Reroof in Sandy, Utah

Required for reroofing an existing residential structure. Flat fee for residential reroof.

Verified 2026-06-29 · Source

When you need this permit

  • Full or partial replacement of roof covering on any structure
  • Roofing material specifications

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Reroof (flat fee)Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Reroof
$115
Plan Review FeeSandy City 2026 Consolidated Fee Schedule, § 3122
65% of the building permit fee
State Building Fee SurchargeSandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge
1% of total permit fee
Re-Inspection FeeSandy City 2026 Consolidated Fee Schedule, § 3122
$70

Review timeline

Plan reviewTypical estimate — confirm current times with the Sandy building department
~1–5 business days

How long did your Reroof permit actually take in Sandy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Roofing Final

    Verify shingle installation, flashing, and ventilation

See the full Sandy inspection guide — scheduling & re-inspection fees →

Tips

  • Roofing contractors typically pull the permit on the homeowner's behalf — verify before signing a contract.
  • A second layer of shingles over existing shingles may have limitations under the adopted IRC — ask your contractor.

Frequently asked questions

Yes. Sandy requires a building permit for reroofing projects. The residential reroof permit is a flat $115.

In Sandy, the published Residential Reroof (flat fee) is: $115. Additional published fees: Plan Review Fee — 65% of the building permit fee; State Building Fee Surcharge — 1% of total permit fee; Re-Inspection Fee — $70. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a reroof permit in Sandy typically runs 1–5 business days. This is an estimate, not a published figure — confirm current review times with Sandy City Building & Safety Division at (801) 568-7100.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

Sandy requires 1 inspection(s) for a reroof permit, in order: Roofing Final. Schedule each through Sandy City Building & Safety Division ((801) 568-7100).

Apply through Sandy City Building & Safety Division at 10000 Centennial Parkway, Sandy, UT 84070. Phone: (801) 568-7100. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://sandy.utah.gov/229/Building.

Sandy, Utah has adopted: 2024 International Building Code (IBC) — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(a)); 2021 International Residential Code (IRC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b)); 2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(d)); 2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(e)); 2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(f)); 2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g)); 2024 International Energy Conservation Code (IECC) — currently in effect as of July 1, 2026, superseding the 2021 IECC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(h)); 2024 International Existing Building Code (IEBC) — currently in effect as of July 1, 2026, superseding the 2021 IEBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(i)); Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — currently in effect as of July 1, 2026, superseding the 2021 ISPSC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(n)); NOTE (updated 2026-07-16): the July 1, 2026 transition forecast in the prior version of this entry has now occurred — confirmed live against Utah Code § 15A-2-103, current version (effective 7/1/2026, superseded 1/1/2027), read at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html. This file cites no Sandy-specific code-adoption webpage; all codesAdopted entries above are sourced directly from the statute.. Local amendments apply — see the Sandy overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.