Permit types & fees
Residential Building Permit (New Home / Cabin)
Required for new single-family home and cabin construction on property within Price City limits (as well as unincorporated Carbon County and the county's other incorporated cities/towns). Issued exclusively by Carbon County's Building & Planning Department — Price City has no independent building-permit function and instead requires proof of separate city zoning approval as a prerequisite. Reviewed under the state-mandated 2024 IBC (incl. Appendix J) and 2021 IRC (incl. Appendix Q), per Utah Code § 15A-2-103, effective 7/1/2026; plus 2024 IPC/IMC/IFGC and 2023 NEC. Carbon County's own FAQ still lists the pre-flip 2021 IBC/IPC/IMC/IFGC and 2020 NEC as of live re-check 2026-07-16 — see codesAdopted for the governing-law citations.
Reviewed 2026-07-20 · Source
Requirements
- Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect/install/enlarge/alter/repair/remove/convert/replace any electrical, gas, mechanical or plumbing system, must first apply to the Building Department and obtain the required permit (per Carbon County Building Permits page, quoting the adopted code's permit-requirement section)
- Proof of city zoning approval required for property within Price City limits, in addition to the county building permit — per both Price City's own Planning & Zoning page and Carbon County's Building Permits FAQ ('If you are building in East Carbon, Helper, Price City, Wellington, or Scofield Town, you must provide proof of city zoning approval')
- Completed and signed Building Permit Application, including contractor's name(s) and license number(s), or a signed Owner/Builder Certification Form if the owner is completing any of the work
- A complete plan set (PDF only — jpgs and other file types not accepted) including site plan, footing/foundation plan, wall framing/columns/beams, floor framing, roof framing or stamped truss sheets, electrical plan, plumbing plan, HVAC plans with heating/cooling load calculations (Manual J & D), and gas pipe sizing calculations
- Proof of fees paid for water connection (PRWID or city water authority) and sewer hook-up (PRWID, city sewer authority, or Scofield Reservoir Special Service District) or, where unserved, spring/well approval from the Utah Division of Water Rights and/or Individual Wastewater (septic) approval from the Southeast Utah Health District
- Engineered WET-stamped plans (no copies accepted) required for all structures in the Scofield area D0 seismic zone, and may be required elsewhere for unusual shapes/sizes, foundation/basement walls over 9 feet, walkout basements, basements with a garage, or non-rectangular log structures
Required documents
- RequiredBuilding Permit ApplicationCompleted and signed, including contractor name(s) and license number(s). Apply online at carbon.utah.gov or in person at the County Building & Planning Office.
- OptionalOwner/Builder Certification FormRequired if the owner is completing any of the work themselves (do-it-yourselfer), in lieu of a licensed contractor.
- RequiredSite Plan (PDF)Drawn to scale, showing lot shape/dimensions, street, front of lot, and setbacks to property lines of all existing and proposed structures, per the county's Residential Site Plan Requirements.
- RequiredFull Construction Plan Set (PDF, not less than 1/4" = 1')Footing/foundation plan; wall framing/columns/beams with sizes; floor framing/girder/joist/blocking sizes and spans; roof framing/rafter size and span or stamped truss sheet details; electrical plan; plumbing plan; HVAC plans with heat loss/gain calculations (Manual J & D); gas pipe sizing calculations.
- RequiredProof of City Zoning ApprovalRequired specifically for property within Price City limits (and East Carbon, Helper, Wellington, Scofield Town) before or alongside the county building permit application, per both Price City's and Carbon County's official guidance.
- RequiredProof of Water/Sewer Fees PaidWater connection from PRWID or city water authority; sewer hook-up from PRWID, city sewer authority, or Scofield Reservoir Special Service District; or septic approval from Southeast Utah Health District where unserved by sewer.
Fee schedule
| Fee type | Amount | Notes |
|---|
Commercial Building Permit
Required for new commercial and industrial construction on property within Price City limits. Issued exclusively by Carbon County's Building & Planning Department — Price City has no independent building-permit function and requires proof of separate city zoning approval as a prerequisite (and, if the site is in an Industrial Zone, a Conditional Use Permit that can take up to 2 months). Carbon County publishes a dedicated 'Commercial and Industrial Structures' checklist distinct from its residential New Home/Cabin packet.
