Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Mineral County, Nevada.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
932 E Street, P.O. Box 2220, Hawthorne, NV 89415
Phone
(775) 316-0145
Office hours
Monday–Friday, 7:30 A.M. – 4:30 P.M.

Inspection sequence

Applies to: Building Permit (Residential & Commercial Construction, Additions, Alterations)

  1. 1

    Foundation/Footing

    Before concrete pour (implied by standard building-permit inspection sequence; the county's published materials do not itemize a full named inspection sequence)

  2. 2

    Framing / Rough Electrical, Plumbing & Mechanical

    Prior to covering framing and rough trade work

  3. 3

    Final

    All work complete per approved plans

Applies to: Solar PV Permit

  1. 1

    Framing/Structural

    Racking and roof-penetration/structural attachment inspection prior to covering, consistent with the general Building Permit inspection sequence

  2. 2

    Rough Electrical / Final

    Trade rough-in and final inspection of the completed installation

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Mineral County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Mineral County building permits

Get alerts for Unincorporated Mineral County

We'll email you when Unincorporated Mineral County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.