Hardin building permits

Verified

Hardin, Montana — as published 2026-07-07.

Verified 2026-07-03 · Source

Codes adopted

Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; non-certified trades — and, where a city's Building certification is itself partial (e.g. residential-only), non-certified project types — fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs (bsd.dli.mt.gov/building-codes-permits).Hardin is a Montana DLI-certified jurisdiction for Building (B), RESIDENTIAL ONLY, within city limits; certified official on file with DLI: Joseph Connolly (listed on City of Hardin's own site as 'Joe Connelly'), (406) 665-9264. Verified directly against the DLI Building Codes Bureau's 'Montana Certified Local Government Program' roster PDF, updated 04/22/2026 (fetched and text-extracted directly from the source PDF): 'Hardin | B (residential only) | Joseph Connolly | 665-9264 | City Limits'. This is a NARROWER certification than the B-only-but-all-project-types pattern seen in Choteau/Conrad/Cut Bank/Glasgow/Lewistown/Red Lodge — Hardin's own certification does not cover COMMERCIAL building work at all, meaning commercial building permits in Hardin route to the state DLI Building Codes Bureau exactly as they would in a non-certified jurisdiction, in addition to Electrical/Plumbing/Mechanical for all project types. Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdfHardin, MT Code of Ordinances, Title 4 Building Regulations, Chapter 1 Building Codes (current through Ord. 2025-04, passed 12-4-2025) contains three sections: 4-1-1 Adoption Of Codes And Regulations, 4-1-2 Building Code Adopted, and 4-1-3 Other Codes Enforced By State Officials — a notably thin chapter (no locally-authored fee schedule or plan-review-timeline section), consistent with a small, partially-certified jurisdiction that enforces state-adopted code editions rather than authoring independent code text or a distinct administrative process. Section 4-1-3's title ('Other Codes Enforced By State Officials') is itself corroborating evidence of the residential-only/state-routed-commercial split described by the DLI roster. Source: https://codelibrary.amlegal.com/codes/hardinmt/latest/hardin_mt/0-0-0-994Per the Montana DLI Building Codes Bureau's Current Codes page (statewide effective date June 11, 2022, applicable uniformly to all certified and state-enforced jurisdictions): 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 ISPSC, 2021 UPC, 2020 NEC, 2017 ICC A117.1 Accessibility. Hardin's own Building Permit Application form cites Title 50, Chapter 60, Section 104, MCA and ARM 24.301.131 (the same statutory/administrative basis as the state's own BCP-1 form), consistent with a residential-certified jurisdiction enforcing the state-adopted editions without independently amended local code text. Source: bsd.dli.mt.gov/building-codes-permits/current-codes; City of Hardin Building Permit Application PDF (hardinmontana.info/Building_Permit_application011019.pdf)

Permit types & fees

Residential Building Permit (New Construction / Addition / Alteration / Re-Roof)

Verified

Required for new single-family/two-family home construction, additions, alterations, and re-roofing on RESIDENTIAL property within Hardin city limits. Issued by the City of Hardin under its DLI certification for Building (B), RESIDENTIAL ONLY, reviewed by Building Inspectors Joe Connelly and Nathan McConnell against the state-adopted 2021 IBC/IRC/IECC editions. This certification does NOT extend to commercial building work — see the separate commercial-building-permit-state entry.

Verified 2026-07-03 · Source

Requirements

  • Complete the City of Hardin Application For Building Permit: property address, county, whether the job is inside city limits, 17-digit GEOCODE, parcel number, lot/block, section/township/range, property owner and general contractor/design professional contact information
  • Select Type of Work: Addition, ReRoofing, Other, Emergency Repair, Fire Suppression, Change of Use, New Construction, Moved Building, or Alteration/Remodel
  • Provide project valuation
  • Electronic plan submittal is preferred per the City's own application form
  • Applicant must indicate 'Primary Contact' as Owner, General Contractor, or Designer
  • The application form itself flags 'Other Work Being Done On Site' checkboxes for Boiler, Elevator, Plumbing, Electrical, Mechanical, and HVAC — these are separate state-issued permit types and are NOT covered by this city-issued residential building permit

