Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for all new single-family residential construction in Star. Applications submitted and payments made online through the IWORQ Permit Portal. Plans must be 24" × 36", submitted in landscape orientation as PDF. Contractors must register before accessing the portal. Typical review: small residential projects 2–4 weeks; larger residential projects approximately 4–6 weeks. Revisions add 3–4 weeks per cycle.
Verified 2026-07-16 · Source
Requirements
- All new construction requires a building permit
- Contractors must complete the Contractor Registration Form before accessing the permit portal
- All plans submitted online via IWORQ Portal (staridpermit.portal.iworq.net); no in-person paper submissions
- Plan size must be 24" × 36" in landscape orientation with space reserved for City approval stamps
- Sewer certificate required from Star Sewer & Water District for all new homes with sewer service
- If structure is in flood plain, contact the City Zoning Administrator before submitting
- Structures 4,000 sq. ft. or more require Fire review for hydrant flow adequacy
- Soils/geotechnical report required if project includes a basement; must be stamped by Idaho licensed engineer
- Structural drawings and calculations must be stamped, signed, and dated by Idaho licensed design professional if applicable
- Fire sprinkler/alarm plans (3 sets, under separate cover) if required — may be deferred
- Energy compliance required: Alternate Energy Path (signed, all pages) or Prescriptive Method
- Plans must include a plan check report as the first pages of the submittal
Required documents
- RequiredResidential Submittal Checklist & Standards (Form #312, Rev 02-2026)City of Star's required residential submittal checklist including site plan, foundation plan, floor plan, roof/floor framing, elevations, wall bracing, wall sections/details, connection details, energy compliance, structural drawings, and MEP floor plan requirements
- RequiredSite PlanMust show location of new structure on site, all existing structures, dimensional setbacks from rear and side yards and from back of sidewalk, driveway width, proposed or existing fences, all property lines and easements, and a short narrative of scope of work with square footage
- RequiredFoundation PlanMust include foundation system type, compliant crawlspace venting, anchor bolt locations, and footing detail. Basements require soils/geotechnical report stamped by Idaho licensed engineer.
- RequiredConstruction Drawings (Floor Plan, Framing, Elevations, Wall Bracing, Sections and Details)Complete plan set showing code compliance per 2018 IRC; all rooms labeled with clear dimensions; all sides of structure shown in elevations
- RequiredEnergy Compliance DocumentationAlternate Energy Path (signed, all pages) or Prescriptive Method demonstrating 2018 IECC compliance
- RequiredContractor Registration FormRequired for all contractors before accessing the permit portal; available on the City of Star Building Department website
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Application Submittal Fee (non-refundable) | $100.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). Applied toward total building permit cost. Not refundable or transferable. |
| Building Permit Fee — Valuation $1 to $500 | $23.50 | Table 1-A, City of Star Building Permit Fees (staridaho.org/ImageRepository/Document?documentId=1637). All tiers re-verified line-by-line against the live fee table 2026-07-16; unchanged. |
| Building Permit Fee — Valuation $501 to $2,000 | $23.50 for first $500 plus $3.05 per each additional $100 or fraction thereof to $2,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $2,001 to $25,000 | $69.25 for first $2,000 plus $14 per each additional $1,000 or fraction thereof to $25,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $25,001 to $50,000 | $391.75 for first $25,000 plus $10.10 per each additional $1,000 or fraction thereof to $50,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $50,001 to $100,000 | $643.75 for first $50,000 plus $7 per each additional $1,000 or fraction thereof to $100,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $100,001 to $500,000 | $993.75 for first $100,000 plus $5.60 per each additional $1,000 or fraction thereof to $500,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $500,001 to $1,000,000 | $3,233.75 for first $500,000 plus $4.75 per each additional $1,000 or fraction thereof to $1,000,000 | Table 1-A, City of Star Building Permit Fees |
| Building Permit Fee — Valuation $1,000,001 to $5,000,000 | $5,608.75 for first $1,000,000 plus $3.65 per each additional $1,000 or fraction thereof to $5,000,000 | Table 1-A, City of Star Building Permit Fees |
| Residential Mechanical Review Fee | $35.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Re-inspection Fee | $65.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Re-review Plans | $50.00 | Must submit original AND updated plans. City of Star Fee Information page. |
| Ada County Highway District — Single Family Detached Impact Fee | $5,803 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). Impact fee paid to ACHD, not City of Star. |
| Star Fire Impact Fee | $2,152 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Star Parks Impact Fee | $4,695.76 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Star Police Impact Fee | $680.88 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Public Safety Mitigation Fee — Police | $3,360 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Public Safety Mitigation Fee — Fire | $3,600 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Ada County Single Family Residential Impact Fees (Jail, EMS, Coroner) | $750 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
Commercial Building Permit (New Construction & TI)
VerifiedRequired for all new commercial construction and tenant improvements in Star. Plans must be stamped and signed by a licensed architect including a full code analysis. All applications submitted online through the IWORQ Permit Portal. Typical review: 4–6 weeks; revisions add 3–4 weeks per cycle.
