How to schedule

Inspections are requested through the building department below.

Address
201 W. 8th St. #120, Pueblo, CO 81003
Phone
719-583-6100
Office hours
Monday-Friday, 7:30 a.m.-4:30 p.m., closed on County holidays. Same-day inspection requests must be submitted before 8:30 a.m.; inspections may otherwise be scheduled in advance. Source: Pueblo County Building Division homepage and Request an Inspection page, https://pueblopermits.com/ and https://pueblopermits.com/request-an-inspection/

Published scheduling rules

  • Same-day inspection requests (with an active permit number and, for contractors, a CLR number) must be submitted before 8:30 a.m. (Electrical Permit)
  • Same-day inspection requests must be submitted before 8:30 a.m.; inspections may otherwise be scheduled in advance. A permit number is required for all inspection requests, and contractors must provide an active CLR (Contractor License Registration) number. Source: https://pueblopermits.com/request-an-inspection/ (General)

Inspection sequence

Applies to: Residential Addition / Remodel / Alteration Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for deck posts, garage foundations, or addition footings

  2. 2

    Framing

    Structural framing and connections to existing structure

  3. 3

    Final

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete pour — verify forms, rebar, and foundation depth meets the 26-inch minimum frost depth

  2. 2

    Framing

    Structural framing per 2021 IRC and approved plans

  3. 3

    Final

    All work complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified per 2023 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    EVSE wiring, box placement, and service connections inspected before walls are closed, if applicable

  2. 2

    Final

    EVSE equipment installed and protections verified per 2023 NEC

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Gas Pressure Test

    Ductwork and equipment rough-in before concealment; gas piping pressure test before concealment or utility turn-on

  2. 2

    Final

    Equipment operational, combustion air/clearances verified

Applies to: Plumbing Permit

  1. 1

    Underground/Rough-In

    Before concealment — verify pipe slope, materials, and cleanouts

  2. 2

    Final

    Fixtures connected, backflow protection verified, no leaks

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Panel mounting, roof penetration sealing, electrical connections, inverter, and interconnection verified

Final inspection only: Roof Permit

Unincorporated Pueblo County building permits

Get alerts for Unincorporated Pueblo County

We'll email you when Unincorporated Pueblo County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.