Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Bonneville County, Idaho.

Reviewed 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
357 Constitution Way, Idaho Falls, ID 83402 (mailing: 605 N Capital Ave, Idaho Falls, ID 83402)
Phone
208-524-7920
Office hours
Mon–Fri 8:00 AM – 5:00 PM (excluding holidays)

Published scheduling rules

  • As of January 20, 2026, apply for and schedule inspections for electrical and plumbing work on the same CityWorks PublicAccess portal as the building permit — Bonneville County no longer routes these trades to the State of Idaho. Projects permitted before January 20, 2026 keep their state-inspected trades through completion. (Residential Building Permit (New Construction / Addition))
  • All applications and inspection scheduling go through the county's online CityWorks PublicAccess portal (app06.cityworksonline.com/CLIENT_BonnevilleCoID-Public/login). The county's own Building & Zoning Applications and Building Permit & Zoning Fees content pages carry no static fee schedule, but the actual fee schedule IS published — as Resolution No. 25-19 (recorded 09/23/2025, effective 10/1/2025) on the county's separate Resolutions page (bonnevillecountyidaho.gov/page/resolutions, a scanned PDF hosted via Dropbox) — found 2026-07-23. It sets a valuation-based building permit fee table plus flat fees for specific permit types (e.g., Solar $210.00, Electrical or Plumbing Inspection $105.00), each subject to a 10% plan-review fee and 5% software fee; still confirm current figures with the department given the January 2026 electrical/plumbing takeover. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction / Addition)

  1. 1

    Footing/Foundation

    Before concrete placement — verify excavation, forms, and reinforcement per 2018 IBC/IRC

  2. 2

    Framing

    After framing, sheathing, and rough electrical/plumbing/mechanical trades complete — before insulation or wall cover

  3. 3

    Electrical Rough-In

    County-administered as of January 20, 2026 under the 2023 NEC — required before wall cover

  4. 4

    Plumbing Rough-In

    County-administered as of January 20, 2026 under the 2017 Idaho State Plumbing Code — required before wall cover

  5. 5

    Final

    All work complete per approved plans; final building, electrical, and plumbing sign-off issued by Bonneville County

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement — now inspected directly by the County as of January 2026

  2. 2

    Final

    Racking, roof-penetration, and electrical interconnection compliance verified by the County

Re-inspection fees

Residential Building Permit (New Construction / Addition)Minimum Reinspection Fee · Resolution 25-19, 'Specific Permit Fees' table
$105.00

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Bonneville County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Bonneville County building permits

Get alerts for Unincorporated Bonneville County

We'll email you when Unincorporated Bonneville County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.