Verified 2026-07-16 · Source
Requirements
- Planning & Zoning approval required to verify proposed use is compatible with current zoning and that no other entitlements are needed
- All commercial projects require a sewer/water certificate from Star Sewer & Water District
- Architectural plans must be stamped and signed by a licensed architect with code analysis (code year, occupancy groups, construction types, floor areas, building height, fire suppression system)
- Civil drawings required per Public Works Department specifications
- Landscape drawings required including pressurized irrigation, street trees; if landscaping is used for stormwater mitigation, engineered design is required
- Soils/geotechnical reports required for new buildings per IBC standards
- Structural drawings and calculations must be stamped, signed, and dated by Idaho licensed design professional
- MEP floor plan must be stamped, signed, and dated by Idaho licensed design professional
- Plans submitted via IWORQ Portal (staridpermit.portal.iworq.net); plan size 24" × 36" in landscape orientation as PDF
- If structure is in flood plain, contact City Zoning Administrator before submitting
- Fire review required for Star Joint Fire Protection District (permits@starfirerescue.org); also contact ACHD Development Services and Central District Health / Southwest District Health as applicable
Required documents
- RequiredCommercial Submittal Checklist & Standards (Form #307, Rev 02-2026)City of Star's required commercial submittal checklist; available at staridaho.org/DocumentCenter/View/1638/Commercial-Submittal-Checklist--2026-02
- RequiredArchitectural Plans with Code AnalysisMust be stamped and signed by a licensed architect; code analysis must include code year, occupancy groups, construction types, all floor areas, building height, and fire suppression system specification
- RequiredCivil and Landscape DrawingsPer Public Works Department specifications; landscape drawings must include pressurized irrigation and street trees
- RequiredSoils / Geotechnical ReportRequired for new commercial buildings per IBC standards; must be stamped and signed by Idaho licensed engineer
- RequiredStructural Drawings and CalculationsMust be stamped, signed, and dated by Idaho licensed design professional
- RequiredMEP Floor PlanMechanical, Electrical, and Plumbing floor plan identifying all rooms by use with all associated MEP and legends; must be stamped, signed, and dated by Idaho licensed design professional
- RequiredProject NarrativeDetailed narrative with full scope of work
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Commercial Application Submittal Fee (non-refundable) | $200.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). Applied toward total permit cost. Not refundable or transferable. |
| Building Permit Fee — valuation-based (Table 1-A) | Valuation-based: e.g., $993.75 for first $100,000 plus $5.60 per $1,000 over $100,000 (to $500,000) | Table 1-A City of Star Building Permit Fees (staridaho.org/ImageRepository/Document?documentId=1637). Same table as residential. |
| Ada County Highway District — Single Family Attached Impact Fee | $3,182 | City of Star Fee Information page. For attached units. Contact ACHD for commercial-specific impact fees. |
| Re-inspection Fee | $65.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
Mechanical Permit
VerifiedRequired for HVAC, gas lines, fireplaces, and other mechanical work on both new and existing residential and commercial properties in Star. Purchased separately from the building permit at City Hall / via the permit portal. Approved and issued same day if associated building permit is already approved.
Verified 2026-07-16 · Source
Requirements
- Mechanical permit required in addition to and separate from any building permit
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Work performed by Idaho state-licensed mechanical contractor for commercial; homeowners may perform their own work on their primary/secondary residence
- Residential permit fee based on square footage of home (see fee schedule)
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; contractor must be registered in City system
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New Residential Mechanical — Single Family under 1,500 sq. ft. | $130.00 | City of Star MEP Fee Schedule, Resolution 2025-03, approved 6/17/2025 (staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule). Confirmed still the current schedule 2026-07-16; no superseding resolution found. |
| New Residential Mechanical — Single Family 1,501–2,500 sq. ft. | $195.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Mechanical — Single Family 2,501–3,500 sq. ft. | $260.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Mechanical — Single Family 3,501–4,500 sq. ft. | $325.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Mechanical — Modular/Manufactured/Mobile Home | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Existing Residential Mechanical | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Gas Line | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Fireplace (Gas, Electric) or Wood Stove/Fireplace — New Residential | $75.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Fireplace (Gas, Electric) or Wood Stove/Fireplace — Existing Residential | $130.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Commercial/Other — valuation-based | Up to $20,000: multiply by 3% add $60; $20,001–$100,000: subtract $20,000, multiply by 2%, add $660; over $100,001: subtract $100,000, multiply by 1%, add $2,260 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Re-inspection Fee | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
Electrical Permit
VerifiedRequired for all electrical work on residential and commercial properties in Star. Purchased separately from the building permit. Approved and issued same day if associated building permit is already approved. Fee schedule based on Resolution 2025-03 (approved 6/17/2025).
