Sandy building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Sandy, Utah.

Verified 2026-06-29 · Source

How to schedule

Inspections are requested through the building department below.

Address
10000 Centennial Parkway, Sandy, UT 84070
Phone
(801) 568-7100
Email
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Inspection sequence

Applies to: Single-Family New Construction

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Underground Plumbing

    Before backfill — all underground pipes and connections

  3. 3

    Framing

    After framing, sheathing, and rough-in mechanical/electrical/plumbing — before insulation or wall cover

  4. 4

    Insulation

    Before drywall — verify insulation meets IECC requirements

  5. 5

    Drywall / Sheathing

    Before taping or finishing — nail pattern and fire-blocking verification

  6. 6

    Final

    All work complete; Certificate of Occupancy issued upon passing final inspection

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts per adopted IBC

  2. 2

    Underground / Rough-In (Plumbing, Electrical, Mechanical)

    Before backfill and before closing walls or ceilings — all underground and rough-in utilities

  3. 3

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  4. 4

    Fire Sprinkler / Fire Alarm

    Separate inspection by the Sandy Fire Department where fire suppression or alarm systems are required

  5. 5

    Final

    All work complete; Certificate of Occupancy issued upon passing final inspection

Applies to: In-Ground Swimming Pool

  1. 1

    Pre-Gunite / Shell

    Verify rebar, bonding wire, and rough plumbing before concrete shell is applied

  2. 2

    Electrical / Bonding

    Verify pool bonding grid, GFCI protection, and underwater lighting

  3. 3

    Barrier / Fence

    Pool barrier compliant with ISPSC before pool can be filled

  4. 4

    Final

    All systems operational, barrier in place, deck and coping complete

Applies to: Residential Addition

  1. 1

    Foundation / Footing

    Before concrete pour if addition requires new foundation work

  2. 2

    Framing

    After framing and rough-in MEP work — before insulation or wall cover

  3. 3

    Insulation

    Verify insulation meets adopted IECC requirements before drywall

  4. 4

    Final

    All work complete; addition approved for occupancy

Applies to: Basement Finish

  1. 1

    Rough-In (Framing, MEP)

    After framing and rough-in electrical, plumbing, and HVAC — before insulation or drywall

  2. 2

    Insulation

    Verify insulation meets adopted IECC requirements before drywall

  3. 3

    Final

    All work complete; space approved for occupancy

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Rough-In (MEP)

    After framing and rough-in mechanical, electrical, and plumbing work — before insulation or wall cover

  2. 2

    Fire Sprinkler / Fire Alarm (if applicable)

    Separate inspection by the Sandy Fire Department where the scope modifies existing fire suppression or alarm systems

  3. 3

    Final

    All work complete; space approved for occupancy under the tenant's use classification

Applies to: Business License Update — Change of Use / Change of Location

  1. 1

    Building & Safety Final Inspection

    Scheduled with Building & Safety (801-568-7251) after the update application is filed; a positive final inspection or recommendation is required before an updated license issues

  2. 2

    Fire Department Final Inspection

    Scheduled with the Sandy Fire Department (801-568-2938) after the update application is filed; a positive final inspection or recommendation is required before an updated license issues

Applies to: Deck / Patio Cover

  1. 1

    Footing

    Before concrete pour — verify footing depth and size

  2. 2

    Framing / Final

    Decking, framing, ledger attachment, guard/railing height and spacing

Applies to: Residential Remodel

  1. 1

    Framing / Rough-In

    After framing, blocking, and rough-in MEP — before insulation or wall cover

  2. 2

    Final

    All work complete and ready for occupancy

Applies to: Residential Solar / PV System

  1. 1

    Rough Electrical

    Wiring, conduit, and connections before closing walls or covering junction boxes

  2. 2

    Final / Interconnection

    System fully installed, labeled, and ready for utility interconnection approval

Re-inspection fees

Single-Family New ConstructionRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Residential AdditionRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Residential RemodelRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Basement FinishRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Deck / Patio CoverRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Residential Solar / PV SystemRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
HVAC / AC / Furnace ReplacementRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Water Heater ReplacementRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
ReroofRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
In-Ground Swimming PoolRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Commercial Building PermitRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70
Commercial Tenant Improvement / Tenant Finish PermitRe-Inspection Fee · Sandy City 2026 Consolidated Fee Schedule, § 3122
$70

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Sandy building permits

Get alerts for Sandy

We'll email you when Sandy's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.