This is PermitBase’s published record for Fort Morgan as of 2026-08-13. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Fort Morgan building permits

Verified

Fort Morgan, Colorado — as published 2026-08-13.

Verified 2026-07-06 · Source

Codes adopted

2024 International Building Code (IBC) — adopted by City of Fort Morgan Ordinance No. 1337, effective June 16, 2026, per the City's Building Department page2024 International Residential Code (IRC) — Ordinance No. 1337, June 16, 20262024 International Mechanical Code (IMC) — Ordinance No. 1337, June 16, 20262024 International Fire Code (IFC) — Ordinance No. 1337, June 16, 20262024 International Existing Building Code (IEBC) — Ordinance No. 1337, June 16, 20262024 International Energy Conservation Code (IECC) — Ordinance No. 1337, June 16, 2026 (City's page notes phased enforcement; the City's CCICC-hosted residential guides still reference an older 2009 IECC enforcement baseline predating the June 2026 update, so confirm current phase-in status directly with the Building Department for a specific project)2018 International Plumbing Code (IPC) and 2018 International Fuel Gas Code (IFGC) — City's Building Department page states these 2018-cycle codes remain currently enforced (not yet updated to the 2024 cycle adopted for the other I-Codes)2023 Colorado Model Electric and Solar Ready Code (CMERSRC) — state-mandated, adopted per Ordinance No. 13372020 National Electrical Code (NEC) — referenced on the City's CCICC-hosted residential building guides; moot for City permitting purposes since the City no longer issues or inspects electrical permits (see localAmendments) — electrical work is governed by whatever NEC edition the State of Colorado Electrical Board currently enforcesFort Morgan Municipal Code Chapter 21 (Building Regulations), Article 2 (Building Code) and Article 3 (Residential Code) codify local adoption and amendments; full municipal code hosted at library.municode.com/co/fort_morgan (page was Cloudflare/captcha-gated during this review — citations here rely on the City's own Building Department page rather than the Municode text directly)

Permit types & fees

Residential Building Permit (New Single-Family Residence / New House)

Verified

Required for new single-family home construction within Fort Morgan city limits, per the City's Building Permit Application (which includes a 'New House' square-footage field) and Building Department page. Reviewed under the 2024 IRC/IBC as locally adopted by Ordinance No. 1337 (effective June 16, 2026), plus the 2023 Colorado Model Electric and Solar Ready Code. Issued by the City of Fort Morgan Building Department; electrical work on the project is NOT included — it is permitted separately through the State of Colorado Electrical Board.

Verified 2026-07-06 · Source

Requirements

  • Plans must comply with the 2024 IRC/IBC as adopted by Ordinance No. 1337, effective June 16, 2026
  • Must additionally comply with the 2023 Colorado Model Electric and Solar Ready Code (CMERSRC), state-mandated
  • Contractor registration with the City of Fort Morgan required before work begins, in addition to any state-level trade licenses
  • Use Tax (4%) applies to building materials not purchased locally; proof of local purchase (sales tax already paid) required to avoid the charge
  • 24 hours advance notice required to schedule inspections
  • Applications submitted via the City's MyGov online portal (public.mygov.us/fort_morgan_co)
  • Electrical work on the project is NOT part of this City building permit — a separate electrical permit must be obtained directly from the State of Colorado Electrical Board (DORA) at dpo.colorado.gov/EandP/Permits

Required documents

  • RequiredBuilding Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co; the legacy paper form (revised 4/9/10) is still hosted on the City's DocumentCenter but the MyGov portal is the current application channel per the Building Department page
  • RequiredConstruction Drawings / Plan SetPlan set sufficient for IRC/IBC plan review as locally adopted; specific submittal checklist not independently located beyond the CCICC residential guides referenced by the City
  • RequiredContractor RegistrationCity of Fort Morgan contractor registration required for all contractors performing work, separate from any state license

