McCall building permits
VerifiedMcCall, Idaho — as published 2026-08-02.
Verified 2026-07-07 · Source
Codes adopted
Permit types & fees
New Residence in City Limits
VerifiedRequired for construction of a new single-family dwelling within McCall city limits. Covers structural construction, plan review, and coordination with Public Works for water/sewer connections.
Verified 2026-07-07 · Source
Requirements
- Applies to all new single-family dwellings within McCall city limits (a separate 'New Residence in Impact Area' process existed but the City stopped accepting Impact Area applications as of November 30, 2025)
- Structures greater than 3,500 square feet within city limits must include plans prepared by an Idaho-licensed architect (or an out-of-state architect with an Idaho practice agreement)
- Single-family residences exceeding 5,000 total square feet require Planning and Zoning Commission Design Review (minimum 45-day review period after a complete application, plus a pre-application conference and public hearing)
- Submit application, plans, and required forms through the online Permit Application Portal (app.govwell.com/mccall-id)
- A Public Works Permit application and Water Infrastructure Sizing Worksheet must be submitted for any project needing a City water/sewer connection
Required documents
- RequiredProject Information FormWorksheet required with the application; contact the Building Department for assistance if it cannot be completed
- RequiredMaintenance During Construction FormRequired construction site management plan per MCC 2.1.080(F)
- RequiredPublic Works Permit Application and Water Infrastructure Sizing WorksheetRequired for connection to City water/sewer infrastructure
- RequiredApplication and Contract for Water Utility ServiceRequired to establish water utility billing for the new residence
- RequiredConstruction Plans (electronic PDF)Site plan, landscape plan, footing/foundation plan, floor plans, wall bracing plan, elevations/wall sections, building sections, roof and framing detail, outdoor lighting plan, and residential energy code check (REScheck, LEED, or equivalent insulation specifications)
- RequiredStructural CalculationsRequired for all applications — calculations for all load-bearing footings, joists, beams, headers, rafters, and braced (shear) walls
- RequiredSewer Permit or Septic PermitFrom Payette Lakes Recreational Water and Sewer District (PLRWSD) if connecting to their system, or a septic permit from Central District Health Department otherwise
- OptionalHOA ApprovalRequired if the property is subject to HOA covenants
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit — valuation $1 to $500 | $23.50 | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024; permit fee calculated using 100% of project valuation |
| Building Permit — valuation $501 to $2,000 | $23.50 for the first $500, plus $3.05 for each additional $100 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$501 to $2,000' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Building Permit — valuation $2,001 to $25,000 | $69.25 for the first $2,000, plus $14 for each additional $1,000 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$2,001 to $25,000' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Building Permit — valuation $25,001 to $50,000 | $391.75 for the first $25,000, plus $10.10 for each additional $1,000 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$25,001 to $50,000' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Building Permit — valuation $50,001 to $100,000 | $643.75 for the first $50,000, plus $7 for each additional $1,000 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$50,001 to $100,000' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Building Permit — valuation $100,001 to $500,000 | $993.75 for the first $100,000, plus $5.60 for each additional $1,000 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$100,001 to $500,000' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Building Permit — valuation $500,001 to $1,000,000 | $3,233.75 for the first $500,000, plus $4.75 for each additional $1,000 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$500,001 to $1,000,000' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Building Permit — valuation $1,000,001 and up | $5,608.75 for the first $1,000,000, plus $3.65 for each additional $1,000 or fraction thereof | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees valuation table, page 9, '$1,000,001 and up' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
| Plan Review Fee | 65% of the calculated Building Permit fee | Resolution 24-11; due upon invoice and must be paid before plans enter the review queue |
| Re-inspection | $85 per additional inspection | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees table, page 9, 'Re-inspection' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
Remodel, Addition, or Accessory Structure Permit
VerifiedRequired for remodels, additions, and accessory structures (including garages and most ADUs) in McCall. Accessory structures 200 square feet or less used for non-living purposes (tool sheds, playhouses) are exempt from a building permit; accessory structures of any size containing living, sleeping, eating, cooking, or sanitation space require a permit.
