reviewed under the 2024 IRC as locally amended; basement finishes are billed as a distinct flat-fee category on the Town's fee schedule.
Verified 2026-07-06 · Source
Requirements
- Additions must comply with the same Climatic and Geographic Design Criteria and IECC/Appendix RM electric-and-solar-ready provisions as new construction where the addition constitutes a 'major renovation'
- A Licensed Colorado design professional's stamp is required where structural elements (wall removal, new foundations) are involved
- Contractor must hold the applicable Town of Berthoud contractor license (Residential General Contractor C for additions/remodels/basement finishes, or Trade Contractor for smaller interior remodel/handyman-scope work) per Ordinance No. 1376
- Basement Finish permits are billed as a distinct flat fee on the Town's 2026 fee schedule rather than the full valuation-based Appendix AB table
Required documents
- RequiredBuilding Permit Application (CommunityCore)Submitted through the Town's CommunityCore online portal
- Required2024 IRC Building Guide — Home AdditionsTown-published submittal guide for additions
- Optional2024 IRC Residential Basement Finish guideTown-published submittal guide specific to basement finish scope
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Construction Permit Fee (Additions/Remodels) | Per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration and $50 Technology fee | 2026 Schedule of Rates, Charges and Fees |
| Basement Finish Permit Fee | $100.00 flat | Distinct flat-fee line item on the 2026 fee schedule, not the valuation-based table |
| Plan Review Fee | 65% of the Permit Fee | — |
| Use Tax | 4% Town + 1.05% Larimer County, per the standard formula | — |
Electrical Permit
VerifiedRequired for installation, alteration, or repair of electrical systems in Berthoud. Governed by the 2023 NEC as adopted. Electricians must hold an active Colorado State Electrical Board (DORA) license, contemporaneously verified by the Town per its posted HB19-1086/SB19-156 procedure — Berthoud does not run a separate local electrical licensing board, and its own Trade Contractor license fee is explicitly waived for electrical contractors 'per State Statutes.'
Verified 2026-07-06 · Source
Requirements
- Governed by the 2023 NEC as adopted by the Town of Berthoud
- Electricians must hold a current Colorado State Electrical Board (DORA) license; verified contemporaneously by Town/SAFEbuilt staff at registration per the Town's posted 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (required under SB19-156 / CRS Title 12 Article 115)
- A Town of Berthoud Trade Contractor license is required for the business entity, but the Town charges NO separate license fee for Electrical Contractors specifically, per Ordinance No. 1376 Appendix A
- Fee calculated either by residential living-area square footage (new living space) or by installation valuation ('All Other')
- New residential construction and major renovations must satisfy Appendix RM/CK electric-ready and EV-ready provisions (dedicated branch circuits, reserved panel space, required labeling)
Required documents
- RequiredElectrical Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- RequiredColorado State Electrical Board (DORA) LicenseVerified contemporaneously by the Town at registration
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Electrical Fee — new living space, 0 to 1,000 sq ft | $100.00 | 2026 Schedule of Rates, Charges and Fees; plus $25 Administration + $25 Technology fee where the electrical work is issued as an over-the-counter permit |
| Residential Electrical Fee — 1,001 to 1,500 sq ft | $150.00 | — |
| Residential Electrical Fee — 1,501 to 2,000 sq ft | $200.00 | — |
| Residential Electrical Fee — each additional 100 sq ft over 2,000 sq ft | $10.00 per 100 sq ft | — |
| All Other Electrical Fee (by valuation) — $1.00 to $2,000.00 | $100.00 | — |
| All Other Electrical Fee (by valuation) — over $2,000.00 | $200 + $10 for each additional $1,000 over $2,000 | — |
| Residential Solar Electrical Fee | $500.00 | — |
| Nonresidential Solar Electrical Fee (< 2MW) | $1,000.00 | — |
| Nonresidential Solar Electrical Fee (> 2MW) | Per Table 1-A, 1997 UBC, plus Plan Review | — |
| Mobile Home/Travel Trailer Electrical Fee | $150.00 per space | — |
| Electrical Re-inspection Fee | $85.00 | — |
| Temporary Construction Meter | $85.00 | — |
| Permanent Meter Inspection | $85.00 | — |
| Electrical Plan Review — Residential | 50% of Electrical Permit Fee | — |
| Electrical Plan Review — Non-Residential | 65% of Electrical Permit Fee | — |
| Electrical Violation Fee | 2x the permit fee | — |
| Electrical Investigation Fee | $150.00 per hour | — |
Plumbing Permit
Required for installation, alteration, or repair of plumbing systems in Berthoud, governed by the 2024 International Plumbing Code (IPC) as locally amended (or the corresponding chapters of the 2024 IRC for one- and two-family work). Plumbers must hold an active Colorado State Plumbing Board (DORA) license, contemporaneously verified by the Town — the same state-anchored model as electrical, with the Town's own Trade Contractor license fee waived for plumbing contractors.