Fee schedule

Fee typeAmountNotes
Construction Fee — valuation $1.00 to $500.00$27.00Citywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03, effective March 3, 2026
Construction Fee — valuation $501.00 to $2,000.00$27.00 for the first $500 plus $3.50 for each additional $100 or fraction thereof
Construction Fee — valuation $2,001.00 to $25,000.00$79.50 for the first $2,000 plus $16.10 for each additional $1,000 or fraction thereof
Construction Fee — valuation $25,001.00 to $50,000.00$401.75 for the first $25,000 plus $10.10 for each additional $1,000 or fraction thereof
Construction Fee — valuation $50,001.00 to $100,000.00$654.25 for the first $50,000 plus $7.00 for each additional $1,000 or fraction thereof
Construction Fee — valuation $100,001.00 to $500,000.00$1,142.55 for the first $100,000 plus $6.44 for each additional $1,000 or fraction thereof
Construction Fee — valuation $500,001.00 to $1,000,000.00$3,827.00 for the first $500,000 plus $5.46 for each additional $1,000 or fraction thereof
Construction Fee — valuation $1,000,001.00 and above$6,327.00 for the first $1,000,000 plus $4.20 for each additional $1,000 or fraction thereof
Plan Review Fee65% of the total permit feeDue at time of plan/specification submittal; additional plan review fees apply if plans are incomplete or changed requiring further review
Use Tax4% of non-locally-purchased building materials valuationPer Colorado Department of Revenue municipal use tax rate data; collected by the Building Department as part of the permit process unless proof of local purchase (with sales tax paid) is provided

Residential Addition / Remodel Permit (Addition, Garage, Basement Finish)

Verified

Required for room additions, garages, and basement finishes to existing residential buildings in Fort Morgan, per the City's Building Permit Application (which itemizes 'Addition, Garage, or House' square footage and 'Basement') and the CCICC-published residential building guides the City references (additions, basement finishes, decks/porches, detached garages, patio covers/carports, enclosing patio covers, ramps, pole barns). Reviewed under the 2024 IRC as locally adopted.

Verified 2026-07-06 · Source

Requirements

  • Permit required for room additions, garage construction/additions larger than 200 sq ft, and basement finishes
  • Detached garages 200 sq ft or less generally covered under the flat 'Garage Permit' fee tier described only for 'New and Additions Larger than 200 Sq. Ft.' in the fee schedule — the fee schedule does not separately break out a flat fee for garages 200 sq ft or under, so this file does not assume one applies (confirm directly for smaller garage projects)
  • Sheds larger than 120 sq ft up to 200 sq ft require a Shed Permit (flat fee); the fee schedule does not state a threshold below which sheds are permit-exempt, so confirm directly with the Building Department for small accessory structures
  • Contractor registration with the City required for all contractors
  • 24 hours advance notice required for inspections
  • Use Tax (4%) applies to non-locally-purchased materials

Required documents

  • RequiredBuilding Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co
  • RequiredConstruction DrawingsScope-appropriate plan set for the addition/remodel/garage/basement-finish project

Fee schedule

Fee typeAmountNotes
Construction Fee (same valuation-based schedule as new construction)$27.00 minimum, scaling per the March 2026 Citywide Fee Schedule valuation tiersApplies to additions and basement finishes valued and reviewed under the general Construction Fees table
Garage Permit (New and Additions Larger than 200 Sq. Ft.)$65.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03
Plan Review Fee65% of the permit fee, where plan review is required
Use Tax4% of non-locally-purchased materials valuation

Electrical Permit — REFERRED TO STATE OF COLORADO (Not Issued by the City)

Verified

The City of Fort Morgan does NOT issue electrical permits or conduct electrical inspections. Per the City's own Building Department page: 'The City of Fort Morgan is no longer issuing electrical permits or conducting inspections for such.' All electrical permitting and inspection for work within Fort Morgan is handled directly by the Colorado Department of Regulatory Agencies (DORA), State of Colorado Electrical Board.

