Inspection sequence, scheduling, and re-inspection fees for building permits in Garden City, Idaho.

Verified 2026-06-29 · Source

How to schedule

Inspections are requested through the building department below.

Address
6015 N Glenwood St, Garden City, ID 83714-1347
Phone
208-472-2921
Office hours
Mon & Fri 9:00 AM – 3:30 PM; Tue & Thu 10:30 AM – 3:30 PM; Wed 9:00 AM – 12:00 PM; closed daily 12:00–1:00 PM for lunch

Published scheduling rules

  • Schedule all building inspections by 4:00 PM the prior day via the Inspection Hotline (208) 472-2920 or the online Inspection Request Form at gardencityidaho.org/inspections/. Same-day inspections are not available. (Residential Building Permit (New Construction / Addition / Remodel))
  • Schedule inspections by 4:00 PM the prior day via the Inspection Hotline (208) 472-2920. (Demolition Permit)
  • All building inspections must be scheduled by 4:00 PM the prior business day. Same-day inspections are not available. Call the Inspection Hotline (208) 472-2920 or submit an online Inspection Request Form at gardencityidaho.org/inspections/. (General)

Inspection sequence

Applies to: Non-Residential Building Permit (New Construction / Tenant Improvement)

  1. 1

    Foundation

    Before concrete pour — schedule by 4:00 PM prior day via Inspection Hotline (208) 472-2920 or online Inspection Request Form

  2. 2

    Framing / Structural

    After structural framing and before wall cover — reviewed by SAFEbuilt or IDOPL

  3. 3

    Final

    All work complete; Certificate of Occupancy (C of O) or Certificate of Compliance (C of C) issued upon passing all required inspections

Applies to: Residential Building Permit (New Construction / Addition / Remodel)

  1. 1

    Footing / Foundation

    Before concrete pour — schedule by 4:00 PM prior day via Inspection Hotline (208) 472-2920 or online Inspection Request Form. Inspections will not be conducted if fees have not been paid or permit is not posted on site.

  2. 2

    Framing

    After framing complete, before insulation or wall cover — building inspection by SAFEbuilt/IDOPL

  3. 3

    Final

    All work complete per approved plans; Certificate of Occupancy issued upon passing all required inspections

Applies to: Manufactured Home Installation Permit

  1. 1

    Installation Inspection

    Structural/installation inspection per Idaho building codes — schedule by 4:00 PM prior day via Inspection Hotline (208) 472-2920

  2. 2

    Final / Safety Checklist Verification

    Manufactured Home Safety Checklist must be completed prior to final certificate; final certificate not issued until safety checklist submitted

Applies to: Residential Solar Photovoltaic (PV) Permit

  1. 1

    State Electrical Inspection

    Performed by DOPL, covering interconnection wiring, disconnects, and equipment grounding per the adopted NEC edition

  2. 2

    City Final (Structural)

    Racking/mounting attachment and roof penetration sealing verified against approved City building permit plans, per SAFEbuilt review

Re-inspection fees

Residential Building Permit (New Construction / Addition / Remodel)Re-inspection or additional inspections · Garden City Development Services Fee Schedule, Resolution 1239-26 Exhibit A
$80.00/hour minimum 1 hour
Manufactured Home Installation PermitRe-inspection fees (after first re-inspection) or additional plan review · Garden City Development Services Fee Schedule, Resolution 1239-26 Exhibit A — Manufactured Home section
$80.00/hour

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Garden City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Garden City building permits

Get alerts for Garden City

We'll email you when Garden City's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.