This is PermitBase’s published record for Spanish Fork as of 2026-06-30. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Spanish Fork building permits

Spanish Fork, Utah — as published 2026-06-30.

Reviewed 2026-06-30 · Source

Codes adopted

2021 International Building Code (IBC) with Utah Amendments — Spanish Fork Design Criteria page (effective 07/01/2025); statewide authority Utah Code § 15A-2-103. NOTE: 2024 IBC takes effect statewide 07/01/2026 per Utah Code § 15A-2-103 (2026 version).2021 International Residential Code (IRC) — Spanish Fork Design Criteria page; Utah Code § 15A-2-103(1)(b); IRC 2021 continues in force after 07/01/2026.2021 International Energy Conservation Code (IECC) — Spanish Fork Design Criteria page; Utah Code § 15A-2-103(1)(h); effective through 06/30/2026. NOTE: 2024 IECC takes effect statewide 07/01/2026.2023 National Electrical Code (NEC) — Spanish Fork Design Criteria page (listed as 'NEC 2023 Commercial Electrical'); Utah Code § 15A-2-103(1)(g).2021 International Fire Code (IFC) — Spanish Fork Design Criteria page; Utah Code § 15A-2-103(1)(c).2021 International Mechanical Code (IMC) — Spanish Fork Design Criteria page; Utah Code § 15A-2-103(1)(e); effective through 06/30/2026.2021 International Plumbing Code (IPC) — Spanish Fork Design Criteria page; Utah Code § 15A-2-103(1)(d); effective through 06/30/2026.2021 International Fuel Gas Code (IFGC) — Spanish Fork Design Criteria page; Utah Code § 15A-2-103(1)(f); effective through 06/30/2026.ICC/ANSI A117.1-2009 (ADA/Accessibility) — Spanish Fork Design Criteria page.NOTE: Effective July 1, 2026 — 2024 editions of IBC, IPC, IMC, IFGC, IECC replace 2021 editions statewide per Utah Code § 15A-2-103 (version effective 7/1/2026). IRC stays 2021; NEC stays 2023.

Permit types & fees

Residential Building Permit

Required for new residential construction, additions, structural alterations, and most residential projects in Spanish Fork. Applies to detached one- and two-family dwellings and townhouses not more than three stories, and their accessory structures.

Reviewed 2026-06-30 · Source

Requirements

  • New single-family or two-family dwelling construction
  • Additions (bedrooms, bathrooms, family rooms, garage conversions)
  • Structural alterations including load-bearing wall removal and framing modifications
  • Covered decks, garages, fireplaces
  • Renovations: garage conversions, kitchen expansion
  • Any project involving electrical, plumbing, or HVAC systems

Required documents

  • RequiredBuilding PlansComplete construction drawings including floor plans, elevations, sections, and structural details. Submit via CitizenServe online portal.
  • RequiredSite PlanProperty survey showing structure footprint, setbacks from property lines, and geotechnical report for footing inspections.
  • RequiredEnergy Compliance (REScheck or equivalent)Documentation demonstrating compliance with 2021 IECC (2024 IECC effective 07/01/2026). Required for new construction and additions affecting the thermal envelope.
  • OptionalEngineered Truss PlansSealed truss layouts from truss manufacturer for new construction using manufactured trusses.

Fee schedule

Fee typeAmountNotes
Building PermitAs set by 2021 IRC Appendix AL valuation tableSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026): 'Building Permit — As set by 2021 IRC.' The Appendix AL fee table is linked to codes.iccsafe.org (subscription-gated). Contact Spanish Fork Building Dept at (801) 804-4540 for a project-specific fee estimate.
Partial Building Permit (Residential)$90Spanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
Plan Check — Residential (per plan)$499 per plan; $129 per hour beyond 3 hoursSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
Duplicate Plan Check — Residential (per plan)$238 per planSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026). A separate $93 'not-ready' fee applies if the inspector arrives and work is not ready for inspection (per inspections page).
Temporary Certificate$120Spanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
Construction Deposit (Single-Family)$1,500 per building permitSpanish Fork Building Fees page, FY2026. Guarantees completion of permit conditions, site plan improvements, repair of city facility damage, and fee payment. Refunded once all permit conditions are met.
Construction Deposit (Multi-Family)$500 per building permit unitSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
State Surcharge1% of permit feeUtah state surcharge applied to all building permits.

Electrical Permit

Required for electrical work in Spanish Fork including new circuits, panel upgrades, service changes, and new construction wiring. Governed by the 2023 National Electrical Code (NEC) as confirmed on Spanish Fork's Design Criteria page.

Reviewed 2026-06-30 · Source

Requirements

  • New electrical circuits or wiring installations
  • Electrical panel upgrades or service entrance changes
  • Adding or relocating outlets, switches, or fixtures
  • Generator or solar panel electrical connections
  • Electric service changes (listed as permit-required on Spanish Fork permits page)

Required documents

  • RequiredPermit Application via CitizenServeApply online at citizenserve.com/spanishforkcity.
  • OptionalElectrical Plan / Single-Line DiagramRequired for service upgrades and new construction — panel schedule and circuit layout.
  • OptionalContractor LicenseValid Utah electrical contractor license (Utah DOPL) for work not performed by a homeowner on their own primary residence.

Fee schedule

Fee typeAmountNotes
Electrical PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current electrical sub-permit fee.Spanish Fork's fees.php page lists building permit, plan check, and re-inspection fees but does not break out a separate electrical sub-permit flat rate.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Plumbing Permit

Required for plumbing installations, alterations, and repairs in Spanish Fork including water heaters, fixture additions, and gas line work. Governed by the 2021 IPC; 2024 IPC effective statewide 07/01/2026.