Verified 2026-07-06 · Source

Requirements

  • Electrical contractors and homeowners performing their own electrical work must apply directly to the State of Colorado Electrical Board (DORA) for any required electrical permit — NOT the City of Fort Morgan
  • Homeowners performing their own electrical work must both own AND reside in the residence, per the State Electrical Board's homeowner-permit rules referenced in this review
  • Applications and permits are obtained online through DORA at https://dpo.colorado.gov/EandP/Permits
  • State-issued electrical permits are valid for one year from the date of issuance, per DORA's published permit/inspection information
  • Contact DORA directly for permitting/inspection questions: 303-894-7800, dora_eandp_permits@state.co.us

Required documents

  • RequiredState of Colorado Electrical Permit Application (DORA online system)Submitted directly to the Colorado Department of Regulatory Agencies, State of Colorado Electrical Board — not through the City of Fort Morgan

Fee schedule

Fee typeAmountNotes
State of Colorado Electrical Permit FeeNot published on any City of Fort Morgan page, since the City does not administer this permit; set and collected entirely by DORA/State Electrical BoardConfirm current state fee directly at dpo.colorado.gov/EandP/Permits — genuinely out of scope for this City-focused file to reproduce, since fee-setting authority rests with the state, not Fort Morgan

Plumbing / Gas / Water & Sewer Line Permit

Verified

Required for plumbing installation/alteration/repair, gas appliance installation, backflow devices, and water/sewer line work in Fort Morgan. Governed by the 2018 International Plumbing Code (IPC) and 2018 International Fuel Gas Code (IFGC) as currently enforced by the City (the City's page notes these codes were not updated to the 2024 cycle alongside the other I-Codes adopted by Ordinance No. 1337). Issued by the City of Fort Morgan Building Department.

Verified 2026-07-06 · Source

Requirements

  • Permit required for plumbing systems, gas appliance installation, backflow devices (lawn sprinklers and domestic water), water heaters, and water/sewer line work outside the building
  • Governed by the 2018 IPC and 2018 IFGC, per the City's Building Department page (these code editions were not updated in the June 2026 Ordinance No. 1337 adoption that moved most other codes to the 2024 cycle)
  • Contractor registration with the City required, in addition to any state plumbing/gas contractor license
  • 24 hours advance notice required for inspections
  • Use Tax (4%) applies to non-locally-purchased materials

Required documents

  • RequiredPlumbing/Gas Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co

Fee schedule

Fee typeAmountNotes
Backflow Device Permit (Plumbing) — Lawn Sprinklers & Domestic Water$35.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03
Gas Appliance Permit$40.00 flat fee
Water Heater Permit (Plumbing) — Gas and Electric Water Heaters$30.00 flat fee
Sewer Line Permit (outside of building, 5 feet from foundation to property line)$40.00 flat fee
Water Line Permit (outside of building, from foundation to meter pit)$30.00 flat fee
Construction Fee (when plumbing is part of a larger project not covered by a flat fee)Calculated per the general valuation-based Construction Fees table ($27.00 minimum)The Citywide Fee Schedule's Construction Fees table explicitly 'Includes Mechanical, Plumbing & Sign Permits'
Plan Review Fee65% of the permit fee, where plan review is required

Mechanical / HVAC Permit (A/C Installation)

Verified

Required for HVAC/air conditioning installation in Fort Morgan. Governed by the 2024 International Mechanical Code (IMC) as adopted by Ordinance No. 1337, effective June 16, 2026. The electrical connection portion of an A/C installation is explicitly excluded from this permit and must be separately permitted through the State of Colorado Electrical Board.