Reviewed 2026-08-02 · Source
Requirements
- Approval from Price City's Zoning Administrator (or the relevant zoning authority) — proof of city zoning approval is required before/alongside the county building permit
- If the property is in an Industrial Zone: all uses require a Conditional Use Permit, and the building permit cannot be approved until that process is complete; approval may take up to 2 months
- Completed and signed Building Permit Application with contractor name(s) and Utah license number(s), applied online at carbon.utah.gov/department/building/
- Site plan drawn to scale showing lot shape/dimensions, street, front of lot, setbacks to property lines, utilities, and septic system if applicable
- 2 sets of engineered WET-stamped plans (PDF, not less than 1/4" = 1'), sealed and signed by registered Utah Architects and/or Professional Engineers trained in the specific discipline (electrical, plumbing, mechanical, or structural) being sealed
- Fire sprinkler system plans, if required
- Proof of fees paid for water connection (PRWID or city water authority) and sewer hook-up (PRWID, city sewer authority, or Scofield Reservoir Special Service District), or spring/well and septic approval where unserved
Required documents
- RequiredCommercial and Industrial Structures Building Permit Information (checklist)Official Carbon County checklist: approval from Zoning Administrator or city jurisdiction; Conditional Use Permit if in an Industrial Zone (up to 2 months); completed/signed permit application; scaled site plan; 2 sets of engineered WET-stamped plans covering footing/foundation, wall framing, floor framing, roof framing/trusses, electrical, plumbing, HVAC with heat-loss calcs, gas pipe sizing, and fire sprinkler system if required; proof of water/sewer fees paid.
- RequiredCommercial Site Plan (example/requirements)County-published example of a commercial site plan showing elevations at property corners and utility/easement locations, distinct from the residential site plan format.
- RequiredProof of City Zoning ApprovalRequired specifically for property within Price City limits before or alongside the county building permit application, per both Price City's and Carbon County's official guidance.
- OptionalConditional Use Permit (Industrial Zone only)Required for all uses in an Industrial Zone; the building permit cannot be approved until this separate process is complete. County guidance states this may take up to 2 months.
Fee schedule
| Fee type | Amount | Notes |
|---|
Commercial Tenant Improvement / Tenant Finish Permit
Required for interior tenant-improvement and tenant-finish work within existing commercial space on property within Price City limits. Carbon County does not publish a fee category or checklist distinct from new commercial construction — the same Commercial and Industrial Structures checklist and unconditional engineered-plan requirement apply, scoped to the actual work performed. Price City zoning approval is still required for the underlying property/use unless the TI is a pure interior scope not implicating zoning.
Reviewed 2026-08-02 · Source
Requirements
- Interior tenant-improvement or tenant-finish work inside existing commercial space within Price City limits
- Completed and signed Building Permit Application with contractor name(s) and license number(s)
- Engineered WET-stamped plans for any structural, electrical, plumbing, or mechanical work involved in the tenant finish, sealed by a Utah-registered Architect or Professional Engineer in the relevant discipline
- Fire sprinkler system plans, if the tenant improvement affects or requires fire suppression coverage
Required documents
- RequiredCommercial and Industrial Structures Building Permit Information (checklist)Same official county checklist used for new commercial construction — Carbon County does not publish a distinct, scaled-down tenant-improvement checklist. Applicants should submit only the items relevant to their actual scope (e.g., floor plan and MEP plans for an interior TI rather than a full site/foundation plan).
- OptionalProof of City Zoning ApprovalRequired if the tenant improvement changes the use/occupancy of the space in a way that implicates Price City zoning; confirm with Price City's Planning & Zoning office whether a pure interior TI still requires sign-off. Price City's own Land Use Development and Management Code (priceutah.gov/uploads/1/1/9/7/119716550/land_use_management_code.pdf), Chapter 16 § 16.2(1)-(2), states 'No building or structure shall be constructed, reconstructed, altered, or moved and no land shall be used except after the issuance of a Building, Use, and Occupancy Permit' and that such permits 'shall not be granted for the construction or alteration of any building or structure... if such structure, construction, alteration, moving, use, or occupancy would be in violation of any of the provisions of this Code' — 'altered' is listed as an independent permit-triggering event, not conditioned on a change of use/occupancy, which textually supports that even a pure-interior TI (an 'alteration') falls within Price City's zoning-permit trigger. However, this is Price City's own general zoning-code definition of a city-issued 'Building, Use, and Occupancy Permit' — a process Price City does NOT actually operate as a distinct standalone application (Price's official Planning & Zoning page and Carbon County's own guidance describe only a single 'proof of city zoning approval' sign-off step feeding into the COUNTY's building permit, not a separate Price-issued permit; see the other Price permit entries). No provision specifically carves out minor/cosmetic interior work from this trigger, and no published source confirms whether in practice Price's Zoning Administrator requires a fresh sign-off for every TI regardless of scope. That question remains unresolved as to real-world practice; a direct call to Price City's Planning & Zoning office (Nick Tatton, 435-636-3184) is the only way to confirm.