Verified 2026-07-07 · Source
Requirements
- Remodels and additions to existing residences
- Accessory structures over 200 square feet (per Building Official Administrative Determination, 12/18/2023, applying 2020 Idaho Residential Code R105.2)
- Accessory structures of any size containing living, sleeping, eating, cooking, or sanitation space (including most Accessory Dwelling Units)
- Accessory structures over 1,500 square feet require Conditional Use Permit approval in addition to the building permit
- Submit application, plans, and required forms through the online Permit Application Portal (app.govwell.com/mccall-id)
Required documents
- RequiredProject Information FormWorksheet required with the application; contact the Building Department for assistance if it cannot be completed
- RequiredMaintenance During Construction FormRequired construction site management plan per MCC 2.1.080(F)
- OptionalWater Fixture WorksheetRequired if the accessory structure includes a separate City water connection, or if plumbing fixtures are being added/changed in the remodel or addition
- RequiredConstruction Plans (electronic PDF)Site plan, footing/foundation plan, floor plans, wall bracing plan, elevations/wall sections, roof and framing detail, outdoor lighting plan, and residential energy code check
- RequiredStructural CalculationsRequired for all applications — calculations for all load-bearing footings, joists, beams, headers, rafters, and braced (shear) walls
- OptionalSewer Permit or Septic PermitFrom Payette Lakes Recreational Water and Sewer District if connecting to their system, or Central District Health Department septic permit otherwise
- OptionalHOA ApprovalRequired if the property is subject to HOA covenants
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit — valuation-based per Resolution 24-11 schedule | Same valuation table as new residential construction: $23.50 (up to $500) through $5,608.75 + $3.65/$1,000 (over $1,000,000) | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024 |
| Plan Review Fee | 65% of the calculated Building Permit fee | Resolution 24-11 |
| Re-inspection | $85 per additional inspection | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees table, page 9, 'Re-inspection' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
Roof Permit
VerifiedRequired for reroofing and roof-related work in McCall. Governed by the Resolution 24-11 fee schedule (roof permit fee based on 50% of project valuation) and Ordinance 988 roof-covering and snow-country amendments.
Verified 2026-07-07 · Source
Requirements
- Reroofing (tear-off or overlay) of any structure in the city
- Roof covering must meet Class B or higher fire-retardant rating (Class A if wood shakes/shingles are used)
- Self-adhering polymer-modified bitumen ice barrier underlayment required on the entire roof, unless prohibited by the manufacturer's installation instructions
- Roof and attic vents must resist intrusion of flame and embers
Required documents
- RequiredRoof Permit ApplicationSubmitted through the online Permit Application Portal
- RequiredConstruction Plan FormRequired supplemental form for the roof permit application
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roof Permit — building permit fee | Calculated using 50% of project valuation against the standard Building Permit fee table (Resolution 24-11): $23.50 (up to $500) through $5,608.75 + $3.65/$1,000 (over $1,000,000) | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024 — 'Roof Permit: Permit Fee Use 50% of the valuation of the project to calculate the permit fee' |
| Plan Review Fee | 65% of the calculated Building Permit fee | Resolution 24-11 |
| Re-inspection | $85 per additional inspection | Resolution 24-11 Comprehensive Fee Schedule, July 25, 2024, Building Fees table, page 9, 'Re-inspection' row; carried forward unchanged in Resolution 25-17 FY26 Comprehensive Fee Schedule, July 24, 2025 |
Fence Permit
VerifiedRequired for installation of fences in McCall. Fences greater than 6 feet in height are not allowed anywhere in the city; fencing within 20 feet of the front property line is limited to 4 feet.
Verified 2026-07-07 · Source
Requirements
- Any new fence installation within the city
- Fences greater than 6 feet in height are not allowed
- Fencing within 20 feet of the front property line must not exceed 4 feet in height
- Chain link fencing is prohibited in most zones
- Fencing within commercial zones is prohibited with few exceptions
- Property pins must be located at the time of application when fencing along property lines
Required documents
- RequiredFence Building Permit ApplicationSubmitted through the online Permit Application Portal
- RequiredSite PlanShowing location of water meter and hydrants (if applicable) and labeled lengths of fencing
- RequiredFence Example PhotoPhoto of the type of fence being installed
- OptionalHOA ApprovalThe City does not enforce HOA rules on fences; it is the applicant's responsibility to ensure the fence complies with any HOA covenants
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fence Permit Fee (Combined CED & Public Works Fees) | $275 | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024 |
Demolition Permit
VerifiedRequired for demolition of structures within the City of McCall. A final inspection by the Building Official is required, and the site must be returned to a safe and natural condition.