Verified 2026-07-06 · Source

Requirements

  • Permit required for A/C installation and other mechanical/HVAC equipment work
  • Governed by the 2024 IMC as adopted by Ordinance No. 1337, effective June 16, 2026
  • The A/C Installation flat fee explicitly does NOT include electrical work ('A/C Installation (Does NOT Include Electrical)' per the fee schedule) — any electrical connection must be separately permitted through the State of Colorado Electrical Board
  • Contractor registration with the City required
  • 24 hours advance notice required for inspections

Required documents

  • RequiredMechanical Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co

Fee schedule

Fee typeAmountNotes
A/C Installation (Does NOT Include Electrical)$40.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03; electrical connection is separately permitted through the State Electrical Board, not included in this fee
Construction Fee (for mechanical work not covered by the flat A/C fee)Calculated per the general valuation-based Construction Fees table ($27.00 minimum)The Citywide Fee Schedule's Construction Fees table explicitly 'Includes Mechanical, Plumbing & Sign Permits'

Roofing Permit (Re-Roofing)

Verified

Required for roofing and re-roofing work in Fort Morgan, billed as a flat fee. The City references CCICC-published roofing requirements and roof inspection procedures documents in addition to the base Building Department page.

Verified 2026-07-06 · Source

Requirements

  • Permit required for roofing/re-roofing work, per the flat-fee schedule
  • Shingle type, felt number, and total layers when complete must be specified on the permit application, per the (legacy) Building Permit Application form fields
  • The City separately publishes 'Roofing Requirements' (dated 010117) and 'Roof Inspection Procedures' documents on the Building Department's Quick Links page, referenced but not independently retrieved in full detail during this review

Required documents

  • RequiredRoofing Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co
  • OptionalRoofing Requirements documentReferenced on the Building Department's Quick Links page (dated 010117); details not independently verified beyond the reference itself in this review

Fee schedule

Fee typeAmountNotes
Roofing Permit$40.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03, effective March 3, 2026

Solar Panel Permit

Verified

Required for solar panel installation in Fort Morgan, billed as a flat fee that explicitly excludes electrical work. The electrical interconnection portion of a solar project must be separately permitted through the State of Colorado Electrical Board, consistent with the City's broader policy of not handling electrical permits.

Verified 2026-07-06 · Source

Requirements

  • Permit required for solar panel installation, per the flat-fee schedule ('Solar Panel Permit (Does NOT Include Electrical)')
  • The electrical interconnection/wiring portion of the solar installation must be separately permitted through the State of Colorado Electrical Board (DORA), consistent with the City's general non-handling of electrical permits

Required documents

  • RequiredSolar Panel Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co for the mounting/structural scope

Fee schedule

Fee typeAmountNotes
Solar Panel Permit (Does NOT Include Electrical)$160.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03, effective March 3, 2026

Demolition / Moving Permit

Verified

Required for demolition or structure-moving work in Fort Morgan, billed at a tiered flat fee (primary vs. secondary structure) when done in conjunction with a Building Permit.

Verified 2026-07-06 · Source

Requirements

  • Permit required for demolition or moving of structures
  • Fee is tiered: a 'Primary' rate and a lower 'Secondary' rate, both described as 'In conjunction with Building Permit' — the fee schedule does not further define what triggers Primary vs. Secondary classification beyond this label; confirm directly with the Building Department for a specific project

Required documents

  • RequiredDemolition/Moving Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co

Fee schedule

Fee typeAmountNotes
Demolition/Moving Permit — Primary$65.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03; 'In conjunction with Building Permit'
Demolition/Moving Permit — Secondary$40.00 flat fee

Fence Permit

Verified

Required for fence construction in Fort Morgan, billed as a flat fee. The legacy Building Permit Application form requests fence type, height, length, and whether the job has been surveyed.