Fee schedule
| Fee type | Amount | Notes |
|---|
Solar PV Permit
Required for residential rooftop or ground-mounted solar photovoltaic (PV) system installations on property within Price City limits. Issued exclusively by Carbon County's Building & Planning Department — Price City has no independent building-permit function. Carbon County publishes a dedicated 'PV System Building Permit' packet with its own Residential PV System Checklist, distinct from the county's general New Home/Cabin Checklist, confirming solar is treated as its own permit category rather than folded into the general building permit with no distinct process.
Reviewed 2026-07-20 · Source
Requirements
- Completed and signed Building Permit Application, including contractor's name and license number, applied for online at carboncounty.cityinspect.com/login
- A signed and notarized Owner/Builder Certification Form, if the owner is completing any of the work
- All 8 items on Carbon County's Residential PV System Checklist — the county states 'NO APPLICATIONS WILL BE ACCEPTED WITHOUT ALL OF THE ITEMS THAT ARE LISTED'
- Proof of city zoning approval for property within Price City limits, per Carbon County's Building Permits FAQ (same city-zoning-approval step required for all building permits, including solar)
Required documents
- RequiredSite PlanDetailed site plan showing the location of the home, electrical meter panel, any back-fed sub-panelboards, and all PV system components on the property.
- RequiredMounting System DetailsModule mounting system and weight of all roof components; support manufacturer specs must specify required support spacing based on local wind and snow loads. Note whether roof rafters are engineered trusses (or type/size if not), and the roof covering type and number of layers.
- RequiredOne-Line Electrical DiagramMust show PV system type (single inverter, micro-inverter, or AC module system), exact module count/layout and series/parallel wiring, all wire types and sizes, conduit types and sizes, grounding wiring and connections, locations of all circuits and components, and ratings of all fuses/breakers.
- RequiredBack-Fed Panel DocumentationNote which home electrical panel the PV system will back-feed, its location and rating, plus photos of the service panel (including its interior label) and photos of labels on any sub-panel that will be back-fed.
- RequiredModule Spec SheetsPV module (solar panel) spec sheets showing STC rated watts (Pmp), Vmp, Imp, Voc, and Isc. Modules must be UL 1703 listed.
- RequiredInverter Spec SheetsInverter manufacturer spec sheets showing rated watts/volts and max AC output amps/voltage. Utility-tied inverters must be listed 'utility interactive' meeting UL 1741, with ground fault protection.
- OptionalTotal Array Power CalculationTotal watts, amps, volts, Voc (at coldest possible outside temperature per NEC 690.7), and short-circuit current the array can produce. Not required for micro-inverter systems.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New Construction / Solar Deposit | $250.00 non-refundable deposit | Carbon County Building Permits page: 'New Construction and Solar building permit applications require a non-refundable $250.00 deposit,' effective January 1, 2025, applied as a credit toward the final permit fee. Show full citationHideCarbon County Building Permits page: 'New Construction and Solar building permit applications require a non-refundable $250.00 deposit,' effective January 1, 2025, applied as a credit toward the final permit fee. Carbon County's official website publishes no further dollar-amount valuation-based fee table for solar permits (the same gap documented on this jurisdiction's residential-building-permit entry; see feesNote) — contact the Building Department directly for a full fee quote. |
Sign Permit
Required for erecting, reconstructing, or remodeling most signs in Price City, per Chapter 4 (Sign Regulations / Sign Code) of the Price City Land Use Development and Management Code, § 4.9 (Sign Permit and Permit Fee Required). Applications go to the Zoning Administrator, who must issue the permit within 60 days of receipt if the proposed sign complies with the code. PermitBase could not locate the specific dollar fee amount in any Price City fee schedule published online — the code states only that the fee is 'established by resolution of the City Council' and identified in 'the approved fee schedule of Price City'; Price's own online Planning and Zoning Permit Fee Schedule (effective 1-1-2026) covers subdivision, rezoning, and conditional-use fees but does not list a sign line item, and no separate building-permit fee schedule with a sign line item was found on either priceutah.gov or Carbon County's building-permit pages (Price contracts building inspection to Carbon County).