Verified 2026-07-16 · Source
Requirements
- Electrical permit required in addition to and separate from any building permit
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Work performed by Idaho state-licensed electrical contractor for commercial; homeowners may perform their own work on their primary/secondary residence
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; contractor must be registered in City system
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New Residential Electrical — Single Family under 1,500 sq. ft. | $130.00 | City of Star MEP Fee Schedule, Resolution 2025-03 (staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule) |
| New Residential Electrical — Single Family 1,501–2,500 sq. ft. | $195.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Electrical — Single Family 2,501–3,500 sq. ft. | $260.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Electrical — Single Family 3,501–4,500 sq. ft. | $325.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Electrical — Modular/Manufactured/Mobile Home | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Existing Residential Electrical | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Additional Branch Circuits (existing residential) | $10.00 per circuit | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Swimming Pool (residential) | $195.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Spas, Hot Tubs, and Hydro Massage Tubs | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Temporary Construction Services | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03. Full credit/refund for temp pole permit if no inspection performed. |
| Commercial/Other — valuation-based | Up to $10,000: multiply by 2% add $60; $10,001–$100,000: subtract $10,000, multiply by 1%, add $260; over $100,001: subtract $100,001, multiply by 0.5%, add $1,160 | City of Star MEP Fee Schedule, Resolution 2025-03. Applies to commercial, industrial, solar, fire alarm, new SF residential over 4,500 sq. ft., multi-family. |
| Re-inspection Fee | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
Plumbing Permit
VerifiedRequired for all plumbing work on residential and commercial properties in Star. Purchased separately from the building permit. Approved and issued same day if associated building permit is already approved. Fee schedule based on Resolution 2025-03 (approved 6/17/2025).
Verified 2026-07-16 · Source
Requirements
- Plumbing permit required in addition to and separate from any building permit
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Work performed by Idaho state-licensed plumbing contractor for commercial; homeowners may perform their own plumbing work on their primary/secondary residence
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; contractor must be registered in City system
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New Residential Plumbing — Single Family under 1,500 sq. ft. | $130.00 | City of Star MEP Fee Schedule, Resolution 2025-03 (staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule) |
| New Residential Plumbing — Single Family 1,501–2,500 sq. ft. | $195.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Plumbing — Single Family 2,501–3,500 sq. ft. | $260.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Plumbing — Single Family 3,501–4,500 sq. ft. | $325.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential Plumbing — Modular/Manufactured/Mobile Home | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential — Sewer and Water | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential — Sewer Only | $50.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| New Residential — Water Only | $50.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Existing Residential Plumbing | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Additional Fixtures (existing residential) | $10.00 per fixture | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Water Heater, Water Softener, Lawn Sprinkler | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Commercial/Other — valuation-based | Up to $20,000: multiply by 3% add $60; $20,001–$100,000: subtract $20,000, multiply by 2%, add $660; over $100,001: subtract $100,000, multiply by 1%, add $2,260 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Re-inspection Fee | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
Residential/Commercial Solar Photovoltaic (PV) Permit
VerifiedRequired for installation of a rooftop or ground-mounted solar photovoltaic system in Star. The City's own Mechanical, Electrical & Plumbing Fee Schedule (Resolution 2025-03, approved 6/17/2025) explicitly lists 'solar' as one of the project types billed under the Electrical Permit's 'Commercial/Other — valuation-based' fee tier, rather than under the flat per-square-footage residential wiring tiers — a real, distinct, City-published fee mechanism for solar. A separate Building Permit (Table 1-A, valuation-based) applies to the mounting/racking structural scope.
Verified 2026-07-20 · Source
Requirements
- Electrical interconnection/wiring for a solar PV system is billed under the Electrical Permit's 'Commercial/Other' valuation-based fee tier, per the City's MEP Fee Schedule, which explicitly states this tier 'applies to commercial, industrial, solar, fire alarm, new SF residential over 4,500 sq. ft., multi-family'
- Mounting/racking structural work is permitted via the standard Residential or Commercial Building Permit (Table 1-A, valuation-based), using the same IWORQ Permit Portal process documented elsewhere in this file
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net); contractor must be registered in the City system before accessing the portal
- Homeowners may perform their own electrical work on their primary/secondary residence; commercial-scope work requires an Idaho state-licensed electrical contractor
- Governed by the 2023 National Electrical Code (NEC) — adopted statewide by the Idaho Electrical Board (IDAPA 24.39.10), effective July 1, 2024 — for the interconnection scope, and the 2018 IBC/IRC for the structural mounting scope
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online for both the Building Permit (structural mounting) and Electrical Permit (interconnection) scopes; contractor must be registered in City system
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Solar Electrical Interconnection — Commercial/Other valuation-based tier | Up to $10,000: multiply by 2% add $60; $10,001-$100,000: subtract $10,000, multiply by 1%, add $260; over $100,001: subtract $100,001, multiply by 0.5%, add $1,160 | City of Star MEP Fee Schedule, Resolution 2025-03, approved 6/17/2025 (staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule) — this Commercial/Other tier is explicitly stated to apply to 'commercial, industrial, solar, fire alarm, new SF residential over 4,500 sq. ft., multi-family,' rather than the flat per-square-footage residential wiring tiers used for ordinary new-home wiring. |
| Building Permit Fee (structural mounting/racking, Table 1-A) | $23.50 minimum, scaling per the valuation tiers documented in the Residential Building Permit entry of this file | City of Star Building Permit Fees (Table 1-A) — applies to the racking/mounting structural scope of a solar installation, same as any other structural work. |
| Re-inspection Fee | $65.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). |
Demolition Permit
VerifiedRequired for demolition of structures in Star. Same-day approval when paperwork is complete.