Verified 2026-07-07 · Source
Requirements
- Demolition of any building, residence, or structure within the McCall Area requires a permit
- Site must be brought back to a safe and natural condition after demolition
- If the building is on Payette Lakes Recreational Water and Sewer District (PLRWSD) sewer service, the district must be contacted regarding disconnection guidance
Required documents
- RequiredDemo Permit ApplicationSubmitted through the online Permit Application Portal
- RequiredSafety PlanElectronic PDF safety plan for the demolition work
- OptionalErosion Control PlanRequired if the property is within the Shoreline or River Environs Zone
- OptionalDemo Guidelines FormRequired if the project is on City water service
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demo Permit Fee (Combined CED & Public Works Fees) | $200 | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024 |
Solar Photovoltaic (PV) System Permit
VerifiedRequired for installation of residential and commercial/non-residential solar photovoltaic systems in McCall. The City issues the building/structural permit; a separate electrical permit for the wiring/inverter portion is issued by the Idaho Bureau of Occupational Licenses (IBOL/DOPL), a separate state agency.
Verified 2026-07-07 · Source
Requirements
- A permit must be obtained prior to the start of any solar PV installation work
- All Solar PV systems (residential, non-residential, commercial) require a McCall Solar Permit Application
- A separate Electrical Permit from the Idaho Bureau of Occupational Licenses (IBOL) is also required — issued by a separate state agency, not the City
- Panels/modules must be listed and labeled in accordance with UL 1703 (panels) and UL 1741 (inverters)
- Idaho code requires a licensed Electrical Journeyman to complete installation beyond the converter/AC combiner box, unless exempt under Idaho Code section 54-1016
- Structural calculations must be stamped and signed by an Idaho-licensed engineer evaluating existing roof adequacy for local design loads plus the solar equipment loads
Required documents
- RequiredMcCall Solar Permit ApplicationSubmitted through the application portal; for new builds, include with the Building Permit Application
- RequiredRoof PlanDrawn to scale, showing exact panel locations and required fire-fighter access clearances from roof edges/peak per the Residential Photovoltaic Panels & Modules Guide
- RequiredOne-Line Electrical DiagramDepicting equipment location, voltage/current ratings, wire size, disconnect rating, and overcurrent protection ratings
- RequiredStructural CalculationsStamped and signed by an Idaho-licensed engineer, evaluating roof structure adequacy for local design loads and solar equipment loads
- RequiredManufacturer SpecificationsFor panels, inverters, racking, and other equipment, showing UL listing (UL 1703 for panels, UL 1741 for inverters, etc.)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Solar PV Building Permit | Calculated based on industry-standard project cost using the standard Building Permit fee table (Resolution 24-11) | Use the City's Fee Calculator (XLSX) on the Building Permit Application Information page for an estimate |
EV Charger / EVSE Permit
VerifiedInstalling a Level 1/Level 2 EV charging circuit in McCall is purely electrical work. The City of McCall's own Construction Information page states plainly that 'Permits and inspections for electrical, mechanical, plumbing, and fireplace installations (that are not wood burning or pellet inserts) are performed by the Idaho Division of Occupational and Professional Licenses' — so the electrical permit is issued directly by the State of Idaho DOPL, not the City. No City permit applies to a stand-alone EV charger circuit unless the installation also involves structural work. No EV-charger-specific line item exists on DOPL's published fee worksheet; a charger circuit added to an existing home is billed under DOPL's general 'Existing Residence' branch-circuit fee.
Verified 2026-07-20 · Source
Requirements
- Electrical permit required from the State of Idaho DOPL for the EV charger circuit/panel work — obtained via dbs.idaho.gov (all permits purchased online as of January 1, 2023)
- Homeowners performing their own work on a primary/secondary residence may use DOPL's Homeowner Permit process; otherwise a licensed electrical contractor must pull the permit
- No City of McCall building permit applies to a stand-alone EV charger circuit with no structural scope; if bundled with new construction or an addition, the City's applicable building-permit process would also apply to that structural scope, per City of McCall Building Permit Application Information and Resolution 24-11
- All work must be inspected by DOPL's assigned state trade inspector for the McCall/Valley County area
Required documents
- RequiredState of Idaho DOPL Electrical Permit Application (Homeowner or Contractor)Filed online at dbs.idaho.gov; no separate EV-charger-specific form exists
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| DOPL Existing Residence — branch circuit addition | $65.00 base fee (includes one circuit) plus $10.00 per additional branch circuit, up to the maximum of the corresponding square footage of the building | Idaho DOPL Electrical Permit Worksheet (Homeowner), Existing Residence category, revised 8/17/2022 -- the applicable category for a typical EV charger circuit or subpanel added to an existing home. The worksheet carries no EV-specific line item. |
Commercial Building Permit
Required for new commercial building construction and for any exterior alterations to existing commercial buildings within McCall city limits or the McCall Impact Area. Uses the same valuation-based Building Permit fee table as residential permits, but new or exterior commercial work also requires Design Review approval from the Planning and Zoning Commission (MCC 3.16.02), and some commercial uses require a Conditional Use Permit.