Required documents

  • RequiredApplication For Building PermitCity of Hardin residential building permit application (a City-branded reformatting of the state BCP-1 template); available at hardinmontana.info/Building_Permit_application011019.pdf or via the City of Hardin Citizen Portal (hardinmt2.portal.iworq.net/portalhome/hardinmt2)
  • RequiredConstruction PlansElectronic plan submittal preferred per the City's application form instructions

Fee schedule

Fee typeAmountNotes
Residential building permit feeNo fixed valuation-based fee table was found published on hardinmt.com, hardinmontana.info, or in the City's downloadable Building Permit Application form (which has a blank 'PROJECT VALUATION' field but no printed fee schedule) as of this review — an honest publication gap after direct review of the City's own permit materials, not an inferred or invented figure. Applicants must contact the Building Department at (406) 665-9260 Ext. 106 for a current fee quote.

Accessory Building Permit (Residential and Business)

Verified

Required for accessory structures (sheds, detached storage buildings, etc.) in Hardin. The City publishes a dedicated Application For Business Accessory Building for accessory structures on business/commercial property, governed by Hardin City Code 11-1-8-2, which caps accessory buildings at 200 square feet without a Variance Request. Residential accessory structures fall under the general residential-building-permit process.

Verified 2026-07-03 · Source

Requirements

  • Per Hardin City Code 11-1-8-2: the accessory building must not exceed 200 square feet; if larger, a Variance Request Form Application must also be submitted
  • A scale map is required showing dimensions, acreage, parking, main structure, intended location of the accessory structure, and the property location
  • A description of the water and sewer system serving the accessory structure is required
  • A design of the building and a picture of the structure (for existing/relocated structures) must be attached
  • Written authorization from the property owner is required if the applicant is not the owner
  • Applicant must appear before the Common Council when the application is considered
  • Applicant certifies that all State, County, and Local laws will be followed

Required documents

  • RequiredApplication For Business Accessory BuildingCity of Hardin form for accessory structures on business/commercial property, citing Hardin City Code 11-1-8-2; available at hardinmontana.info/Accessory_Building_Permit_010226.pdf
  • RequiredScale MapSite plan showing dimensions, acreage, parking, main structure, and proposed accessory structure location
  • OptionalVariance Request Form ApplicationRequired only if the proposed accessory building exceeds 200 square feet

Fee schedule

Fee typeAmountNotes
Accessory building permit / application feeNo fixed fee amount is printed on the City's Application For Business Accessory Building form or published elsewhere on hardinmt.com/hardinmontana.info as of this review. Contact the Building Department at (406) 665-9260 Ext. 106 (or the general city line, (406) 665-9260 Ext. 104) for a current quote.

Commercial Building Permit (State-Issued)

Verified

Because Hardin's DLI certification for Building covers RESIDENTIAL work only, any commercial building project within Hardin city limits — new construction, addition, alteration — requires a Building Permit/Plan Review Application issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Hardin, under the 2021 IBC.

Verified 2026-07-03 · Source

Requirements

  • Submit a Building Permit/Plan Review Application together with complete construction plans to the Building Codes Bureau
  • Plan review fee is generally 1%-2% of building valuation, calculated by the Bureau after initial screening
  • A state building permit must be obtained before construction begins; starting construction beforehand may result in an investigation fee and required corrective construction
  • Building permits must be issued before related Plumbing, Mechanical, or Electrical permits can be issued or that work can begin
  • Design professionals are encouraged for complex projects; complete plans expedite review
  • Apply in accordance with Title 50, Chapter 60, MCA and ARM Title 24, Chapter 301

Required documents

  • RequiredBuilding Permit/Plan Review ApplicationMontana Building Codes Bureau statewide form; mailed with payment to Building and Commercial Measurements Bureau, PO Box 200517, Helena, MT 59602, or filed online at BuildingPermits.Mt.Gov
  • RequiredConstruction PlansComplete construction plans and details (site plan, floor plan, accessibility/restroom details, wall sections) are required and expedite plan review per the Bureau's own guidance

Fee schedule

Fee typeAmountNotes
Building Permit/Plan Review FeeGenerally 1%-2% of building valuation, calculated by the Building Codes Bureau after screeningMontana DLI Building Codes Bureau, 'Is a State Building Permit Needed?' guidance page — this is the Bureau's own stated fee-calculation method for state-issued building permits, which governs Hardin's commercial building projects since Hardin's own certification does not cover commercial building work

Electrical Permit (State-Issued)

Verified

Because Hardin holds no DLI certification in Electrical (only a residential-only Building certification), electrical work anywhere within Hardin city limits — residential or commercial — requires a Residential or Commercial Electrical Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Hardin, under the 2020 NEC.