Verified 2026-07-06 · Source

Requirements

  • Permit required for fence construction, per the flat-fee schedule
  • Application (per the legacy paper form's fields, presumed still relevant to the current MyGov application) requests: type of fence, height, length, and whether the job has been surveyed
  • No retaining-wall-specific flat fee or height threshold is published separately from the general Fence Permit line item; a retaining wall project may fall under the general valuation-based Construction Fee table instead — not independently confirmed in this review

Required documents

  • RequiredFence Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co

Fee schedule

Fee typeAmountNotes
Fence Permit$35.00 flat feeCitywide Fee Schedule, Exhibit A to Resolution No. 2026-03-03, effective March 3, 2026

EV Charger / Electric Vehicle Charging Station Permit — REFERRED TO STATE OF COLORADO (Not Issued by the City)

Verified

The City of Fort Morgan does NOT issue electrical permits or conduct electrical inspections of any kind, including for EV charger/EVSE circuits. Per the City's own Building Department page: 'The City of Fort Morgan is no longer issuing electrical permits or conducting inspections for such.' All electrical permitting and inspection for EV charger installation within Fort Morgan is handled directly by the Colorado Department of Regulatory Agencies (DORA), State of Colorado Electrical Board — the same authority-split mechanism documented in the electrical-permit entry, which also explicitly carves electrical scope out of the City's A/C and solar permits.

Verified 2026-07-20 · Source

Requirements

  • Electrical contractors and homeowners installing an EV charger circuit must apply directly to the State of Colorado Electrical Board (DORA) for the required electrical permit — NOT the City of Fort Morgan
  • Homeowners performing their own EV charger wiring must both own AND reside in the residence, per the State Electrical Board's homeowner-permit rules
  • Applications and permits are obtained online through DORA at https://dpo.colorado.gov/EandP/Permits
  • State-issued electrical permits are valid for one year from the date of issuance, per DORA's published permit/inspection information
  • Contact DORA directly for permitting/inspection questions: 303-894-7800, dora_eandp_permits@state.co.us

Required documents

  • RequiredState of Colorado Electrical Permit Application (DORA online system)Submitted directly to the Colorado Department of Regulatory Agencies, State of Colorado Electrical Board — not through the City of Fort Morgan — same application used for any electrical work including EV charger circuits

Fee schedule

Fee typeAmountNotes
State of Colorado Electrical Permit Fee (applies to EV charger circuit; no distinct EV line)Not published on any City of Fort Morgan page, since the City does not administer this permit; set and collected entirely by DORA/State Electrical BoardConfirm current state fee directly at dpo.colorado.gov/EandP/Permits — genuinely out of scope for this City-focused file to reproduce, since fee-setting authority rests with the state, not Fort Morgan

Commercial Building Permit (New Construction, Additions, Remodels / Tenant Improvements)

Verified

Required for new commercial construction, commercial additions, and commercial alterations/remodels (including tenant improvements) within Fort Morgan city limits. Issued by the City of Fort Morgan Building Department — Fort Morgan is a home-rule city; Morgan County's building division covers only unincorporated county territory. The City's Building Department page states it performs 'Construction Plan Reviews for residential, commercial, and miscellaneous construction,' and that 'The Chief Building Official and Fire Marshal review all construction plans to ensure compliance with all adopted Codes.' Reviewed under the 2024 IBC/IEBC/IMC/IFC/IECC as adopted by Ordinance No. 1337 (effective June 16, 2026), with plumbing/fuel-gas still on the 2018 IPC/IFGC cycle. Electrical work is NOT included — it is permitted separately through the State of Colorado Electrical Board (DORA), and commercial fire sprinkler systems are permitted through the State of Colorado (Division of Fire Prevention and Control), per the City's own fee schedule. There is NO separately-published tenant-improvement permit type: TI/remodel work runs through this same permit and valuation-based fee, with the fee schedule's own valuation rule that 'Remodel projects with no addition in square footage that include all trades will be calculated at 60% of the unit costs.'