Reviewed 2026-07-20 · Source
Requirements
- All signs must comply with current International Electric Code and International Building Code standards as adopted by Price City, plus city ordinances and Utah law (§ 4.5.2)
- Signs requiring inspection of electrical connections or structural attachments must be installed under inspection of the Price City Building Inspector (§ 4.5.4)
- No permit required for sign maintenance or a change of copy alone (§ 4.5.1)
- Anyone erecting, altering, relocating, constructing, or maintaining signs near/upon public right-of-way must hold a valid Utah contractor license and valid business license, and carry liability insurance of at least $3,000,000 (§ 4.5.8)
- Sign type, dimensions, number, and location are regulated by one of three sign overlay districts — S-1 (Residential), S-2 (Downtown/Shopping Centers), S-3 (Arterial/State Highways) — per §§ 4.11–4.13
Required documents
- RequiredSign Permit ApplicationSubmitted to the Price City Zoning Administrator per § 4.9. The Zoning Administrator must issue the permit within 60 days of receipt if the sign complies with the code.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sign Permit Fee | Established by resolution of the Price City Council — specific dollar amount not found in any Price City or Carbon County fee schedule published online as of this check | Price City Land Use Development and Management Code (2026 edition) § 4.9: 'Application for a sign permit shall be made to the Zoning Administrator and shall be accompanied by a fee identified in the… Show full citationHidePrice City Land Use Development and Management Code (2026 edition) § 4.9: 'Application for a sign permit shall be made to the Zoning Administrator and shall be accompanied by a fee identified in the approved fee schedule of Price City to defray the expenses to Price City incurred in the administration of this chapter. Such fee shall be established by resolution of the City Council.' The city's online 'Planning and Zoning Permit Fee Schedule' (effective 1-1-2026) lists subdivision, rezoning, conditional-use, and similar planning fees but no sign line item. The fee-setting chapter that the Land Use code's 'approved fee schedule of Price City' language points to is Price City Municipal Code Title 3 Revenue and Finance, Chapter 3.24 'Administrative Service And Operational Fees' (codelibrary.amlegal.com/codes/priceut/latest/price_ut/0-0-0-1089), which is where the current sign permit dollar figure sits. Chapter 3.24's rates were adopted by 'RESOLUTION 2014-11. Setting forth the rates and charges for administrative service and operational fees to the general public,' approved at the City Council's 4/9/2014 meeting per the Council minutes on priceutah.gov; the resolution's fee-table exhibit itself is not published online. Open the amlegal chapter link in an ordinary web browser — the chapter text does not render in simpler tools. Neither Price City's FY2027 Approved Budget (priceutah.gov/uploads/1/1/9/7/119716550/2027_fiscal_year_approved_budget.pdf), which reports only an aggregate 'LICENSES & PERMITS' revenue-category total ($92,350/$90,000) with no itemized fee schedule, nor the City's 2026 Business License Application, which lists no dollar amounts beyond a reference to 'applicable licensing fees', states the sign permit fee. For the current figure, read Chapter 3.24 in a web browser or contact Price City — the City Recorder's office can provide the Chapter 3.24 fee table. |
| Re-inspection Fee | Amount not published; charged per notice-of-violation re-inspection | Price City Land Use Development and Management Code § 4.10: a re-inspection fee is charged to defray re-inspection costs after a notice of violation, 'for each inspection required until compliance... Show full citationHidePrice City Land Use Development and Management Code § 4.10: a re-inspection fee is charged to defray re-inspection costs after a notice of violation, 'for each inspection required until compliance... has occurred.' Amount 'established by resolution of the City Council' — not found in a published fee schedule. |
Conditional Use Permit — Business Occupancy
VerifiedUnlike the Carbon County-administered building permit process (which folds a 'change of occupancy' into its generic building-permit definition with no separate fee), Price City's own Planning and Zoning Permit Fee Schedule publishes a genuinely distinct, separately-priced permit category specifically for occupying an existing building with a business use: the 'Conditional Use Permit — Business Occupancy' track, priced separately from the City's 'Conditional Use Permit — Development' track used for new construction/site development. This is the real change-of-use mechanism in Price: when a business (a new tenant, or an existing tenant changing its use) occupies a building, Price City Community Development Services reviews and prices that occupancy separately from any building-permit work, and ties it into the City's Business License process.