Verified 2026-07-03 · Source

Requirements

  • Application must be signed and dated by the licensed electrical contractor's person in charge, or filed as a homeowner permit for owner-performed work
  • Payment must be submitted with the application; incomplete applications are returned unprocessed
  • Property address, GEOCODE/parcel/lot/block, owner information, and power company must be provided
  • Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431

Required documents

  • RequiredApplication for Residential Electrical PermitMontana Building Codes Bureau statewide form; mailed with payment to Building Codes Program, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov / BuildingPermits.Mt.Gov

Fee schedule

Fee typeAmountNotes
Single Family Dwelling or Cabin — up to 200-amp service (includes meter base and attached garages if wired at the same time)$200Montana Building Codes Bureau, Application for Residential Electrical Permit (Rev. 12/22) — the same statewide fee schedule applied to all non-electrically-certified Montana jurisdictions; cross-verified against the identical schedule already confirmed for Choteau, MT and Conrad, MT in this same dataset
Single Family Dwelling or Cabin — 201 to 400-amp service$380Application for Residential Electrical Permit (Rev. 12/22)
Residential Change of Service — exterior meter base & interior/exterior main disconnect only$45Application for Residential Electrical Permit (Rev. 12/22)

Plumbing Permit (State-Issued, incl. Water Heater)

Verified

Because Hardin holds no DLI certification in Plumbing (only a residential-only Building certification), plumbing work anywhere within Hardin city limits — including water heater installation/replacement, residential or commercial — requires a Plumbing Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Hardin, under the 2021 Uniform Plumbing Code.

Verified 2026-07-03 · Source

Requirements

  • Application must be signed by the Master Plumber and include the Master Plumber License Number, or filed as a homeowner permit for owner-performed work where allowed
  • Property address, county, and whether the job is inside city limits must be indicated
  • Type of Building and Type of Work must be indicated; sewer service type (public/septic) and potable water source must be indicated
  • Apply in accordance with Title 50, Chapter 60, Section 505, MCA and ARM 24.301.301 / 24.301.361

Required documents

  • RequiredApplication for Plumbing PermitMontana Building Codes Bureau statewide form (BCP-1); mailed with payment to Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov / BuildingPermits.Mt.Gov

Fee schedule

Fee typeAmountNotes
Each NEW water heater (or replacement)$25Montana Building Codes Bureau, Application for Plumbing Permit (BCP-1) statewide Fee Schedule — the same schedule applied to all non-plumbing-certified jurisdictions; cross-verified against the identical schedule already confirmed for Choteau, MT and Conrad, MT in this same dataset
Each plumbing fixture or trap$10 per fixture/trapApplication for Plumbing Permit (BCP-1) statewide Fee Schedule

Mechanical / HVAC Permit (State-Issued)

Verified

Because Hardin holds no DLI certification in Mechanical (only a residential-only Building certification), mechanical/HVAC work anywhere within Hardin city limits — residential or commercial — requires a Mechanical Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Hardin, under the 2021 International Mechanical Code and International Fuel Gas Code.

Verified 2026-07-03 · Source

Requirements

  • Project Value must be provided; permit fee is calculated from the state's valuation-based fee schedule
  • Type of Building and Type of Work must be indicated
  • Boiler work requires a separate Boiler Permit form, not the Mechanical Permit
  • Apply in accordance with Title 50, Chapter 60, Section 104, MCA and ARM 24.301.172

Required documents

  • RequiredApplication for Mechanical PermitMontana Building Codes Bureau statewide form (BCP-1); mailed with payment to Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov / BuildingPermits.Mt.Gov

Fee schedule

Fee typeAmountNotes
Mechanical Permit — Project value $0-$10,000$48 for the first $1,000, plus $14 for each additional $1,000 or fraction thereofMontana Building Codes Bureau, Application for Mechanical Permit (BCP-1) statewide Fee Schedule — the same schedule applied to all non-mechanically-certified jurisdictions; cross-verified against the identical schedule already confirmed for Choteau, MT and Conrad, MT in this same dataset

Demolition / Building Removal Permit

Verified

Required for demolishing or removing a structure within Hardin city limits, using the City's residential-building-permit process (Type of Work checkboxes on the same Application For Building Permit include 'Moved Building' and 'Other', the latter used with a full description of work for demolition scope) for residential property; commercial demolition follows the state-routed process since Hardin's certification excludes commercial building work.