Verified 2026-08-02 · Source

Requirements

  • Plans must comply with the 2024 IBC, IEBC, IMC, IFC, and IECC as adopted by Ordinance No. 1337 (effective June 16, 2026), the 2018 IPC/IFGC (still current for plumbing/fuel-gas), and the 2023 Colorado Model Electric and Solar Ready Code
  • All construction plans are reviewed by BOTH the Chief Building Official and the Fire Marshal, per the City's Building Department page
  • Contractor registration with the City of Fort Morgan required before work begins; at registration each contractor must provide proof of general liability insurance (Certificate of Insurance), per the City's Contractor Registration page (requirement effective June 30, 2025) — registration fees are quarterly-prorated ($50.00 first quarter down to $12.50 fourth quarter) and all registrations expire December 31 regardless of issue date
  • Electrical work on the project is NOT part of this City permit — a separate electrical permit must be obtained directly from the State of Colorado Electrical Board (DORA) at dpo.colorado.gov/EandP/Permits
  • Commercial fire sprinkler systems are NOT permitted by the City — the Citywide Fee Schedule's Fire Department section directs commercial (and residential) sprinkler permits to the State of Colorado, (303) 239-4100, colorado.gov/dfpc; fire alarm permits ($75.00) and commercial hood permits ($75.00) are issued through the City's Fire Department
  • Use Tax (4%) applies to building materials not purchased locally; proof of local purchase (sales tax already paid) required to avoid the charge, collected through the Building Department as part of the permit process
  • 24 hours advance notice required to schedule inspections; every permit issued requires at least one inspection, per the City's Building Department FAQ
  • Applications submitted via the City's MyGov online portal (public.mygov.us/fort_morgan_co)

Required documents

  • RequiredBuilding Permit Application (MyGov portal)Submitted online via public.mygov.us/fort_morgan_co, the City's current application channel per the Building Department page
  • RequiredConstruction Drawings / Plan SetFull plan set sufficient for joint plan review by the Chief Building Official and Fire Marshal under the 2024 I-Codes as locally adopted; no commercial-specific submittal checklist is published on the City's site
  • RequiredContractor Registration with Certificate of InsuranceCity of Fort Morgan contractor registration (separate from any state license) with proof of general liability insurance, required before performing work in city limits

Fee schedule

Fee typeAmountNotes
Construction Fee — valuation $1.00 to $500.00$27.00Citywide Fee Schedule ('Construction Fees — Includes Mechanical, Plumbing & Sign Permits'), re-verified live 2026-08-02 from the City's Schedule of Fees document (Exhibit A to Resolution No. 2026-03-03)
Construction Fee — valuation $501.00 to $2,000.00$27.00 for the first $500 plus $3.50 for each additional $100 or fraction thereofThe published schedule's own text at this row reads 'each additional $1000,' but the tier arithmetic ($79.50 at exactly $2,000 = $27.00 + 15 × $3.50) confirms the increment is per $100 — recorded per the internally-consistent reading rather than the row's apparent typo
Construction Fee — valuation $2,001.00 to $25,000.00$79.50 for the first $2,000 plus $16.10 for each additional $1,000 or fraction thereof
Construction Fee — valuation $25,001.00 to $50,000.00$401.75 for the first $25,000 plus $10.10 for each additional $1,000 or fraction thereof
Construction Fee — valuation $50,001.00 to $100,000.00$654.25 for the first $50,000 plus $7.00 for each additional $1,000 or fraction thereof
Construction Fee — valuation $100,001.00 to $500,000.00$1,142.55 for the first $100,000 plus $6.44 for each additional $1,000 or fraction thereof
Construction Fee — valuation $500,001.00 to $1,000,000.00$3,827.00 for the first $500,000 plus $5.46 for each additional $1,000 or fraction thereof
Construction Fee — valuation $1,000,001.00 and above$6,327.00 for the first $1,000,000 plus $4.20 for each additional $1,000 or fraction thereof
Plan Review Fee65% of the total permit feeDue at time of submitting plans and specifications; additional plan review fees charged when plans are incomplete or changed so as to require additional review
Valuation basis (commercial)Unit costs per square foot by occupancy classification and construction type, per the fee schedule's attached Square Foot Construction Costs table (table is headed '2021 International Building Code' groups)Fee-schedule valuation rules: remodel projects with no addition in square footage that include all trades are calculated at 60% of the unit costs; Shell Only Buildings deduct 20%; commercial air conditioning equipment adds $7.20 per sq. ft.
Temporary Certificate of Occupancy (TCO) — commercial under 3,000 sq ft$500.00$350 refund if complete by expiration; if not, no refund, with new TCO and fee required
Temporary Certificate of Occupancy (TCO) — commercial (and multi-family per building) 3,000 sq ft and above$1,200.00$900 refund if complete by expiration; if not, no refund, with new TCO and fee required
Fire Alarm Permit (City Fire Department)$75.00
Commercial Hood Permit (City Fire Department)$75.00Commercial sprinkler permits are NOT a City fee line — the fee schedule directs them to the State of Colorado, (303) 239-4100, colorado.gov/dfpc
Use Tax4% of non-locally-purchased building materials valuationCollected by the Building Department as part of the permit process unless proof of local purchase (with sales tax paid) is provided
Re-inspection fees1st inspection included with permit; 2nd inspection $50.00; 3rd inspection $100.00; 4th inspection $250.00; each additional inspection after the 4th adds $100.00; No Show Fee $25.00 plus cost of inspection (if applicable)
After-hours inspections $50.00/hour weekdays, $60.00/hour weekends and holidays (by approval, minimum 1-hour charge). Show full citation