Verified 2026-07-16 · Source
Requirements
- Permit required for demolition of any structure
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net)
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; contractor or homeowner must be registered in City system
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit Fee | $100.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
Residential Swimming Pool Permit
VerifiedRequired for residential swimming pool installation in Star. Separate application review fee applies in addition to the building permit fee.
Verified 2026-07-16 · Source
Requirements
- Building permit required for swimming pool installation
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Separate electrical permit required for pool wiring (residential pool electrical fee: $195)
- Submit site plan showing pool location with all setbacks
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; contractor or homeowner must be registered
- RequiredSite PlanShowing pool location on property with all setback dimensions
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Swimming Pool Application Review Fee | $70.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information). In addition to building permit fee (Table 1-A) and separate electrical permit. |
| Swimming Pool Electrical Permit | $195.00 | City of Star MEP Fee Schedule, Resolution 2025-03 (staridaho.org/DocumentCenter/View/1603/Mechanical-Electrical--Plumbing-Fee-Schedule) |
Manufactured / Mobile Home Setup Permit
VerifiedRequired for setting manufactured, modular, or mobile homes in Star. Includes separate mobile home setup fee. Separate MEP permits required for mechanical, electrical, and plumbing.
Verified 2026-07-16 · Source
Requirements
- Building permit required for setting a manufactured, modular, or mobile home
- Apply via IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Separate electrical, mechanical, and plumbing permits required
- Sewer certificate required from Star Sewer & Water District if connecting to public sewer
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; contractor must be registered in City system
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mobile Home Set-up Fee | $100.00 | City of Star Fee Information page (staridaho.org/1249/Fee-Information) |
| Modular/Manufactured/Mobile Home — Electrical Permit | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Modular/Manufactured/Mobile Home — Mechanical Permit | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
| Modular/Manufactured/Mobile Home — Plumbing Permit | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 |
EV Charger / EVSE Permit
VerifiedThe City of Star has no dedicated electric-vehicle-charging-station permit or fee line. An EV charger circuit added to an existing home is electrical work covered by the general Electrical Permit process (Resolution 2025-03 MEP Fee Schedule): the 'Existing Residential Electrical' flat fee applies to the permit itself, with the 'Additional Branch Circuits' per-circuit fee layered on if more than one circuit is added. A charger installed as part of new residential construction would instead be folded into the applicable 'New Residential Electrical' square-footage tier. No EV/EVSE-specific dollar figure was found on the published fee schedule.
Verified 2026-07-20 · Source
Requirements
- Electrical permit required, purchased separately from any building permit, per the same process documented in this file's Electrical Permit entry
- Apply via the IWORQ Permit Portal (staridpermit.portal.iworq.net)
- Homeowners may perform their own electrical work on their primary/secondary residence; commercial work requires an Idaho state-licensed electrical contractor
- No dedicated EV/EVSE line-item, application, or checklist was found on the City's MEP Fee Schedule (Resolution 2025-03) or Building Department pages
Required documents
- RequiredPermit Application (online via IWORQ Portal)Submitted online; no dedicated EV/EVSE checkbox exists
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Existing Residential Electrical (new circuit for EV charger added to an existing home) | $65.00 | City of Star MEP Fee Schedule, Resolution 2025-03 — closest applicable line-item for adding an EV charger circuit to an existing residence; no dedicated EV/EVSE fee exists |
| Additional Branch Circuits (existing residential) | $10.00 per circuit | City of Star MEP Fee Schedule, Resolution 2025-03 — applies if the charger install adds more than one circuit |
| New Residential Electrical (if charger is part of new-home construction, billed at the applicable square-footage tier) | $130.00-$325.00 depending on home size (see Electrical Permit entry for full tier table) | City of Star MEP Fee Schedule, Resolution 2025-03 |
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Star building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.