Verified 2026-07-20 · Source
Requirements
- A business occupying an existing building within Price City limits, where the proposed use requires a Conditional Use Permit under the zoning ordinance -- reviewed by Community Development Services (Room 201, 435-636-3184)
- Completion of the Price City Business License application process (185 E. Main, Room 202) alongside or before the Conditional Use Permit, since the Business License guide states a business will be 'notified by Community Development Services' if a conditional use permit is required
- Passed building and/or fire inspection where required -- the Business License guide states 'all commercial businesses require an inspection'
- If the business is relocating from one Price City location to another, the same Business Occupancy review applies again: 'This may require a new building and/or fire inspection. A new Conditional Use Permit may also be required.'
Required documents
- RequiredConditional Use Permit Application — Business Occupancy trackReviewed through Price City's two-stage Concept Approval, then Preliminary and Final Approval process, per the City's Planning and Zoning Permit Fee Schedule (effective 1-1-2026). Contact Community Development Services, Room 201, (435) 636-3184.
- RequiredPrice City Business License ApplicationFiled at 185 E. Main, City Recorder Office, Room 202; requires prior Utah State business-name registration and, for certain business types, Southeastern Utah District Health Department sign-off before submission.
- OptionalZoning Verification Letter (optional but commonly used)A research letter from Price City confirming a parcel's zoning, legal-lot-of-record status, flood zone, or similar -- useful ahead of a business-occupancy application to confirm the proposed use is allowed in that zone. Normal processing is 1 week; expedited processing (2 business days or less) is available for an additional fee.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Conditional Use Permit — Business Occupancy, Concept Approval | 75.00 dollars | Price City Planning and Zoning Permit Fee Schedule, as adopted, effective 1-1-2026 (priceutah.gov/uploads/1/1/9/7/119716550/2026_planning_and_zoning_permit_fee_schedule.pdf): 'Conditional Use Permit… Show full citationHidePrice City Planning and Zoning Permit Fee Schedule, as adopted, effective 1-1-2026 (priceutah.gov/uploads/1/1/9/7/119716550/2026_planning_and_zoning_permit_fee_schedule.pdf): 'Conditional Use Permit ($150 total fee through final) -- Business Occupancy... A. Concept Approval $75.00.' The PDF's columns misalign when copy-pasted, so read the figures from the page as published. |
| Conditional Use Permit — Business Occupancy, Preliminary and Final Approval | 75.00 dollars | Same source, table row 'B. Preliminary and Final Approval $75.00' -- combined with the Concept Approval fee, this totals 150.00 dollars through final approval, exactly as labeled in the fee… Show full citationHideSame source, table row 'B. Preliminary and Final Approval $75.00' -- combined with the Concept Approval fee, this totals 150.00 dollars through final approval, exactly as labeled in the fee schedule's own '$150 total fee through final' heading for the Business Occupancy track. This is a materially different (lower) fee than the City's separate 'Conditional Use Permit -- Development' track, which totals 250.00 dollars through final ($100 Concept + $150 Preliminary/Final). |
| Zoning Verification Letter | 100.00 dollars normal processing (1 week); 200.00 dollars total for expedited processing (2 business days or less) | Same fee schedule: 'Zoning Verification*... Normal Processing -- 1 week $100.00' and 'Expedited: within 2 business days or less... $100.00 additional fee + fee above = $200.00.' |
| Commercial Business License Fee (annual, separate from the CUP) | 100.00 dollars per calendar year | Price City Business License Information guide (priceutah.gov/uploads/1/1/9/7/119716550/-_business_license_info_-_how_to_guide_-.pdf): 'The business license fee for a commercial location is $100.00… Show full citationHidePrice City Business License Information guide (priceutah.gov/uploads/1/1/9/7/119716550/-_business_license_info_-_how_to_guide_-.pdf): 'The business license fee for a commercial location is $100.00 per calendar year and the Conditional Use Permit fee is $100.00 (varies).' Note this guide's own CUP figure (100.00 dollars, described as approximate/'varies') is superseded here by the more precise, currently-effective Planning and Zoning Permit Fee Schedule figure of 150.00 dollars total for the Business Occupancy CUP track. |
EV Charger / EVSE Permit
EV charger installation for property within Price City limits falls under Carbon County's standard building permit process — the Carbon County Building & Planning Department issues all building permits for Price City, which has no independent building-permit function of its own. Carbon County's Building Permits page (carbon.utah.gov/service/building-permits/) lists 'Altering electrical, gas, or plumbing systems' among the reasons a permit is required, with no EV-charger or electric-vehicle mention anywhere on the county site. No dollar-amount valuation-based fee table could be located on Carbon County's website for building permits generally, let alone for electrical work specifically — the same fee-table gap that affects Price's other county-administered permit types. No fee is listed here and confidence is partial rather than borrowing a figure from a different jurisdiction.
