Codes adopted

2018 International Building Code (IBC)2020 IRC — Idaho Residential Code (based on the 2018 IRC), Parts I, II, III, IX as amended, with Appendices A, B, C, D, and R (Tiny Homes)2020 IECC — Idaho Energy Conservation Code (residential portion amended)2018 International Existing Building Code (IEBC)2017 National Electrical Code (NEC)2017 Idaho State Plumbing Code (based on the 2015 Uniform Plumbing Code)2018 International Mechanical Code (IMC)2018 IRC Parts V (Mechanical) and VI (Fuel Gas)2018 International Fuel Gas Code (IFGC)2018 International Fire Code (IFC)2009 ICC/ANSI A117.1 Accessible and Usable Buildings and Facilities2010 ADA Standards for Accessible Design1991 Uniform Code for Abatement of Dangerous BuildingsMcCall City Code Title 2 (Building Regulations), Chapter 1 — Applicable Codes, as amended by Ordinance 988 (eff. 4/27/2020)

Permit types & fees

New Residence in City Limits

Verified

Required for construction of a new single-family dwelling within McCall city limits. Covers structural construction, plan review, and coordination with Public Works for water/sewer connections.

Verified 2026-07-07 · Source

Requirements

  • Applies to all new single-family dwellings within McCall city limits (a separate 'New Residence in Impact Area' process existed but the City stopped accepting Impact Area applications as of November 30, 2025)
  • Structures greater than 3,500 square feet within city limits must include plans prepared by an Idaho-licensed architect (or an out-of-state architect with an Idaho practice agreement)
  • Single-family residences exceeding 5,000 total square feet require Planning and Zoning Commission Design Review (minimum 45-day review period after a complete application, plus a pre-application conference and public hearing)
  • Submit application, plans, and required forms through the online Permit Application Portal (app.govwell.com/mccall-id)
  • A Public Works Permit application and Water Infrastructure Sizing Worksheet must be submitted for any project needing a City water/sewer connection

Required documents

  • RequiredProject Information FormWorksheet required with the application; contact the Building Department for assistance if it cannot be completed
  • RequiredMaintenance During Construction FormRequired construction site management plan per MCC 2.1.080(F)
  • RequiredPublic Works Permit Application and Water Infrastructure Sizing WorksheetRequired for connection to City water/sewer infrastructure
  • RequiredApplication and Contract for Water Utility ServiceRequired to establish water utility billing for the new residence
  • RequiredConstruction Plans (electronic PDF)Site plan, landscape plan, footing/foundation plan, floor plans, wall bracing plan, elevations/wall sections, building sections, roof and framing detail, outdoor lighting plan, and residential energy code check (REScheck, LEED, or equivalent insulation specifications)
  • RequiredStructural CalculationsRequired for all applications — calculations for all load-bearing footings, joists, beams, headers, rafters, and braced (shear) walls
  • RequiredSewer Permit or Septic PermitFrom Payette Lakes Recreational Water and Sewer District (PLRWSD) if connecting to their system, or a septic permit from Central District Health Department otherwise
  • OptionalHOA ApprovalRequired if the property is subject to HOA covenants

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $1 to $500$23.50Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024; permit fee calculated using 100% of project valuation
Building Permit — valuation $501 to $2,000$23.50 for the first $500, plus $3.05 for each additional $100 or fraction thereof
Building Permit — valuation $2,001 to $25,000$69.25 for the first $2,000, plus $14 for each additional $1,000 or fraction thereof
Building Permit — valuation $25,001 to $50,000$391.75 for the first $25,000, plus $10.10 for each additional $1,000 or fraction thereof
Building Permit — valuation $50,001 to $100,000$643.75 for the first $50,000, plus $7 for each additional $1,000 or fraction thereof
Building Permit — valuation $100,001 to $500,000$993.75 for the first $100,000, plus $5.60 for each additional $1,000 or fraction thereof
Building Permit — valuation $500,001 to $1,000,000$3,233.75 for the first $500,000, plus $4.75 for each additional $1,000 or fraction thereof
Building Permit — valuation $1,000,001 and up$5,608.75 for the first $1,000,000, plus $3.65 for each additional $1,000 or fraction thereof
Plan Review Fee65% of the calculated Building Permit feeResolution 24-11; due upon invoice and must be paid before plans enter the review queue
Re-inspection$85 per additional inspection

Remodel, Addition, or Accessory Structure Permit

Verified

Required for remodels, additions, and accessory structures (including garages and most ADUs) in McCall. Accessory structures 200 square feet or less used for non-living purposes (tool sheds, playhouses) are exempt from a building permit; accessory structures of any size containing living, sleeping, eating, cooking, or sanitation space require a permit.