Verified 2026-07-03 · Source

Requirements

  • Type of Work box 'Other' checked on the Application For Building Permit with a full description of the demolition scope attached, or 'Moved Building' for relocating a structure
  • Project valuation (prior value and completed/post-project value) must be provided
  • Property address, GEOCODE, parcel/lot/block information required as with any other permit type on this form
  • For commercial structures, submit instead to the Montana DLI Building Codes Bureau since Hardin's certification does not cover commercial building work

Required documents

  • RequiredApplication For Building Permit (Other/Moved Building)Same City of Hardin form used for all residential building/zoning work, with 'Other' or 'Moved Building' selected and a full work-scope description attached

Fee schedule

Fee typeAmountNotes
Demolition/building permit feeNo fixed table was found published on hardinmt.com, hardinmontana.info, or the City's Building Permit Application form; no dedicated demolition bond amount (comparable to Billings' $10,000 site bond) was found published for Hardin either. Contact the Building Department at (406) 665-9260 Ext. 106 for current requirements and fees, since this is a small jurisdiction without Billings-scale published demolition procedures.

Solar Photovoltaic (PV) Permit

Verified

Required for installation of rooftop or ground-mount solar photovoltaic systems within Hardin city limits. For a RESIDENTIAL installation: a City Building Permit (structural/racking, issued by the City's Building Inspectors) plus a State of Montana Electrical Permit (wiring/interconnection) -- Hardin is city-certified for residential Building permits only. For a COMMERCIAL installation: BOTH the building permit and the electrical permit are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, since Hardin's local certification does not extend to commercial building work or to any electrical/plumbing/mechanical permits of any project type.

Verified 2026-07-20 · Source

Requirements

  • Residential solar: City Building Permit Application (structural/racking scope) submitted to City Building Inspectors Joe Connelly or Nathan McConnell
  • Residential solar electrical scope: State of Montana Application for Residential Contractor Electrical Permit -- Hardin is not certified for electrical permitting of any project type
  • Commercial solar: BOTH the building permit and electrical permit are issued directly by the Montana Building Codes Bureau, not the City, per Hardin's certification (residential building only)
  • Licensed electrical contractors select 'Solar' as the Alternative Energy Source on the state electrical application and specify Micro Inverter/AC Module System or PV String System, and whether the system produces 90 or more volts
  • Non-electrician installers submit the state's Alternate Energy Permit instead of the standard contractor electrical permit, per Montana Building Codes Bureau Alternative Energy Information guidance

Required documents

  • RequiredCity of Hardin Application For Building PermitFor the residential structural/racking scope only; commercial building goes through the state instead
  • RequiredMontana Application for Residential (or Commercial) Contractor Electrical PermitState of Montana Building Codes Bureau form; includes an Alternative Energy Source section (Solar/Wind/Hydro checkbox, system type, voltage)

Fee schedule

Fee typeAmountNotes
City Residential Building Permit FeeNo fixed valuation-based fee table was found published on hardinmt.com, hardinmontana.info, or in the City's downloadable Building Permit Application form, consistent with this corpus's existing residential-building-permit entry for Hardin, which documents this same unresolved gap. Contact the Building Department at (406) 665-9260 Ext. 106 for a current quote.
State Electrical Permit -- Alternative Energy (residential, by licensed contractor)$45Montana Building Codes Bureau, Application for Residential Contractor Electrical Permit (Rev 6/24), line item K 'Alternative Energy' -- applies to Hardin since the City is not certified for electrical permitting of any project type
Commercial Building Permit/Plan Review Fee (state-issued, applies to commercial solar)Generally 1%-2% of building valuation, calculated by the Building Codes Bureau after screeningMontana DLI Building Codes Bureau, 'Is a State Building Permit Needed?' guidance page -- consistent with this corpus's existing commercial-building-permit-state entry for Hardin, since Hardin's certification does not cover commercial building work
State Electrical Permit -- Commercial (valuation-based, includes solar)$45 for the 1st $500 plus 6% of balance (projects $0-$1,000); $75 for the 1st $1,000 plus 2% of balance ($1,001-$10,000); $255 for the 1st $10,000 plus 0.5% of balance ($10,000-$50,000); $455 for the 1st $50,000 plus 0.3% of balance ($50,001+)Montana Building Codes Bureau, Application for Commercial Electrical Permit (Rev 6/24) -- includes a dedicated Alternative Energy Source (Solar/Wind/Hydro) question set

