Inspection sequence, scheduling, and re-inspection fees for building permits in Missoula, Montana.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
435 Ryman St., Missoula, MT 59802
Phone
(406) 552-6630
Office hours
Permit/application questions: Mon–Fri 9:00 AM–4:00 PM, (406) 552-6060, coordinators@ci.missoula.mt.us. Building code questions: Mon–Fri 8:00 AM–5:00 PM, (406) 552-6630, BLDG@ci.missoula.mt.us. Inspection scheduling: (406) 552-6040 or text (888) 413-4439.

Published scheduling rules

  • Rough mechanical, electrical, and plumbing inspections must pass BEFORE a framing inspection can be scheduled. (Residential Building Permit (New Construction))
  • Schedule inspections by 4:00 PM the day before, via phone (406-552-6040), text (888-413-4439), or the online portal; work must be ready for inspection by 7:00 AM. (Residential Building Permit (New Construction))
  • Rough mechanical, electrical, and plumbing inspections must all pass BEFORE a framing inspection can be scheduled on new residential construction. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing and Foundation

    Before concrete pour

  2. 2

    Framing/Structural

    Requires rough mechanical, electrical, and plumbing inspections to be completed and passed first

  3. 3

    Mechanical (Rough)

    Ductwork and equipment rough-in before wall cover; must pass before framing inspection

  4. 4

    Plumbing (Rough)

    Pipe rough-in before wall cover; must pass before framing inspection

  5. 5

    Electrical (Rough)

    Wiring rough-in before wall cover; must pass before framing inspection

  6. 6

    Insulation

    Before drywall installation

  7. 7

    Drywall (fire-rated walls)

    Verification of fire-rated assemblies before finish

  8. 8

    Roofing

    Roof covering installation

  9. 9

    Siding

    Exterior siding installation

  10. 10

    Final

    Required on all permits; all work complete per approved plans

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Footing and Foundation

    Before concrete pour (detached ADU)

  2. 2

    Framing/Structural

    Structural framing, egress, fire separation

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before wall cover

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Residential Addition / Remodel / Alteration Permit

  1. 1

    Framing/Structural

    After framing complete, before wall cover

  2. 2

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before wall cover; separate trade permits required

  3. 3

    Final

    Required on all permits

Applies to: Residential Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping

  2. 2

    Rough-In

    Ductwork and mechanical equipment before wall cover

  3. 3

    Final

    Equipment operational, venting and combustion air verified

Applies to: Change-of-Use Permit / Certificate of Occupancy

  1. 1

    Final Building Inspection

    Verifies the changed occupancy/use complies with adopted building codes; required before a Certificate of Occupancy can be requested

  2. 2

    Fire Final Inspection (Commercial Only)

    Commercial properties must pass a final fire inspection before CO issuance; schedule using inspection code 191. Residential properties do not require this inspection.

Applies to: Electric Vehicle (EV) Charger Permit

  1. 1

    Rough-In

    New wiring/circuit inspected before wall cover, if applicable

  2. 2

    Final

    Charger circuit, disconnect, and connections verified per 2020 NEC

Applies to: Fire Alarm System Permit

  1. 1

    Alarm Rough-In / Wiring

    Device and wiring rough-in inspected before concealment

  2. 2

    Fire Alarm Final

    System tested and verified operational, including device activation and monitoring-company connection; required before Certificate of Occupancy issuance

Applies to: Fire Sprinkler System Permit

  1. 1

    Sprinkler Rough-In / Cover

    Piping and system components inspected before concealment

  2. 2

    Fire Sprinkler Final

    System tested and verified operational; required before Certificate of Occupancy issuance

Applies to: Residential Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before wall cover

  2. 2

    Final

    Devices, panel labeling, and protection verified per 2020 NEC

Applies to: Residential Plumbing Permit

  1. 1

    Rough-In

    After pipes installed, before wall cover

  2. 2

    Final

    Fixtures connected, no leaks, venting verified

Applies to: Residential Re-Roof Permit

  1. 1

    Dry-In

    After tear-off and underlayment installation; verifies correct underlayment, ice dam membrane, and drip edge installation

  2. 2

    Final

    Verifies correct roofing material installation, penetration flashing, and roof-to-wall junctures

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Panel mounting, electrical connections, and interconnection point verified

Final inspection only: Sign Permit

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Missoula building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Missoula building permits

Get alerts for Missoula

We'll email you when Missoula's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.