Reviewed 2026-07-06 · Source
Requirements
- Governed by the 2024 IPC (Chapters 1-13) as adopted, or the 2024 IRC plumbing provisions for one- and two-family dwellings, both locally amended (12-inch sewer depth, 12-inch roof drain extension, DWV rough testing by water or air without evidence of leakage)
- Plumbers must hold a current Colorado State Plumbing Board (DORA) license; verified contemporaneously by Town/SAFEbuilt staff per the Town's posted HB19-1086 procedure (CRS Title 12 Article 155)
- A Town of Berthoud Trade Contractor license is required for the business entity, but the Town charges NO separate license fee for Plumbing Contractors specifically, per Ordinance No. 1376 Appendix A
- Graywater systems (where installed in new homes) must comply with Colorado State Regulation 86; the Town is the designated local agency for graywater oversight and requires graywater specifications and connections to be identified on permit drawings
Required documents
- RequiredPlumbing/Building Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- RequiredColorado State Plumbing Board (DORA) LicenseVerified contemporaneously by the Town at registration
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plumbing Permit Fee (part of the Residential/Non-Residential Construction valuation-based fee) | Per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration + $50 Technology fee | 2026 Schedule of Rates, Charges and Fees — Berthoud does not publish a separately itemized standalone plumbing-only fee table distinct from the general Building Permit Fee valuation schedule |
| Plan Review Fee | 65% of the Permit Fee | — |
| Water Service Line Repair (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
| Wastewater Service Line Repair (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
Mechanical / HVAC Permit
VerifiedRequired for heating, cooling, and ventilation equipment installation or replacement in Berthoud. Governed by the 2024 International Mechanical Code (IMC) and 2024 International Fuel Gas Code (IFGC) as locally amended.
Verified 2026-07-06 · Source
Requirements
- Governed by the 2024 IMC (Chapters 1-15) and 2024 IFGC (Chapters 1-8) as adopted
- Plastic fuel gas piping must be buried a minimum of 18 inches below grade; fuel gas test pressure amended to 10 psig (from base code's 3 psig)
- Contractor must hold a Town of Berthoud Trade Contractor license (Mechanical, ICC G29 pathway) plus any applicable Colorado state trade credential
- New buildings/major renovations must provide dedicated electric-ready infrastructure for combustion HVAC equipment per Appendix CK/RM (reserved panel space, labeled circuit, condensate drain provision) even when the primary system is gas-fired
Required documents
- RequiredMechanical/Building Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- RequiredTown of Berthoud Trade Contractor License (Mechanical)Required per Ordinance No. 1376
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mechanical Permit Fee (part of the general valuation-based Building Permit Fee) | Per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration + $50 Technology fee | 2026 Schedule of Rates, Charges and Fees |
| Air Conditioning (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
| Furnace Replacement (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
| Gas Piping (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
| Hot Water Boiler (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
| Hot Water Heater (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee | — |
| Plan Review Fee | 65% of Permit Fee | — |
Re-Roof Permit
VerifiedRequired for all residential re-roofing in Berthoud, billed as a flat over-the-counter fee. Governed by 2024 IRC Chapter 9 as locally amended, requiring Class 4 impact-resistant asphalt shingles (UL 2218), full tear-off to the deck, and ice barrier underlayment to at least 24 inches inside the exterior wall line. Detailed in the Town's own 'Building Guide — 2024 IRC Residential Re-Roof' (published by SAFEbuilt, January 2026).