EV Charger / EVSE Permit

Verified

Because Hardin holds no DLI certification in Electrical (only a residential-only Building certification), EV charger circuit work anywhere within Hardin city limits -- residential or commercial -- requires an Electrical Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Hardin, under the 2020 NEC. The state's Application for Residential Electrical Permit (Rev. 11/25) has no dedicated EV/EVSE line item -- it lists an 'Alternative Energy' line (K, $45) that only covers Solar/Wind/Hydro generation, not vehicle-charging loads. A single EV charger circuit added to an existing home instead falls under line H, '1 additional circuit or piece of equipment' ($45), the same category used for a hot tub or A/C circuit.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit issued by the Montana DLI Building Codes Bureau (Helena), not the City of Hardin, per Title 50, Chapter 60, Section 604 MCA and ARM 24.301.431
  • No EV/EVSE-specific line item exists on the state's Residential or Commercial Electrical Permit application -- do NOT check the 'Alternative Energy Source' box, which is scoped to Solar/Wind/Hydro generation systems, not EV charging
  • A single charger circuit added to an existing single-family home falls under line H, '1 additional circuit or piece of equipment'
  • New-construction wiring for a charger circuit is included in the applicable new-dwelling amperage-tier fee (lines A-D)
  • Larger, multi-unit, or commercial charger installations use the Commercial Electrical Permit's valuation-based tiers

Required documents

  • RequiredApplication for Residential Electrical Permit (or Commercial Electrical Permit for larger projects)Montana Building Codes Bureau statewide form (Rev. 11/25); mailed with payment to Building Codes Program, PO Box 200517, Helena, MT 59620-0517, or filed online via aca-prod.accela.com/bcb

Fee schedule

Fee typeAmountNotes
Single-family interior/exterior wire or rewire -- 1 additional circuit or piece of equipment (applies to a single EV charger circuit added to an existing home)$45Montana Building Codes Bureau, Application for Residential Electrical Permit, line H (Rev. 11/25) -- same category used for a hot tub or A/C circuit; no dedicated EV/EVSE line item exists
Commercial Electrical Permit -- valuation-based (for larger/commercial charger installs)$45 for the 1st $500 plus 6% of balance ($0-$1,000); $75 for the 1st $1,000 plus 2% of balance ($1,001-$10,000); $255 for the 1st $10,000 plus 0.5% of balance ($10,001-$50,000); $455 for the 1st $50,000 plus 0.3% of balance ($50,001+)Montana Building Codes Bureau, Application for Commercial Electrical Permit (Rev 6/24)

Sign Regulations Compliance (No Standalone Sign Permit Published)

Verified

Hardin City Code 11-1-8-3 (Sign Regulations, part of Title 11 Zoning, Chapter 1) establishes substantive size, placement, and attachment standards for signs by zoning district. Direct review of the City's Permits/Forms page (which lists every downloadable PDF form the City publishes) and the general Application For Building Permit's Type of Work checkbox list found no standalone sign-permit application, fee schedule, or dedicated form -- an honest publication gap, not an invented omission. Sign compliance in Hardin appears to be enforced through the City's general, complaint-driven Code Enforcement process rather than a proactive permit-application gate.

