Residential Solar / PV System in Sandy, Utah
Required for rooftop and ground-mount residential solar photovoltaic systems. Two fee tiers based on system size: under 10,000 kW and 10,000 kW or larger (or energy storage systems). Fees are based on total project valuation.
Verified 2026-06-29 · Source
When you need this permit
- Rooftop or ground-mount PV system installation
- Equipment specifications and installation drawings
- Structural letter or engineering for roof-mounted systems on older homes
- Electrical single-line diagram
- Utility interconnection application (Rocky Mountain Power)
Required documents
- Req
Building Permit Application
Submit via Sandy City online permit portal or in person at 10000 Centennial Parkway
- Req
Electrical Single-Line Diagram
Showing PV array, inverter, disconnect, and utility interconnection
- Req
PV System Layout Plan
Roof plan with module locations, dimensions, and attachment details
- Opt
Structural / Load Calculations
Manufacturer specs and, if required, a structural engineer letter confirming roof capacity
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Solar < 10,000 kW — total valuation < $50,000 | $372 | Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Solar <10,000 kW |
| Solar < 10,000 kW — total valuation $50,000–$100,000 | $589 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar < 10,000 kW — total valuation $100,000–$250,000 | $1,239 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar < 10,000 kW — total valuation $250,000–$500,000 | $1,517 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar < 10,000 kW — total valuation $500,000–$1,000,000 | $2,156 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar < 10,000 kW — total valuation $1,000,000–$2,500,000 | $2,722 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar < 10,000 kW — total valuation > $2,500,000 | $3,446 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar >= 10,000 kW or Energy Storage System — total valuation < $50,000 | $553 | Sandy City 2026 Consolidated Fee Schedule, § 3122 Building Permit Fees, Residential Permits — Solar >10,000 kW or ESS |
| Solar >= 10,000 kW or ESS — total valuation $50,000–$100,000 | $638 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar >= 10,000 kW or ESS — total valuation $100,000–$250,000 | $1,037 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar >= 10,000 kW or ESS — total valuation $250,000–$500,000 | $1,303 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar >= 10,000 kW or ESS — total valuation $500,000–$1,000,000 | $2,150 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar >= 10,000 kW or ESS — total valuation $1,000,000–$2,500,000 | $3,107 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Solar >= 10,000 kW or ESS — total valuation > $2,500,000 | $3,796 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| Plan Review Fee | 65% of the building permit fee | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
| State Building Fee Surcharge | 1% of total permit fee | Sandy City 2026 Consolidated Fee Schedule, § 3122 — state-regulated surcharge |
| Re-Inspection Fee | $70 | Sandy City 2026 Consolidated Fee Schedule, § 3122 |
Review timeline
~3–10 business days
Typical estimate — confirm current times with the Sandy building department
Inspection process
- 1
Rough Electrical
Wiring, conduit, and connections before closing walls or covering junction boxes
- 2
Final / Interconnection
System fully installed, labeled, and ready for utility interconnection approval
Tips
- Rocky Mountain Power serves Sandy — contact them for interconnection approval before activating your system.
- Energy storage systems (batteries) use the higher >= 10,000 kW fee tier regardless of PV system size.
- Have your system equipment spec sheets ready; the building department may require manufacturer documentation.
Frequently asked questions
- Do I need a permit for rooftop solar in Sandy?
- Yes. Sandy requires a building permit for all residential solar PV installations. The contractor or homeowner must apply at the Building Division.
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
- Sandy City Building & Safety Division — official building department
- Sandy City 2026 Consolidated Fee Schedule (PDF)
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sandy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sandy
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.