Reviewed 2026-07-20 · Source
Requirements
- Any owner or owner's authorized agent who intends to erect/install/enlarge/alter/repair/remove/convert/replace an electrical system (including EV charger/EVSE circuits) must first apply to Carbon County's Building Department and obtain the required permit
- Proof of city zoning approval required for property within Price City limits, in addition to the county building/electrical permit — per both Price City's own Planning & Zoning page and Carbon County's Building Permits FAQ
- New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g))
Required documents
- RequiredBuilding Permit ApplicationCompleted and signed; apply online at carbon.utah.gov or in person at the County Building & Planning Office (751 E 100 N, Suite 2600, Price, UT 84501).
- RequiredProof of City Zoning ApprovalRequired specifically for property within Price City limits before or alongside the county building/electrical permit application.
Fee schedule
| Fee type | Amount | Notes |
|---|
Fire Sprinkler System Permit / Plan Review
Fire sprinkler system installation within Price City limits runs on two separate, non-substituting tracks depending on the building. For ordinary private commercial and industrial buildings, sprinkler plans are reviewed and inspected as part of Carbon County's standard commercial building-permit process — its Commercial and Industrial Structures checklist requires 'Fire sprinkler system plans, if required,' and the commercial building permit here already lists a distinct 'Fire Sprinkler' inspection — with no separate county or city fee published for that item. Separately, any building falling under the State Fire Prevention Board's jurisdiction per Utah Admin. Code R710-4 — publicly owned buildings including all public and private schools, colleges and universities; institutional occupancies such as hospitals, assisted living facilities and day care centers; and any place of assemblage where 50 or more persons may gather — requires a separate, mandatory Automatic Fire Sprinkler Plan Submittal filed directly with the Utah State Fire Marshal's Office in Sandy, UT, with its own published fee, in addition to and not instead of the local building permit. For other private buildings, Price City's own full-service Fire Department (87 North 200 East, 435-636-3187) is the Local Fire Authority under Utah Admin. Code R710-9 §8, with the State Fire Marshal stepping in only if the local authority does not complete the review; Price City's Fire Department publishes no distinct fire-sprinkler fee schedule.
Reviewed 2026-07-22 · Source
Requirements
- Fire sprinkler system plans submitted as part of Carbon County's Commercial and Industrial Structures checklist for any Price City commercial/industrial building requiring sprinklers, reviewed and inspected within the standard county building-permit process (no distinct county fee published)
- For buildings under State Fire Prevention Board jurisdiction (Utah Admin. Code R710-4: publicly owned buildings, public/private schools/colleges/universities, institutional occupancies, and assembly occupancies of 50+ persons): a separate Automatic Fire Sprinkler Plan Submittal filed directly with the Utah State Fire Marshal's Office, in addition to the local building permit
- A completed Water Supply Analysis (static pressure, residual pressure, flow in gpm, source of information) per Utah Admin. Code R710-4-5, required before a State Fire Marshal submittal can even begin review
- Engineered hydraulic calculations, sprinkler drawings (number of sheets, dated), material submittals, and — where applicable — seismic calculations
- For property within Price City limits generally: proof of city zoning approval, per the same city/county split documented on this jurisdiction's other Carbon-County-administered permit types
Required documents
- RequiredAutomatic Fire Sprinkler Plan Submittal Form (Utah State Fire Marshal's Office)Official statewide form (firemarshal.utah.gov); fee is calculated directly on the form at $0.022 per square foot of the scope-of-work area, $75.00 minimum. Submitted directly to the SFM's Office (410 West 9800 South, 3rd Floor, Sandy, UT 84070; planreviews@utah.gov; 801-256-2390) for buildings under State Fire Prevention Board jurisdiction (R710-4) — not to Price City or Carbon County.