Reviewed 2026-08-02 · Source
Requirements
- Applies to new commercial building construction and to exterior alterations of existing commercial buildings within McCall city limits and the McCall Impact Area
- At a minimum, Design Review approval by the McCall Area Planning and Zoning Commission is required for commercial projects (MCC 3.16.02); the Commercial Building Checklist confirms Design Review is required for 'New or Exterior commercial work'
- Some commercial uses require a Conditional Use Permit (reviewed by Planning & Zoning and City Council, or the Valley County Commission in the Impact Area) — see the Allowed Use table (CC and CBD zones) in the Commercial Development Guide; uses not listed require a CUP
- Projects with condominium units or business suites under separate ownership require condominium platting through the Subdivision approval process
- A Planned Unit Development is required for projects over 2 acres in the CBD - Central Business District zone
- Architect (Idaho-licensed) stamped plans required for all commercial building permit applications
- MEP (mechanical/electrical/plumbing) engineering required
- Structural Calculations required for all applications — footings, joists, beams, headers, rafters, and braced/shear walls
- Commercial energy code compliance (COMcheck or other energy modeling) required
- New commercial development must include sidewalks, curbs/gutters, or pathways per the McCall Area Pathways Master Plan where not already present along the property frontage
- Off-street parking required per MCC 3.8.06(A) unless the property is within an established Improvement District; required parking-space counts vary by land use per MCC 3.8.062 (e.g., 1 space per 500 sq ft of floor area for offices, retail, and restaurants)
- Submit application, plans, and required forms through the online Permit Application Portal (app.govwell.com/mccall-id)
- A Public Works Permit application and Water Infrastructure Sizing Worksheet must be submitted when the project ties into City water or involves a driveway off a City-owned street
Required documents
- RequiredMaintenance During Construction FormRequired construction site management plan per MCC 2.1.080(F); e-submitted through the application portal
- OptionalPublic Works Permit Application and Water Infrastructure Sizing WorksheetRequired when the project ties into City water or includes a driveway off a City-owned street
- OptionalApplication and Contract for Water Utility ServiceRequired when applicable to establish water utility billing
- OptionalAuthorization for Automatic WithdrawalOptional autopay enrollment for the water bill
- RequiredArchitect (Idaho-licensed) Stamped PlansRequired for all commercial building permit applications
- RequiredStructural EngineeringStructural engineering plans; the checklist requires Structural Calculations (footings, joists, beams, headers, rafters, braced/shear walls) for all applications
- RequiredMEP EngineeringMechanical, electrical, and plumbing engineering plans
- RequiredSite PlanProposed and existing structure footprints, lot lines, setbacks, easements, water meter pit and sewer tap locations, significant trees (12"+) existing/removed, 2nd-stage gas regulator location (if propane), topo lines, driveway location/width/slope, culvert size, parking, walkways, decks, landscaping (MCC 3.8.13), lot coverage computation (MCC 3.03), and snow storage (MCC 3.8.15)
- RequiredCode Study & AnalysisOccupancy, exiting, construction type, allowable areas and heights, etc.
- RequiredFloor PlanOccupancy type, room use, egress, accessibility
- RequiredFooting and Foundation Plan/Detail
- RequiredElevations/Wall Sections
- RequiredBuilding Section(s)
- RequiredRoof Framing Detail
- RequiredOutdoor Lighting PlanPer MCC 3.14 (Dark Sky ordinance) — full cutoff luminaires, downcast and fully shielded; parking-area lights capped at 17 ft. in height
- RequiredCOMcheck (Commercial Energy Check Report)COMcheck or other energy modeling report
- OptionalPlanning & Zoning / Design Review ApprovalRequired for new or exterior commercial work, per the Commercial Building Checklist and MCC 3.16.02
- OptionalSewer Permit or Septic PermitFrom Payette Lakes Recreational Water and Sewer District (PLRWSD) if connecting to their system, or a septic permit from Central District Health Department otherwise
- OptionalHOA ApprovalRequired if the property is subject to HOA covenants
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit — valuation-based per Resolution 24-11 schedule | Same city-wide valuation table used for all building permits: $23.50 (up to $500) through $5,608.75 + $3.65/$1,000 (over $1,000,000) | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024, 'Building Fees' section — the fee table is not commercial-specific, it is the single city-wide Building Permit valuation table |
| Plan Review Fee | 65% of the calculated Building Permit fee | Resolution 24-11; due upon invoice, must be paid before plans enter the review queue |
| Design Review (DR) | $2,200 | Resolution 24-11, 'Planning & Zoning Fees' section; required for new or exterior commercial work per MCC 3.16.02 and the Commercial Building Checklist |