Verified 2026-07-06 · Source
Requirements
- Class 4 impact-resistant asphalt shingles (tested to UL 2218) required, with narrow exceptions for color/style-matching replacements or repairs/additions to existing sub-Class-4 roofing
- If a repair exceeds 50% of the roof area, the entire roof must be replaced with Class 4 shingles
- Full tear-off of all existing roofing layers down to the deck is required for complete re-roofs (one-layer overlay is essentially not permitted under current fire/wind codes)
- Ice barrier required from the lowest roof edges to at least 24 inches inside the exterior wall line
- Drip edge required at all eaves and gables for new roof installations
- Design wind speed of 115 mph must be accommodated per manufacturer installation specifications
- Damaged, rusted, or deteriorated roof jacks/vents/b-vents must be replaced; additional roof vents added where needed to comply with 2024 IRC Section 806 (Roof Ventilation)
- Contractor must hold a Town of Berthoud Trade Contractor license (Roofing, ICC G14/G15 pathway)
Required documents
- RequiredBuilding Permit Application — Re-Roof scope (CommunityCore)Submitted via the Town's online permitting portal
- OptionalManufacturer's Specifications and Installation InstructionsRequired on-site and available to installers and the inspector for tile, metal, and special roof materials exceeding 7.5 lb/sq ft
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roofing/Re-Roofing (Residential) — Over-the-Counter One-Stop Fee | $150.00 + $25 Administration + $25 Technology fee = $200.00 total | 2026 Schedule of Rates, Charges and Fees — confirmed via direct page render of the fee schedule PDF |
Rooftop Solar / Photovoltaic Permit
VerifiedRequired for solar photovoltaic and solar thermal installations in Berthoud. Electrical portions governed by the 2023 NEC (Article 625 for EVSE-adjacent work) as adopted; new construction and major renovations must also satisfy Appendix RM/CK Colorado Model Solar Ready Code provisions even where solar is not being installed at time of construction. PV fees are billed as flat amounts distinct from the standard electrical fee tables.
Verified 2026-07-06 · Source
Requirements
- Governed by the 2023 NEC as adopted; solar-ready zone, roof-load documentation, and interconnection-pathway requirements apply per Appendix RM (residential) / Appendix CK (commercial) of the 2024 IECC
- Contractor must hold a Town of Berthoud Trade Contractor license (Solar pathway) plus any required Colorado state electrical trade credential, contemporaneously verified per the Town's HB19-1086/SB19-156 procedure
- Residential solar-ready zone: minimum 300 sq ft per dwelling unit (150 sq ft for qualifying 3-story-or-less townhouses ≤2,000 sq ft conditioned space), free from obstructions, with a documented interconnection pathway and reserved main-panel breaker space labeled 'For Future Solar Electric'
- Commercial solar-ready zone: minimum 40% of qualifying roof area, subject to shading/engineering-certification exceptions
Required documents
- RequiredSolar/Electrical Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- RequiredTown of Berthoud Trade Contractor License (Solar)Required per Ordinance No. 1376
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Solar Electrical Fee | $500.00 flat | 2026 Schedule of Rates, Charges and Fees |
| Nonresidential Solar Electrical Fee (< 2MW) | $1,000.00 flat | — |
| Nonresidential Solar Electrical Fee (> 2MW) | Per Table 1-A, 1997 UBC, plus Plan Review | — |
| Electrical Plan Review — Residential Solar | 50% of the Electrical Permit Fee | — |
Accessory Dwelling Unit (ADU) Permit
Berthoud's zoning code permits accessory dwelling units in at least its R4 (mixed-use residential) zone district, where an ADU counts as 0.33 units toward overall project density and is listed as requiring approval via a Building Permit following the applicable land-use approval (Table 3.3 of the Berthoud Development Code). There is no dedicated standalone 'ADU permit' fee line on the Town's fee schedule — an approved ADU is built and permitted through the standard residential building-permit process once zoning/land-use approval is secured.