Verified 2026-07-22 · Source

Requirements

  • R District: churches, public and semi-public buildings, hospitals, and institutions may have one bulletin board not more than fifteen (15) square feet in area
  • R District: temporary signs pertaining to lease or sale of premises must not exceed ten (10) square feet; nonilluminated nameplates must not exceed one (1) square foot (an R2 District nameplate may be up to four (4) square feet)
  • C Districts: total sign area on a premises may not exceed two (2) square feet of sign for each lineal foot of street frontage of that premises
  • C Districts: every sign must be either (1) attached to a building and not extending more than five feet (5') over the property line, or (2) located wholly on privately owned property without extending over the property line or any adjacent right of way, or (3) approved in writing as an encroachment by the City Council
  • No City-published sign-permit application, fee, or standalone review process was found; confirm current requirements directly with the City before installing a sign in a C District, since the encroachment-approval path (option 3 above) requires City Council action

Required documents

  • OptionalNo dedicated Sign Permit application publishedNot among the PDFs listed on the City's Permits/Forms page (hardinmt.com/Permits-Forms.html) as of this review; a wall-mounted commercial sign's attachment method could plausibly fall under the general Application For Building Permit's 'Other' Type of Work checkbox, but this is not stated anywhere in the Sign Regulations ordinance itself and is not confirmed as a requirement

Fee schedule

Fee typeAmountNotes
Sign permit / review feeNo fee amount is published on hardinmt.com, hardinmontana.info, or in Hardin City Code 11-1-8-3 as of this review -- an honest publication gap after direct review of the ordinance text and the City's Permits/Forms page, not an inferred or invented figure.

Fire Sprinkler (Fire Suppression) and Fire Alarm Permit

Verified

Hardin holds no Montana DLI certification in Fire (its only certification is Building (B), RESIDENTIAL ONLY) and has no local Fire Marshal -- confirmed there is no dedicated, separately-fee-scheduled 'Fire Sprinkler/Alarm Permit' product published by the City. Fire SUPPRESSION (sprinkler) work is instead processed through the same general Application For Building Permit used for all other Hardin building work: 'Fire Suppression' is an explicit Type of Work checkbox on both the City's own form and the underlying Montana BCP-1 statewide template it is based on (confirmed by direct read of the current PDF) -- residential-scope sprinkler work goes to the City (Joe Connelly / Nathan McConnell), commercial-scope sprinkler work goes to the state DLI Building Codes Bureau in Helena, mirroring the same residential/commercial split as Hardin's other building permits. Fire ALARM system wiring has no dedicated line item on either the current Montana Residential or Commercial Electrical Permit fee schedules (confirmed by direct read of both PDFs) and, since Hardin holds no Electrical certification at all, is billed under the same general state Electrical Permit valuation/circuit-based fee tiers as any other electrical work. Montana has adopted the 2021 International Fire Code statewide via ARM 23.12.601, administered by the Montana DOJ Office of the State Fire Marshal (not the DLI Building Codes Bureau) -- but direct review of the State Fire Marshal's own 'Fire Prevention and Investigations' page shows its published functions are inspection certification, code-adoption assistance, and fire investigation, not a separate SFMO-issued sprinkler/alarm permit with its own fee schedule comparable to larger Montana cities' locally-issued fire-alarm-and-sprinkler permits (e.g. Great Falls). No such Hardin-specific or SFMO-specific fire permit fee was found published.

Verified 2026-07-22 · Source

Requirements

  • Fire suppression (sprinkler) work: check the 'Fire Suppression' box under Type of Work on the Application For Building Permit -- submit to the City of Hardin Building Department for residential-scope work, or mail to the Montana DLI Building Codes Bureau (PO Box 200517, Helena, MT 59620-0517) for commercial-scope work, since Hardin's certification does not cover commercial building work
  • Fire alarm system wiring: apply for a state Residential or Commercial Electrical Permit (Hardin holds no Electrical certification of any project type) -- there is no dedicated 'fire alarm' line item, so the fee is calculated from the same general valuation/circuit-based tiers used for any other electrical work
  • Commercial/public-building fire protection systems are subject to the 2021 International Fire Code as adopted statewide by Montana (ARM 23.12.601), administered by the Montana DOJ Office of the State Fire Marshal
  • No separate Hardin-specific or Montana State Fire Marshal-specific sprinkler/alarm permit application or fee schedule was found published -- confirm current requirements directly with the City Building Department and, for commercial projects, the Montana Building Codes Bureau and/or Office of the State Fire Marshal