| Conditional Use Permit (CUP) | $3,500 | Resolution 24-11; required if the proposed commercial use is not directly permitted in the zone (see Allowed Use table in the Commercial Development Guide) |
| CBD Parking In-Lieu Fee (Central Business District only) | $10,000 per parking space omitted | Resolution 24-11 lists this as '$10,000 Per Space Omitted' (eff. Show full citationHideResolution 24-11 lists this as '$10,000 Per Space Omitted' (eff. July 25, 2024). NOTE: the City's separate Commercial Development Guide document states the in-lieu fee is 'currently $7500' — that guide is undated/older than the July 2024 resolution. This entry uses the Resolution 24-11 figure ($10,000) as the more current primary source, since it is the same fee-schedule source used for every other fee in this record; applicants should confirm the current amount with the Building Department. |
| Engineering Review | $100 | Resolution 24-11; billed hourly |
| Re-inspection | $85 per additional inspection | Resolution 24-11 |
Commercial Tenant Improvement (TI) / Interior Alteration Permit
VerifiedMcCall does not publish a separate tenant-improvement or commercial-remodel permit product. Interior build-outs and alterations of existing commercial space use the same Commercial Building Checklist, application portal, and valuation-based fee table as new commercial construction (see Commercial Building Permit). The key practical difference, from the Commercial Building Checklist itself: Design Review by the Planning and Zoning Commission is required only for 'New or Exterior commercial work,' not for interior-only alterations.
Verified 2026-08-02 · Source
Requirements
- Applies to interior remodels, build-outs, and alterations of existing commercial space that do not add to the building's exterior footprint or building envelope
- Uses the same Commercial Building Checklist and Permit Application Portal as new commercial construction — McCall does not publish a separate TI-specific checklist, permit type, or fee schedule
- Design Review by the Planning and Zoning Commission is NOT required for interior-only commercial alterations — the Commercial Building Checklist ties Design Review only to 'New or Exterior commercial work'
- If the new tenant's proposed use is not directly permitted in the zone (see the Allowed Use table — CC or CBD — in the Commercial Development Guide), a Conditional Use Permit is required regardless of whether any work is exterior
- Structural Calculations required where load-bearing elements (footings, joists, beams, headers, rafters, braced/shear walls) are affected by the scope of work
- MEP (mechanical/electrical/plumbing) engineering required where MEP systems are being modified
- Commercial energy code compliance (COMcheck or equivalent) required where the scope of work triggers IECC compliance
- Submit application, plans, and required forms through the online Permit Application Portal (app.govwell.com/mccall-id)
Required documents
- RequiredMaintenance During Construction FormRequired construction site management plan per MCC 2.1.080(F); e-submitted through the application portal
- RequiredArchitect (Idaho-licensed) Stamped PlansRequired per the Commercial Building Checklist, which does not distinguish new construction from alteration/TI work
- OptionalMEP EngineeringRequired where the scope of work affects mechanical, electrical, or plumbing systems
- RequiredFloor PlanOccupancy type, room use, egress, accessibility
- RequiredCode Study & AnalysisOccupancy, exiting, construction type, allowable areas and heights, etc.
- OptionalStructural CalculationsRequired where load-bearing footings, joists, beams, headers, rafters, or braced (shear) walls are affected
- OptionalCOMcheck (Commercial Energy Check Report)Required where the scope of work triggers commercial energy-code compliance
- OptionalPlanning & Zoning / Conditional Use Permit ApprovalRequired only if the tenant's proposed use requires a CUP under the Allowed Use table in the Commercial Development Guide — not triggered by interior work alone
- OptionalHOA ApprovalRequired if the property is subject to HOA covenants
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit — valuation-based per Resolution 24-11 schedule | Same city-wide valuation table used for all building permits: $23.50 (up to $500) through $5,608.75 + $3.65/$1,000 (over $1,000,000) | Resolution 24-11 Comprehensive Fee Schedule, eff. July 25, 2024, 'Building Fees' section — same table applies to new construction and to alterations/TI; there is no separate TI fee line |
| Plan Review Fee | 65% of the calculated Building Permit fee | Resolution 24-11 |
| Conditional Use Permit (CUP) | $3,500 | Resolution 24-11; only required if the tenant's proposed use is not directly permitted in the zone per the Allowed Use table in the Commercial Development Guide |
| Re-inspection | $85 per additional inspection | Resolution 24-11 |
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fee schedules
Applications & forms
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the McCall building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.