- RequiredCommercial and Industrial Structures Building Permit Information (checklist)The official Carbon County commercial submittal checklist. It requires fire sprinkler system plans as part of the standard commercial submittal for buildings not under State Fire Prevention Board jurisdiction.
- OptionalWater Supply AnalysisStatic pressure, residual pressure, and flow (gpm) data, sourced from contract specifications, a water supply analysis, the water purveyor, or a flow test — required per R710-4-5 before a State Fire Marshal plan review can originate.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Utah State Fire Marshal — Automatic Fire Sprinkler Plan Review | $0.022 per square foot of the scope-of-work area; $75.00 minimum fee | From the Utah State Fire Marshal's Office's official Automatic Fire Sprinkler Plan Submittal Form (firemarshal.utah.gov/wp-content/uploads/Automatic-Fire-Sprinkler-Plan-Submittal-Form-2022-R.pdf):… Show full citationHideFrom the Utah State Fire Marshal's Office's official Automatic Fire Sprinkler Plan Submittal Form (firemarshal.utah.gov/wp-content/uploads/Automatic-Fire-Sprinkler-Plan-Submittal-Form-2022-R.pdf): 'SQUARE FEET x.022$ = $... Note: Minimum fee is $75.' Fees must be paid before the plan review will be released. This fee governs buildings under the State Fire Prevention Board's jurisdiction per Utah Admin. Code R710-4 (publicly owned buildings, schools/colleges/universities, institutional occupancies, and assembly occupancies of 50+ persons). The Utah Office of Administrative Rules bulletin (rules.utah.gov/publicat/bulletin/2016/20160701/40485.htm) quotes R710-4 as applying to 'any publicly owned building, including all public and private schools, colleges, and university buildings, and in any building or structure used or intended for use, as an asylum, hospital, mental hospital, sanitarium, home for the aged, assisted living facility, children's home or day care center, or any similar institutional type occupancy of any capacity; and in any place of assemblage where fifty (50) or more persons may gather.' |
| Carbon County / Price City local fire-sprinkler fee (ordinary private commercial buildings) | No separate dollar amount is published — folded into the general Carbon County commercial building permit fee, which itself has no published valuation table; ask the County for a project-specific quote | Carbon County's Commercial and Industrial Structures checklist lists fire sprinkler system plans as a submittal requirement and a 'Fire Sprinkler' inspection as part of the standard commercial… Show full citationHideCarbon County's Commercial and Industrial Structures checklist lists fire sprinkler system plans as a submittal requirement and a 'Fire Sprinkler' inspection as part of the standard commercial building-permit sequence, but carbon.utah.gov publishes no separate fee line item for it — the same pages that carry no fee table for the commercial-building-permit entry carry none here. Price City's own Fire Department likewise publishes no fee schedule for fire-sprinkler plan review on its official webpage (priceutah.gov/fire-department.html). See this jurisdiction's residential-building-permit local amendments for the full detail; this is the same county-wide fee-table gap affecting the local (non-SFM) portion of every Carbon-County-administered permit type. |
Fire Alarm System Permit / Plan Review
Fire alarm installation inside Price City limits splits across two tracks. For an ordinary private building, alarm wiring is folded into the general Carbon County building/electrical permit under its 'Altering electrical, gas, or plumbing systems' trigger — Carbon County's Commercial and Industrial Structures checklist does not list 'fire alarm' separately (it calls for a general electrical plan and, separately, fire sprinkler plans), and no distinct city or county fire-alarm fee is published. Separately, any building under the State Fire Prevention Board's jurisdiction per Utah Admin. Code R710-4 — publicly owned buildings (including all public and private schools, colleges and universities), institutional occupancies (hospitals, assisted living facilities, day care centers and similar), and any place of assemblage where 50 or more persons may gather — requires a Fire Alarm Plan Review Submittal filed directly with the Utah State Fire Marshal's Office in Sandy, UT, carrying its own published fee, in addition to the local building permit. Price City's own full-service Fire Department (87 North 200 East, 435-636-3187) is the Local Fire Authority for other buildings under Utah Admin. Code R710-9 §8, but publishes no fire-alarm fee schedule — call them for a figure before bidding.
