How to schedule

Inspections are requested through the building department below.

Address
110 Sherman Street, Fort Morgan, CO 80701 (mailing: P.O. Box 100, Fort Morgan, CO 80701); Building Inspector office at 710 E. Railroad Ave., Fort Morgan, CO 80701
Phone
970-542-3907
Office hours
Monday-Friday, 8:00 a.m. to 5:00 p.m., per the City's Building Permit Application form (710 E. Railroad Ave. location). Chief Building Official: Rocky Watkins, 970-370-6559. Permit Technician: Kayla Thompson, 970-542-3907. Building Inspector line: 970-542-3908.

Published scheduling rules

  • 24 hours advance notice required to schedule inspections (Residential Building Permit (New Single-Family Residence / New House))
  • 24 hours advance notice is required to schedule any City inspection, per the Building Department page. (General)

Inspection sequence

Applies to: Residential Addition / Remodel Permit (Addition, Garage, Basement Finish)

  1. 1

    Foundation (if new footings)

    Before concrete pour, for additions/garages with new foundation elements

  2. 2

    Rough Framing

    Framing complete and tied into existing structure before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment, where applicable; electrical rough-in (if any) is inspected separately by the State of Colorado Electrical Board, not the City

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans

Applies to: Residential Building Permit (New Single-Family Residence / New House)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment; plumbing and mechanical are inspected by the City — electrical rough-in is inspected separately by the State of Colorado Electrical Board, not the City

  4. 4

    Final Inspection

    All City-permitted work (building, plumbing, mechanical) complete per approved plans; a separate final electrical inspection and sign-off is required from the State of Colorado Electrical Board before occupancy

Applies to: Mechanical / HVAC Permit (A/C Installation)

  1. 1

    Rough Mechanical

    Equipment placement and ductwork before concealment

  2. 2

    Final Inspection

    Equipment operational; the City verifies mechanical scope only — electrical connection sign-off is separately handled by the State of Colorado Electrical Board

Applies to: Plumbing / Gas / Water & Sewer Line Permit

  1. 1

    Rough Plumbing / Gas Line

    Pipe, drain, waste, vent, and gas-line installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Fort Morgan building permits

Get alerts for Fort Morgan

We'll email you when Fort Morgan's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.