Verified 2026-07-07 · Source

Requirements

  • Remodels and additions to existing residences
  • Accessory structures over 200 square feet (per Building Official Administrative Determination, 12/18/2023, applying 2020 Idaho Residential Code R105.2)
  • Accessory structures of any size containing living, sleeping, eating, cooking, or sanitation space (including most Accessory Dwelling Units)
  • Accessory structures over 1,500 square feet require Conditional Use Permit approval in addition to the building permit
  • Submit application, plans, and required forms through the online Permit Application Portal (app.govwell.com/mccall-id)

Required documents

  • RequiredProject Information FormWorksheet required with the application; contact the Building Department for assistance if it cannot be completed
  • RequiredMaintenance During Construction FormRequired construction site management plan per MCC 2.1.080(F)
  • OptionalWater Fixture WorksheetRequired if the accessory structure includes a separate City water connection, or if plumbing fixtures are being added/changed in the remodel or addition
  • RequiredConstruction Plans (electronic PDF)Site plan, footing/foundation plan, floor plans, wall bracing plan, elevations/wall sections, roof and framing detail, outdoor lighting plan, and residential energy code check
  • RequiredStructural CalculationsRequired for all applications — calculations for all load-bearing footings, joists, beams, headers, rafters, and braced (shear) walls
  • OptionalSewer Permit or Septic PermitFrom Payette Lakes Recreational Water and Sewer District if connecting to their system, or Central District Health Department septic permit otherwise
  • OptionalHOA ApprovalRequired if the property is subject to HOA covenants

Fee schedule

Fee typeAmountNotes
Building Permit — valuation-based per Resolution 24-11 scheduleSame valuation table as new residential construction: $23.50 (up to $500) through $5,608.75 + $3.65/$1,000 (over $1,000,000)Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024
Plan Review Fee65% of the calculated Building Permit feeResolution 24-11
Re-inspection$85 per additional inspection

Roof Permit

Verified

Required for reroofing and roof-related work in McCall. Governed by the Resolution 24-11 fee schedule (roof permit fee based on 50% of project valuation) and Ordinance 988 roof-covering and snow-country amendments.

Verified 2026-07-07 · Source

Requirements

  • Reroofing (tear-off or overlay) of any structure in the city
  • Roof covering must meet Class B or higher fire-retardant rating (Class A if wood shakes/shingles are used)
  • Self-adhering polymer-modified bitumen ice barrier underlayment required on the entire roof, unless prohibited by the manufacturer's installation instructions
  • Roof and attic vents must resist intrusion of flame and embers

Required documents

  • RequiredRoof Permit ApplicationSubmitted through the online Permit Application Portal
  • RequiredConstruction Plan FormRequired supplemental form for the roof permit application

Fee schedule

Fee typeAmountNotes
Roof Permit — building permit feeCalculated using 50% of project valuation against the standard Building Permit fee table (Resolution 24-11): $23.50 (up to $500) through $5,608.75 + $3.65/$1,000 (over $1,000,000)Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024 — 'Roof Permit: Permit Fee Use 50% of the valuation of the project to calculate the permit fee'
Plan Review Fee65% of the calculated Building Permit feeResolution 24-11
Re-inspection$85 per additional inspection

Fence Permit

Verified

Required for installation of fences in McCall. Fences greater than 6 feet in height are not allowed anywhere in the city; fencing within 20 feet of the front property line is limited to 4 feet.

Verified 2026-07-07 · Source

Requirements

  • Any new fence installation within the city
  • Fences greater than 6 feet in height are not allowed
  • Fencing within 20 feet of the front property line must not exceed 4 feet in height
  • Chain link fencing is prohibited in most zones
  • Fencing within commercial zones is prohibited with few exceptions
  • Property pins must be located at the time of application when fencing along property lines

Required documents

  • RequiredFence Building Permit ApplicationSubmitted through the online Permit Application Portal
  • RequiredSite PlanShowing location of water meter and hydrants (if applicable) and labeled lengths of fencing
  • RequiredFence Example PhotoPhoto of the type of fence being installed
  • OptionalHOA ApprovalThe City does not enforce HOA rules on fences; it is the applicant's responsibility to ensure the fence complies with any HOA covenants

Fee schedule

Fee typeAmountNotes
Fence Permit Fee (Combined CED & Public Works Fees)$275Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024

Demolition Permit

Verified

Required for demolition of structures within the City of McCall. A final inspection by the Building Official is required, and the site must be returned to a safe and natural condition.