Reviewed 2026-07-06 · Source
Requirements
- Zoning/land-use review to confirm the parcel's zone district permits an ADU and to determine which approval track applies (the Town's Table 3.3 land-use table lists ADUs as requiring a Building Permit following the applicable land-use approval in at least the R4 district) — confirm the specific zone district and any use-by-special-review requirement with Planning & Zoning before applying for the building permit itself
- Once zoning approval is secured, the ADU is permitted as a standard Residential Building Permit (new construction) or Residential Addition permit (if attached/converted from existing space), subject to the same 2024 IRC design criteria, Appendix RM electric/solar-ready provisions, and contractor-licensing requirements as any other residential structure
- Contractor must hold the applicable Town of Berthoud contractor license (Residential General Contractor C, or Trade Contractor if the ADU qualifies as a small accessory structure) per Ordinance No. 1376
Required documents
- RequiredLand-Use/Zoning Approval (Planning Division)Required before building-permit submittal; specific track (Site Plan, Use by Special Review, or administrative Building Permit approval) depends on zone district per Development Code Table 3.3
- RequiredBuilding Permit Application (CommunityCore)Submitted after zoning approval, using the standard new-construction or addition permit track
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (standard new-construction/addition valuation-based fee) | Per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration + $50 Technology fee | No distinct ADU-specific fee line exists on the Town's 2026 fee schedule; an ADU is billed under the same schedule as any comparable new residential structure or addition |
Demolition Permit
VerifiedRequired for demolition of structures in Berthoud, billed as a flat over-the-counter fee. A separate, additional 'Historic Building Alteration/Demolition' Planning Division application fee applies if the structure has historic designation.
Verified 2026-07-06 · Source
Requirements
- Governed by the 2024 IBC/IRC and 2024 IEBC as locally amended
- Contractor must hold a Town of Berthoud Trade Contractor license (demolition/excavation falls under the Trade Contractor category)
- Historic Building Alteration/Demolition requires a separate Planning Division application and fee if the structure carries historic designation
Required documents
- RequiredDemolition Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- OptionalHistoric Building Alteration/Demolition ApplicationRequired only if the structure has historic designation
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition — Over-the-Counter One-Stop Fee | $150.00 + $25 Administration + $25 Technology fee = $200.00 total | 2026 Schedule of Rates, Charges and Fees — confirmed via direct page render |
| Historic Building Alteration/Demolition (Planning Division application fee, if applicable) | $100.00 | Separate from the Building Department's demolition permit fee; applies only to historically designated structures |
Commercial Tenant Improvement Permit
VerifiedRequired for tenant finishes and remodels of commercial buildings in Berthoud. Reviewed under the 2024 IBC/IECC as locally amended by the Town's Planning & Building Department; fire-protection-system components (sprinklers, alarms, suppression, fire pumps) are independently plan-reviewed and permitted by the Berthoud Fire Protection District, which publishes an actual 15-business-day turnaround SLA distinct from the Town's own unpublished timeline.