After-hours inspections $50.00/hour weekdays, $60.00/hour weekends and holidays (by approval, minimum 1-hour charge). Figures re-verified live 2026-08-02 from the current Schedule of Fees document; note these differ from an earlier capture of this schedule recorded elsewhere in this file's localAmendments

Sign Permit

Verified

Fort Morgan regulates signage under Municipal Code Chapter 20 (Land Use Code), Article 9 — Sign Regulations, per the full text hosted on Municode Library. The sign code exempts signs installed by the Federal government, State of Colorado, Morgan County, the City itself, and Morgan County School District Re-3 (including street signs and traffic-control devices) from the chapter's regulations. The City Manager or designee has authority to inspect signs and order repair, repainting, alteration, or removal of any sign that constitutes a hazard to safety, health, or public welfare due to inadequate maintenance, dilapidation, or building/electrical code violations. Sign permits are administered by the City's Building Department alongside general building permits.

Verified 2026-08-13 · Source

Requirements

  • Signage in Fort Morgan is regulated under Municipal Code Chapter 20, Article 9 (Sign Regulations); most signs visible from a public right-of-way require a permit unless specifically exempted
  • Signs installed by the Federal government, State of Colorado, Morgan County, the City of Fort Morgan, or Morgan County School District Re-3 — including street signs and traffic-control devices — are exempt from Article 9's permit requirements
  • Signs not visible from certain vantage points due to building configuration or topography are subject only to specific sections of the chapter rather than the full sign code, per Article 9's own scoping language
  • The City Manager or designee may order repair, repainting, alteration, or removal of any sign that has become a hazard due to inadequate maintenance, dilapidation, or building/electrical code violations, or that is otherwise noncompliant
  • No numeric sign-permit fee schedule or review-timeline figure was found published on the City's Permits/Licenses or Building Department pages as of the last verification — confirm current fee and turnaround with the Building Department (970-542-3907)

Required documents

  • RequiredBuilding and Sign Permit ApplicationFort Morgan's Building Department administers sign permits as part of its general building-permit process; contact the department to confirm the current application form

Fee schedule

Fee typeAmountNotes
Sign Permit FeeNot published as a numeric figure on the City's Permits/Licenses or Building Department pagesContact the City of Fort Morgan Building Department (970-542-3907) for a current fee quote

Fire Sprinkler / Fire Alarm System Permit

Verified

Fort Morgan Fire Department (Fire Marshal, 116 Main Street, 970-542-3983) issues fire alarm and fire sprinkler permits via its own Fire Alarm & Fire Sprinkler Permit Request Form, published on the City's Fire Department Documents page. The form requires the application to be filled out completely and accompanied by detailed plans before a permit is issued; inspections are scheduled by appointment.

