Single-Family New Construction in Sandy, Utah
Required for new single-family residential construction in Sandy. Permit fees are based on total project valuation and include plan review at 65% of the permit fee. The state adds a 1% surcharge on all building fees.
Verified 2026-06-29 · Source
When you need this permit
- New single-family dwelling construction on a permitted lot
- Complete architectural and structural drawings
- Site plan showing setbacks, lot coverage, and drainage
- Energy code compliance documentation (REScheck or equivalent)
- Soils report if lot has special conditions
Required documents
- Req
Building Permit Application
Submit via Sandy City online permit portal or in person at 10000 Centennial Parkway
- Req
Construction Plans
Complete drawings to scale — site plan, floor plans, elevations, sections, and structural details
- Req
Energy Code Compliance Documentation
REScheck or equivalent documentation demonstrating compliance with adopted IECC
- Opt
Structural Calculations
Sealed by a licensed Utah PE for projects requiring engineered design
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New Single-Family Build — total valuation < $100,000 | $2,967 | Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Single Family New Build |
| New Single-Family Build — total valuation $100,000–$500,000 | $4,866 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| New Single-Family Build — total valuation $500,000–$1,000,000 | $6,837 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| New Single-Family Build — total valuation $1,000,000–$2,500,000 | $8,569 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| New Single-Family Build — total valuation $2,500,000–$5,000,000 | $10,185 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| New Single-Family Build — total valuation > $5,000,000 | $12,572 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Plan Review Fee | 65% of the building permit fee | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| State Building Fee Surcharge | 1% of total permit fee | Sandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge |
| Re-Inspection Fee | $70 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| After-Hours Inspection (after 5 p.m. or holidays/weekends) | $35/hour, minimum $70 (2-hour minimum) | Sandy City 2026 Consolidated Fee Schedule |
Review timeline
~10–30 business days
Typical estimate — confirm current times with the Sandy building department
Inspection process
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Underground Plumbing
Before backfill — all underground pipes and connections
- 3
Framing
After framing, sheathing, and rough-in mechanical/electrical/plumbing — before insulation or wall cover
- 4
Insulation
Before drywall — verify insulation meets IECC requirements
- 5
Drywall / Sheathing
Before taping or finishing — nail pattern and fire-blocking verification
- 6
Final
All work complete; Certificate of Occupancy issued upon passing final inspection
Tips
- Permit fees are based on total project valuation — have a contractor cost estimate ready at application time.
- Plan review adds 65% to the permit fee; budget both together.
- Sandy uses a state-mandated 1% surcharge on all building fees.
- Work done without a permit carries an investigation fee equal to the full permit fee.
Frequently asked questions
- How long does plan review take for a new home?
- Sandy does not publish a specific first-review timeline. A typical new single-family build may take 2–6 weeks for plan review; contact the Building Division at (801) 568-7100 for current turnaround estimates.
- Is the plan review fee separate from the building permit fee?
- Yes. Sandy charges a plan review fee equal to 65% of the building permit fee, in addition to the permit fee itself. Both are due at permit issuance.
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
- Sandy City Building & Safety Division — official building department
- Sandy City 2026 Consolidated Fee Schedule (PDF)
- Sandy City Building Permits
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sandy
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.