Skip to main content
PermitBase

Fruita building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Fruita, Colorado.

Verified 2026-07-13 · Source

How to schedule

Inspections are requested through the building department below.

Address
325 E Aspen Avenue, Suite 155, Fruita, CO 81521
Phone
970-639-9919 (Building Division main line); Community Development Department (970) 858-0786
Office hours
Monday through Thursday, 7:30 a.m. - 5:00 p.m. (closed Fridays and Municipal Holidays), per the City of Fruita Building Division page

Published scheduling rules

  • All permit applications and inspection requests go through Cloudpermit — create your account before you need to apply, since account setup can add a day of lead time. (Residential Building Permit (New Construction))
  • Applications, plan submittals, and inspection requests are made through the City's Cloudpermit online portal (Residential Building Permit (New Construction))

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Required before concrete pour; a Top of Foundation Compliance Form is part of Fruita's standard submittal package

  2. 2

    Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical

    Framing, electrical, plumbing, and mechanical rough-ins inspected before concealment

  3. 3

    Insulation

    Energy Code Checklist compliance verified before drywall/cover, per the 2021 IECC as locally amended

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes; floodplain administrator sign-off required first if the parcel is in a mapped flood hazard area

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Rough Frame / Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour, for addition footings or deck posts requiring a permit

  2. 2

    Rough Frame / Rough Electrical / Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; structural connections to the existing structure verified

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Roofing Permit (Reroof)

  1. 1

    Roof Sheathing

    Inspects the framing of the roof system and sheathing before it is covered — per Fruita's own Reroof Information page

  2. 2

    Mid-Roof

    Required when 10% to 40% of the shingles are installed; verifies roof deck, all flashings, drip edge, underlayment, nailing, and roof ventilation — per Fruita's own Reroof Information page

  3. 3

    Final Inspection

    ALWAYS required, per Fruita's own Reroof Information/FAQ page

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel inspected before concealment/insulation

  2. 2

    Final Electrical

    Devices installed, panel labeled, system energized and verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    EVSE circuit wiring and disconnect inspected before concealment, per the City's standard electrical rough-in practice

  2. 2

    Final Electrical

    EVSE unit connections verified, circuit labeled, system energized

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment rough-in inspected before concealment

  2. 2

    Final Mechanical

    Equipment operational; combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Underground/in-slab and rough-in plumbing inspected before concealment

  2. 2

    Final Plumbing

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement verified before energizing, per standard electrical permit inspection practice; electrical plans must be on site for this inspection

  2. 2

    Final Inspection

    Racking, roof penetrations, electrical connections, and all required NEC labeling (Sections 690.54, 690.13(b), 705.10, 705.12, 690.56) verified

Re-inspection fees

Electrical PermitRe-inspection Fee · Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation
Plumbing PermitRe-inspection Fee · Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation
Mechanical / HVAC PermitRe-inspection Fee · Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation
EV Charger / EVSE PermitRe-inspection Fee · Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation

Fruita building permits

Get alerts for Fruita

We'll email you when Fruita's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.