Reviewed 2026-07-22 · Source
Requirements
- Any owner or authorized agent installing/altering a fire alarm system must first obtain a Carbon County building/electrical permit for the underlying electrical work — no distinct 'fire alarm permit' category or fee is published by Carbon County or Price City
- For buildings under State Fire Prevention Board jurisdiction (Utah Admin. Code R710-4: publicly owned buildings, public/private schools/colleges/universities, institutional occupancies, and assembly occupancies of 50+ persons): a separate Fire Alarm Plan Review Submittal filed directly with the Utah State Fire Marshal's Office, in addition to the local building/electrical permit
- A floor plan indicating room size/use, occupancy type, project code analysis, locations of alarm-initiating and notification appliances, alarm control/trouble signaling equipment, annunciation, power connection, battery calculations, conductor type/sizes, voltage drop calculations, manufacturer cut sheets, ceiling height/construction details, and the interface of fire safety control functions — all required items on the State Fire Marshal's submittal form
- For property within Price City limits generally: proof of city zoning approval, per the same city/county split documented on this jurisdiction's other Carbon-County-administered permit types
Required documents
- RequiredFire Alarm Plan Review Submittal Form (Utah State Fire Marshal's Office)Official statewide form (firemarshal.utah.gov); fee is calculated directly on the form at $0.022 per square foot of the scope-of-work area, $75.00 minimum. Submitted directly to the SFM's Office (410 West 9800 South, 3rd Floor, Sandy, UT 84070; planreviews@utah.gov; 801-256-2390) for buildings under State Fire Prevention Board jurisdiction (R710-4) — not to Price City or Carbon County. Requires a floor plan, occupancy type, code analysis, alarm-device locations, control/annunciation equipment, power connection, battery calculations, conductor sizing, voltage-drop calculations, and manufacturer cut sheets.
- RequiredBuilding Permit Application (Carbon County)Same general building/electrical permit application used for other electrical work within Price City limits — Carbon County's checklist has no fire-alarm-specific line item.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Utah State Fire Marshal — Fire Alarm Plan Review | $0.022 per square foot of the scope-of-work area; $75.00 minimum fee | From the Utah State Fire Marshal's Office's official Fire Alarm Submittal Form (firemarshal.utah.gov/wp-content/uploads/Fire-Alarm-Submittal-Form-2023D-R.pdf): 'SQUARE FT x.022$ = $... Show full citationHideFrom the Utah State Fire Marshal's Office's official Fire Alarm Submittal Form (firemarshal.utah.gov/wp-content/uploads/Fire-Alarm-Submittal-Form-2023D-R.pdf): 'SQUARE FT x.022$ = $... Note: Minimum fee is $75.' Fees must be paid before the plan review will be released. This fee governs buildings under the State Fire Prevention Board's jurisdiction per Utah Admin. Code R710-4 (publicly owned buildings, schools/colleges/universities, institutional occupancies, and assembly occupancies of 50+ persons), scope per the Utah Office of Administrative Rules bulletin (rules.utah.gov/publicat/bulletin/2016/20160701/40485.htm). |
| Carbon County / Price City local fire-alarm fee (ordinary private buildings) | No separate dollar amount is published — fire alarm wiring is folded into the general Carbon County building/electrical permit, which itself has no published valuation table; ask the County for a project-specific quote | Carbon County's Commercial and Industrial Structures checklist and Building Permits page contain no fire-alarm-specific line item or fee; Show full citationHideCarbon County's Commercial and Industrial Structures checklist and Building Permits page contain no fire-alarm-specific line item or fee; fire alarm circuits fall under the same 'Altering electrical, gas, or plumbing systems' general permit trigger that covers EV charger installations. Price City's own Fire Department publishes no fee schedule for fire-alarm plan review on its webpage (priceutah.gov/fire-department.html), and no figure appears via the city's Business License page or Ordinance 281. The same county-wide fee-table gap affects the local, non-State-Fire-Marshal portion of every Carbon County-administered permit type here — see the residential building permit localAmendments for details. |
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-08.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Price building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.