Verified 2026-08-13 · Source

Requirements

  • Application must be filled out completely and accompanied by detailed plans before a permit will be issued, per the Fire Alarm & Fire Sprinkler Permit Request Form
  • Applicant must provide job address, property owner, contact person/phone, building square footage by floor (garage, basement, 1st floor, 2nd floor), and building/electrical/fire-alarm contractor names and phone numbers
  • A copy of the factory certification for the specific fire alarm type, or a NICET Fire Alarm Level II certificate, must accompany the plans prior to review in order to receive a permit
  • Fire Alarm Permit Fee: flat $75.00
  • Fire Sprinkler Permit Fee: $75.00 for residential; commercial sprinkler permits are fee-scaled (exact commercial fee schedule not published on the form itself — confirm with the Fire Marshal)
  • Inspections are conducted by appointment only, coordinated with the Fire Marshal's office (970-542-3983)

Required documents

  • RequiredFire Alarm & Fire Sprinkler Permit Request FormCity of Fort Morgan Fire Department form; select Fire Alarm Permit or Fire Sprinkler Permit and provide job/property/contractor details
  • RequiredDetailed PlansDetailed system plans must accompany the permit application
  • RequiredFactory Certification or NICET Fire Alarm Level II CertificateMust accompany the plans prior to review to receive a permit

Fee schedule

Fee typeAmountNotes
Fire Alarm Permit Fee$75.00 flatPer the City's Fire Alarm & Fire Sprinkler Permit Request Form
Fire Sprinkler Permit Fee — Residential$75.00 flatPer the City's Fire Alarm & Fire Sprinkler Permit Request Form
Fire Sprinkler Permit Fee — CommercialScaled (exact schedule not published on the permit form)The form marks the commercial sprinkler fee as "(scale)" without a numeric table; contact the Fire Marshal (970-542-3983) for a project-specific quote

Change of Use / Change of Occupancy

Verified

Fort Morgan does not publish a standalone 'Change of Use' or 'Change of Occupancy' permit application separate from its general building permit process — the City's Building Department and Permits/Licenses pages list only standard building, sign, and trade permit categories. A change of use or occupancy classification is governed by the City's adopted 2024 International Existing Building Code (IEBC), per Ordinance No. 1337 (effective June 16, 2026), which generally addresses change-of-occupancy requirements in IEBC Chapter 10. A use/occupancy change is processed through the same Building Permit Application used for all other Fort Morgan permit types.

Verified 2026-08-13 · Source

Requirements

  • No standalone change-of-use or change-of-occupancy application is published on the City's Building Department or Permits/Licenses pages — checked directly
  • Governed by the City's adopted 2024 International Existing Building Code (IEBC), per Ordinance No. 1337 (effective June 16, 2026); IEBC Chapter 10 (Change of Occupancy) applies as adopted, since no City amendment to that chapter was confirmed
  • Processed through the standard Building Permit Application used for every other Fort Morgan permit type
  • Where alteration or construction work accompanies the use change, standard building-permit fees and review timelines apply; contact the Building Department (970-542-3907) to confirm requirements for a specific project
  • Fort Morgan Fire Department review may be required depending on whether the new occupancy classification triggers fire/life-safety requirements — see this file's fire-sprinkler-alarm-permit entry

Required documents

  • RequiredBuilding Permit ApplicationSame form used for all Fort Morgan permit types; used to document occupancy classification changes

Fee schedule

Fee typeAmountNotes
Building Permit Fee / Plan Check Fee (only if construction accompanies the change)Not published as a standalone change-of-use fee lineNo standalone 'change of use' fee is published on the City's Permits/Licenses or Building Department pages; contact the Building Department (970-542-3907) for a project-specific quote

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Morgan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-08-02)Later version (2026-08-21) →View current record →All versions →

Permalink: /colorado/morgan-county/fort-morgan/as-of/2026-08-13/

Snapshot date: 2026-08-13

Commit: 1a7358f

Reproducible from PermitBase’s version-controlled dataset, commit 1a7358f.