Verified 2026-07-06 · Source
Requirements
- Governed by the 2024 IBC as locally amended; General Contractor D Town license category specifically covers 'Tenant Finishes and Remodels, swimming pool/spa of Commercial Buildings' per Ordinance No. 1376
- New commercial buildings and first tenant finishes crediting toward Appendix CK compliance must satisfy the Colorado Model Electric and Solar Ready Code — Commercial (dedicated electric infrastructure for combustion equipment, solar-ready roof zone ≥40% of qualifying roof area, EV power transfer infrastructure per Table CV502.1) before a Certificate of Occupancy is issued to the tenant
- Any fire-protection system work (sprinklers, alarms, kitchen/spray-booth suppression, fire pumps) requires a SEPARATE plan review and permit from the Berthoud Fire Protection District, independent of the Town's Building Department review
- General Contractor D or applicable Trade Contractor Town license required, per Ordinance No. 1376, with $300,000 general liability insurance
Required documents
- RequiredCommercial Building Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- RequiredCommercial Estimate Request FormTown-published form for commercial project valuation estimates
- OptionalBerthoud Fire Protection District Plan Review ApplicationSeparate application/fee for any fire-protection system component; submitted directly to BFPD, not the Town Building Department
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Non-Residential Construction Permit Fee | Per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration + $50 Technology fee | 2026 Schedule of Rates, Charges and Fees — Berthoud applies the same Appendix AB-keyed valuation table to non-residential construction as to residential |
| Plan Review Fee | 65% of the Permit Fee | — |
| Use Tax | 4% Town + 1.05% Larimer County, per the standard formula | — |
| Berthoud Fire Protection District Plan Review/Permit Fee | Per BFPD's own consolidated fee schedule (separate from the Town's fee schedule) | Not itemized here — administered entirely by the independent Fire District, not the Town Building Department |
Deck / Patio Cover / Patio Enclosure Permit
Required for decks, patio covers, and patio enclosures in Berthoud per the Town's published 'Building Permits Are Required For' list. Reviewed under the 2024 IRC as locally amended; the Town publishes dedicated Building Guides for Uncovered Decks & Porches and Patio Covers.
Reviewed 2026-07-06 · Source
Requirements
- Decks, Patio Covers, and Patio Enclosures are explicitly listed on the Town's 'Building Permits Are Required For' checklist — confirmed directly from the Town's own published list (807 Mountain Ave letterhead document)
- Pergolas over 120 sq ft, or of any size if attached to the house, require a permit per the same checklist
- Governed by the 2024 IRC as locally amended, including the Climatic and Geographic Design Criteria (35 psf ground snow load, 115-140 mph wind speed) for structural design
- Contractor must hold the applicable Town of Berthoud contractor license (Trade Contractor category explicitly covers 'decks, sheds, carports, pergolas' for residential work) per Ordinance No. 1376
Required documents
- RequiredBuilding Permit Application (CommunityCore)Submitted via the Town's online permitting portal
- Optional2024 IRC Building Guide — Uncovered Decks & PorchesTown-published submittal guide
- Optional2024 IRC Building Guide — Patio CoverTown-published submittal guide
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (Work not specifically listed — Residential) | 65% of Permit Fee (Plan Review) per the 2024 IRC Appendix AB valuation-based fee table, plus $50 Administration + $50 Technology fee | 2026 Schedule of Rates, Charges and Fees; decks/patio covers/enclosures do not have their own dedicated fee line and are billed under the general valuation-based Building Permit Fee schedule |
Furnace / Water Heater Replacement Permit
VerifiedLike-for-like furnace and hot water heater/boiler replacements are billed as a distinct flat-fee 'Over the Counter One-Stop' permit category in Berthoud, separate from the full valuation-based Building Permit Fee schedule used for new HVAC/plumbing system installs.
Verified 2026-07-06 · Source
Requirements
- Applies to straightforward replacement (not new installation) of furnaces, hot water heaters, and hot water boilers
- Contractor must hold the applicable Town of Berthoud Trade Contractor license (Mechanical/Plumbing pathway) plus any required Colorado state trade credential
- New/replacement combustion equipment must still meet the Electric Ready code's dedicated branch-circuit and panel-space provisions in new construction contexts, though a simple like-for-like replacement in an existing home is not itself 'new construction or major renovation' triggering Appendix RM
Required documents
- RequiredOver-the-Counter Permit Application (CommunityCore)Submitted via the Town's online permitting portal
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Furnace Replacement (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee = $200.00 total | 2026 Schedule of Rates, Charges and Fees — confirmed via direct page render |
| Hot Water Boiler (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee = $200.00 total | — |
| Hot Water Heater (over-the-counter) | $150.00 + $25 Administration + $25 Technology fee = $200.00 total | — |
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Berthoud building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.