Residential Building Permit in Orem, Utah

Required for new single-family homes, additions, structural alterations, accessory structures, and attached garages. Valuation is calculated using current ICC Building Valuation Tables (BVT). All submittals are online only via the CityInspect portal.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $1–$1,300$86.00Table 3A, 1997 UAC w/2023 revisions; valuation from ICC BVT. Source: Orem City FY 2025-2026 Adopted Budget (orem.gov, p. 204–206) referencing UAC Table 3A; tier amounts from Orem Consolidated Fee Schedule, Utah PMN file 1163157 (FY 2023–2024 edition).
Building Permit — valuation $1,301–$2,000$86.00 + $3.00 per each $100 or fraction thereof over $1,300Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Building Permit — valuation $2,001–$40,000$107.00 + $11.00 per each $1,000 or fraction thereof over $2,000Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Building Permit — valuation $40,001–$100,000$525.00 + $9.00 per each $1,000 or fraction thereof over $40,000Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Building Permit — valuation $100,001–$500,000$1,065.00 + $7.00 per each $1,000 or fraction thereof over $100,000Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Building Permit — valuation $500,001–$1,000,000$3,865.00 + $5.00 per each $1,000 or fraction thereof over $500,000Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Building Permit — valuation $1,000,001–$5,000,000$6,354.00 + $3.00 per each $1,000 or fraction thereof over $1,000,000Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Building Permit — valuation $5,000,001 and above$20,354.00 + $2.00 per each $1,000 or fraction thereof over $5,000,000Table 3A, 1997 UAC w/2023 revisions. Sources: same as above.
Plan Review — Commercial & ResidentialLesser of 65% of the permit fee or actual costOrem City FY 2025-2026 Adopted Budget, Building Safety Plan Review (p. 205).
Plan Review — Fast Track, Commercial (project value under $5M)$811.00 minimum + $88.00/hr if over 4 hoursOrem City FY 2025-2026 Adopted Budget, Building Safety Plan Review (p. 205).
Plan Review — Fast Track, Residential$291.00 minimum + $88.00/hr if over 2 hoursOrem City FY 2025-2026 Adopted Budget, Building Safety Plan Review (p. 205).
Re-inspection (Required Inspection Call-back)$125.00Orem City FY 2025-2026 Adopted Budget, Building Safety Special Inspections (p. 206).
Inspections Outside Normal Working Hours$151.00 + $88.00/hr if over 2 hoursOrem City FY 2025-2026 Adopted Budget, Building Safety Special Inspections (p. 206).
Building Without a PermitDouble the building permit fee (including plumbing, electrical, and mechanical)Orem City FY 2025-2026 Adopted Budget, Building Safety Miscellaneous Fees (p. 206).
Temporary Certificate of Occupancy — Residential$250.00 ($100.00 refunded if completed within 30 days, unless illegally occupied)Orem City FY 2025-2026 Adopted Budget, Building Safety Permits (p. 205).
Temporary Certificate of Occupancy — Commercial$390.00 (non-refundable)Orem City FY 2025-2026 Adopted Budget, Building Safety Permits (p. 205).

Review timeline

~515 business days

Typical estimate — confirm current times with the Orem building department

Inspection process

  1. 1

    Footing / Foundation

    Before concrete pour; verify setbacks, depth, reinforcement

  2. 2

    Framing

    After rough framing is complete, before insulation or drywall

  3. 3

    Rough-in (Electrical / Plumbing / Mechanical)

    After rough-in work is complete and accessible, before covering

  4. 4

    Insulation

    After insulation installed, before drywall

  5. 5

    Final

    All work complete; issues Certificate of Occupancy upon passing

Tips

Frequently asked questions

Do I need a permit for a storage shed?
Yes — accessory structures require a building permit. Check Orem's 'What Needs a Permit?' guide at orem.gov/buildingpermits/ for current thresholds.
How is project valuation determined?
Orem uses the ICC Building Valuation Tables (BVT) published by the International Code Council, not the contractor's bid amount.
Can I do the work myself?
Owner-builder permits are allowed for your primary residence. You must still obtain all required permits and pass inspections.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Orem building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Orem

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.