Verified 2026-07-07 · Source

Requirements

  • Demolition of any building, residence, or structure within the McCall Area requires a permit
  • Site must be brought back to a safe and natural condition after demolition
  • If the building is on Payette Lakes Recreational Water and Sewer District (PLRWSD) sewer service, the district must be contacted regarding disconnection guidance

Required documents

  • RequiredDemo Permit ApplicationSubmitted through the online Permit Application Portal
  • RequiredSafety PlanElectronic PDF safety plan for the demolition work
  • OptionalErosion Control PlanRequired if the property is within the Shoreline or River Environs Zone
  • OptionalDemo Guidelines FormRequired if the project is on City water service

Fee schedule

Fee typeAmountNotes
Demo Permit Fee (Combined CED & Public Works Fees)$200Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024

Solar Photovoltaic (PV) System Permit

Verified

Required for installation of residential and commercial/non-residential solar photovoltaic systems in McCall. The City issues the building/structural permit; a separate electrical permit for the wiring/inverter portion is issued by the Idaho Bureau of Occupational Licenses (IBOL/DOPL), a separate state agency.

Verified 2026-07-07 · Source

Requirements

  • A permit must be obtained prior to the start of any solar PV installation work
  • All Solar PV systems (residential, non-residential, commercial) require a McCall Solar Permit Application
  • A separate Electrical Permit from the Idaho Bureau of Occupational Licenses (IBOL) is also required — issued by a separate state agency, not the City
  • Panels/modules must be listed and labeled in accordance with UL 1703 (panels) and UL 1741 (inverters)
  • Idaho code requires a licensed Electrical Journeyman to complete installation beyond the converter/AC combiner box, unless exempt under Idaho Code section 54-1016
  • Structural calculations must be stamped and signed by an Idaho-licensed engineer evaluating existing roof adequacy for local design loads plus the solar equipment loads

Required documents

  • RequiredMcCall Solar Permit ApplicationSubmitted through the application portal; for new builds, include with the Building Permit Application
  • RequiredRoof PlanDrawn to scale, showing exact panel locations and required fire-fighter access clearances from roof edges/peak per the Residential Photovoltaic Panels & Modules Guide
  • RequiredOne-Line Electrical DiagramDepicting equipment location, voltage/current ratings, wire size, disconnect rating, and overcurrent protection ratings
  • RequiredStructural CalculationsStamped and signed by an Idaho-licensed engineer, evaluating roof structure adequacy for local design loads and solar equipment loads
  • RequiredManufacturer SpecificationsFor panels, inverters, racking, and other equipment, showing UL listing (UL 1703 for panels, UL 1741 for inverters, etc.)

Fee schedule

Fee typeAmountNotes
Solar PV Building PermitCalculated based on industry-standard project cost using the standard Building Permit fee table (Resolution 24-11)Use the City's Fee Calculator (XLSX) on the Building Permit Application Information page for an estimate

EV Charger / EVSE Permit

Verified

Installing a Level 1/Level 2 EV charging circuit in McCall is purely electrical work. The City of McCall's own Construction Information page states plainly that 'Permits and inspections for electrical, mechanical, plumbing, and fireplace installations (that are not wood burning or pellet inserts) are performed by the Idaho Division of Occupational and Professional Licenses' — so the electrical permit is issued directly by the State of Idaho DOPL, not the City. No City permit applies to a stand-alone EV charger circuit unless the installation also involves structural work. No EV-charger-specific line item exists on DOPL's published fee worksheet; a charger circuit added to an existing home is billed under DOPL's general 'Existing Residence' branch-circuit fee.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit required from the State of Idaho DOPL for the EV charger circuit/panel work — obtained via dbs.idaho.gov (all permits purchased online as of January 1, 2023)
  • Homeowners performing their own work on a primary/secondary residence may use DOPL's Homeowner Permit process; otherwise a licensed electrical contractor must pull the permit
  • No City of McCall building permit applies to a stand-alone EV charger circuit with no structural scope; if bundled with new construction or an addition, the City's applicable building-permit process would also apply to that structural scope, per City of McCall Building Permit Application Information and Resolution 24-11
  • All work must be inspected by DOPL's assigned state trade inspector for the McCall/Valley County area

Required documents

  • RequiredState of Idaho DOPL Electrical Permit Application (Homeowner or Contractor)Filed online at dbs.idaho.gov; no separate EV-charger-specific form exists

Fee schedule

Fee typeAmountNotes
DOPL Existing Residence — branch circuit addition$65.00 base fee (includes one circuit) plus $10.00 per additional branch circuit, up to the maximum of the corresponding square footage of the buildingIdaho DOPL Electrical Permit Worksheet (Homeowner), 'Existing Residence' category, revised 8/17/2022 — the applicable category for a typical EV charger circuit/subpanel added to an existing home; no EV-specific line item exists on the worksheet, confirmed by direct review of the same DOPL worksheet documented for other Idaho jurisdictions in this corpus (e.g., Malad City).

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the McCall building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

View current record →All versions →

Permalink: /idaho/valley-county/mccall/as-of/2026-07-07/

Snapshot date: 2026-07-07

Commit: af1def2

Reproducible from PermitBase’s version-controlled dataset, commit af1def2.