Required documents

  • RequiredApplication For Building Permit (Fire Suppression checkbox)Same City of Hardin / state BCP-1-derived form used for all other building work, with 'Fire Suppression' selected under Type of Work
  • RequiredApplication for Residential or Commercial Electrical PermitMontana Building Codes Bureau statewide form, used for fire alarm system wiring since no dedicated fire-alarm permit exists; mailed to PO Box 200517, Helena, MT 59620-0517, or filed online via ebiz.mt.gov/bcb

Fee schedule

Fee typeAmountNotes
Fire Suppression (sprinkler) building-permit feeNo fixed fee table was found published on hardinmt.com, hardinmontana.info, or the City's Building Permit Application form -- the same publication gap already documented for Hardin's residential-building-permit entry, since Fire Suppression is processed as a Type of Work option on that same form rather than a separate product.
Fire alarm wiring -- billed under general state Electrical Permit valuation tiers$45 for the 1st $500 plus 6% of balance ($0-$1,000); $75 for the 1st $1,000 plus 2% of balance ($1,001-$10,000); $255 for the 1st $10,000 plus 0.5% of balance ($10,001-$50,000); $455 for the 1st $50,000 plus 0.3% of balance ($50,001+), commercial schedule (Rev 6/24); a comparable residential tiered schedule applies for residential-scope alarm wiringMontana Building Codes Bureau, Application for Commercial Electrical Permit (Rev 6/24) and Application for Residential Electrical Permit -- neither current PDF contains a dedicated 'fire alarm' or 'life safety' line item, so alarm wiring is billed under the same general valuation/circuit-based tiers as any other electrical work, confirmed by direct read of both current forms.

Change Of Use Permit (No Standalone Certificate Of Occupancy)

Verified

'Change of Use' is an explicit Type of Work checkbox on the same general Application For Building Permit used for all other Hardin building work (confirmed by direct read of the current PDF) -- there is no standalone change-of-use application, fee, or Certificate of Occupancy document published separately by the City. The form additionally requires a mandatory free-text 'detailed description of the project use and occupancy... before application is accepted' regardless of which Type of Work box is checked. For residential property, submit to the City of Hardin Building Department under Hardin's residential Building certification; for commercial property, Hardin's certification does not cover commercial building work at all, so a change-of-use submission routes to the Montana DLI Building Codes Bureau's BCP-1 Building Permit/Plan Review Application in Helena instead (same 'Change of Use' checkbox), consistent with this corpus's existing commercial-building-permit-state entry for Hardin. No dedicated 'Certificate of Occupancy' form or process was found among the City's downloadable Permits/Forms PDFs.

Verified 2026-07-22 · Source

Requirements

  • Check the 'Change of Use' box under Type of Work on the Application For Building Permit
  • Provide a detailed description of the project's proposed use and occupancy -- the form states this information 'must be submitted' before the application will be accepted, regardless of Type of Work selected
  • Residential-scope change of use: submit to the City of Hardin Building Department (406 N. Cheyenne Ave, or the Citizen Portal)
  • Commercial-scope change of use: submit to the Montana DLI Building Codes Bureau (PO Box 200517, Helena, MT 59620-0517, or BuildingPermits.Mt.Gov), since Hardin's own certification does not cover commercial building work
  • No standalone Certificate of Occupancy document or fee was found published by the City -- confirm with the Building Department whether any additional sign-off is issued upon completion

Required documents

  • RequiredApplication For Building Permit (Change of Use checkbox)Same City of Hardin / state BCP-1-derived form used for all other building work, with 'Change of Use' selected under Type of Work and a required written description of the proposed use/occupancy

Fee schedule

Fee typeAmountNotes
Change of use / building permit feeNo fixed fee table was found published on hardinmt.com, hardinmontana.info, or the City's Building Permit Application form -- the same publication gap already documented for Hardin's residential-building-permit entry, since Change of Use is processed as a Type of Work option on that same form rather than a separate product. Contact the Building Department at (406) 665-9260 Ext. 106 for a current quote.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hardin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-04)View current record →All versions →

Permalink: /montana/big-horn-county/hardin/as-of/2026-07-07/

Snapshot date: 2026-07-07

Commit: 371a356

Reproducible from PermitBase’s version-controlled dataset, commit 371a356.