Alamogordo building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Alamogordo, New Mexico.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
CID Las Cruces Office: 505 S. Main St., Ste. 103, Loretto Town Center, Las Cruces, NM 88001. City of Alamogordo Planning & Zoning: 1376 E. Ninth Street, Alamogordo, NM 88310
Phone
CID Las Cruces: (575) 524-6320; City of Alamogordo Planning & Zoning: (575) 439-4220
Office hours
City of Alamogordo Planning & Zoning: Mon-Fri 8:00 AM-5:00 PM (closed for lunch 12:00-1:00 PM)

Published scheduling rules

  • Alamogordo has no city Building Inspectors — all inspection requests and permitting questions go to CID, not the City, per the Planning & Zoning Department's own FAQ page. (Residential Building Permit (New Construction))
  • For CID inspection requests, email CID.Inspection@state.nm.us or call 505-222-9813 / 877-243-0979. For general CID permit questions, email CID.PERMITHELP@rld.nm.gov. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation Inspection

    Made after excavations for footings are complete and required reinforcing steel is in place, before concrete placement

  2. 2

    Concrete Slab / Under-Floor Inspection

    Made after all in-slab or under-floor building service equipment, conduit, and piping are in place, but before concrete is placed or floor sheathing installed

  3. 3

    Frame Inspection

    Made after roof, framing, fire blocking, and bracing are in place and rough electrical, plumbing, and heating are complete and approved

  4. 4

    Weather-Resistive Barrier Inspection

    Made after installation of the weather-resistive barrier and before it is covered

  5. 5

    Final Inspection

    Made after finish grading and building completion; final electrical, plumbing, and mechanical inspections must be conducted first. CID issues the Certificate of Occupancy after approving the final inspection

Applies to: Plumbing Permit

  1. 1

    Underground / Slab Plumbing

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Change of Use / Certificate of Occupancy Permit

  1. 1

    Zoning Compliance Review

    Planning & Zoning confirms the proposed use is permitted in the applicable zoning district before issuing the compliance certificate

  2. 2

    Final Building Inspection (occupancy-classification changes only)

    If a new CID building permit was required because the occupancy classification changed, CID performs a final inspection verifying code compliance for the new occupancy before issuing the Certificate of Occupancy

Applies to: Electrical Permit

  1. 1

    Rough-In Inspection

    Wiring and conduit installed before walls closed

  2. 2

    Final Inspection

    All devices installed, panel labeled, system energized

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In Inspection

    Wiring and conduit installed before walls closed

  2. 2

    Final Inspection

    Charger installed, circuit verified, unit energized

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Rough-In Inspection (Sprinkler Piping / Alarm Wiring)

    Sprinkler piping and control wiring, or fire alarm conductors and devices, installed and inspected before walls/ceilings are closed

  2. 2

    Final Acceptance Test

    Water-flow, valve supervision, and alarm-notification functions tested and verified operational before the system is placed in service; CID final inspection required, coordinated as needed with the Alamogordo Fire Department's Fire Inspector

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Ductwork and mechanical equipment rough-in before walls closed

  2. 2

    Final

    Equipment operational, combustion air verified, venting correct

Applies to: Residential Addition / Alteration Permit

  1. 1

    Frame Inspection

    After framing, fire blocking, and bracing complete; rough electrical, plumbing, and heating approved

  2. 2

    Final Inspection

    After completion; final electrical, plumbing, and mechanical inspections conducted first

Applies to: Roofing Permit (Reroof)

  1. 1

    Decking Inspection

    Required upon removal of the existing roof, before new roofing material is applied

  2. 2

    Final Inspection

    Upon completion of the roofing project or application of the roof coating system

Applies to: Sign Permit

  1. 1

    Zoning/Code Compliance Review

    Planning & Zoning validates the proposed sign against the City's zoning ordinance sign regulations before approving the permit

  2. 2

    Electrical Final Inspection (illuminated signs only)

    If the sign includes electrical/illuminated components, CID performs a final electrical inspection of the sign circuit and connections before energizing

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Electrical Rough-In / Structural (if applicable)

    Conduit runs, mounting/racking attachment, and structural reinforcement (if required) verified before energizing

  2. 2

    Final Electrical Inspection

    All electrical connections, grounding, and interconnection point verified per the approved one-line diagram

Re-inspection fees

Electrical PermitReinspection Fee · NM RLD CID Fees page
$80
Plumbing PermitEach Re-Inspection · NM RLD CID Fees page
$80.00
Plumbing Permit2nd Re-Inspection · NM RLD CID Fees page
$120.00
Mechanical / HVAC PermitEach Re-Inspection · NM RLD CID Fees page
$80.00
Mechanical / HVAC Permit2nd Re-Inspection · NM RLD CID Fees page
$120.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Alamogordo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Alamogordo building permits

Get alerts for Alamogordo

We'll email you when Alamogordo's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.