Reviewed 2026-06-30 · Source

Requirements

  • New plumbing fixture installations (sinks, toilets, showers)
  • Water heater installation or replacement (including like-for-like swaps)
  • Water and sewer lateral repairs (listed in Spanish Fork permits FAQ)
  • Gas line installation or modification
  • Backflow prevention device installation

Required documents

  • RequiredPermit Application via CitizenServeApply online at citizenserve.com/spanishforkcity.
  • OptionalPlumbing PlanRequired for larger projects — isometric or plan showing fixture locations, pipe sizes, and drainage.
  • OptionalContractor LicenseValid Utah plumbing contractor license (Utah DOPL) for work not performed by a homeowner on their own primary residence.

Fee schedule

Fee typeAmountNotes
Plumbing PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current plumbing permit fee.Spanish Fork's fees.php page does not break out a separate plumbing permit flat rate.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Mechanical / HVAC Permit

Required for heating, ventilation, and air conditioning installations, replacements, and modifications in Spanish Fork. The city's FAQ explicitly lists 'furnace & water heater change outs/new installation' and 'air conditioners' as permit-required. Governed by the 2021 IMC; 2024 IMC effective statewide 07/01/2026.

Reviewed 2026-06-30 · Source

Requirements

  • Furnace or boiler installation or replacement (including like-for-like)
  • Air conditioning system installation or replacement
  • Ductwork installation or major modification
  • Evaporative cooler installation
  • Fireplace installation

Required documents

  • RequiredPermit Application via CitizenServeApply online at citizenserve.com/spanishforkcity. Select mechanical permit type.
  • OptionalEquipment SpecificationsManufacturer data sheets for furnace, AC, or heat pump.
  • OptionalContractor LicenseValid Utah HVAC/mechanical contractor license (Utah DOPL) for work not performed by the homeowner.

Fee schedule

Fee typeAmountNotes
Mechanical PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current mechanical permit fee.Spanish Fork's fees.php page does not break out a separate mechanical permit flat rate.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Roofing Permit

Required for roof replacement and re-roofing in Spanish Fork under the 2021 IRC. Covered under the general building permit fee schedule.

Reviewed 2026-06-30 · Source

Requirements

  • Complete roof replacement (tear-off and re-roof)
  • Structural roof repairs or modifications
  • Changes to roofing material type

Required documents

  • RequiredPermit Application via CitizenServeApply online at citizenserve.com/spanishforkcity.
  • OptionalContractor LicenseValid Utah roofing contractor license (Utah DOPL) if not performed by the homeowner.

Fee schedule

Fee typeAmountNotes
Roofing PermitValuation-based per 2021 IRC Appendix AL. Contact (801) 804-4540 for a fee estimate.Spanish Fork Building Fees page, FY2026: 'Building Permit — As set by 2021 IRC.' Roofing permits are valuation-based.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Solar Panel Permit

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Spanish Fork. Solar is explicitly listed as a permit type in CitizenServe. IMPORTANT: Spanish Fork operates its own municipal Power & Light electric utility — solar interconnection goes through Spanish Fork City, NOT Rocky Mountain Power.

Reviewed 2026-06-30 · Source

Requirements

  • Rooftop solar panel installation
  • Ground-mounted solar array installation
  • Battery storage system installation
  • Electrical service upgrade for solar interconnection

Required documents

  • RequiredSolar Permit Application (CitizenServe)Spanish Fork has a specific solar permit application type in CitizenServe. Apply at citizenserve.com/spanishforkcity.
  • RequiredSolar Site Plan / Roof PlanShowing panel placement, setbacks, and fire department access pathways on the roof.
  • RequiredElectrical Single-Line DiagramSystem wiring from panels to inverter to main panel and utility meter.
  • RequiredStructural AnalysisRoof load calculation confirming the structure can support the panels.
  • RequiredEquipment SpecificationsData sheets for panels, inverter, and racking system.
  • RequiredInterconnection Agreement (Spanish Fork City Power & Light)Spanish Fork operates its own municipal electric utility. Interconnection approval goes through Spanish Fork City Finance/Utilities, NOT Rocky Mountain Power. Contact (801) 804-4500.

Fee schedule

Fee typeAmountNotes
Solar PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current solar permit fee.Spanish Fork's fees.php does not publish a solar permit fee amount. Contact the building department.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Deck Permit

Required for deck construction in Spanish Fork. The city's permits page lists 'covered decks, decks over 30 inches above grade' as permit-required. Spanish Fork has a specific deck permit application type in CitizenServe.

Reviewed 2026-06-30 · Source

Requirements

  • Covered decks
  • Decks more than 30 inches above grade
  • Attached decks (ledger board connection to house)
  • Structural modifications to existing decks

Required documents

  • RequiredDeck Permit Application (CitizenServe)Spanish Fork has a specific deck permit type in CitizenServe. Apply at citizenserve.com/spanishforkcity.
  • RequiredDeck PlansFraming plan with beam/joist sizes, post locations, footing details, and ledger attachment method.
  • RequiredSite PlanShowing deck location with setbacks from property lines.

Fee schedule

Fee typeAmountNotes
Deck PermitValuation-based per 2021 IRC Appendix AL. Contact (801) 804-4540 for a fee estimate.Spanish Fork Building Fees page, FY2026: 'Building Permit — As set by 2021 IRC.' Deck permits are valuation-based.
Plan Check — Residential$499 per plan; $129 per hour beyond 3 hoursSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Basement Finish Permit

Verified

Required for finishing or remodeling an unfinished basement in Spanish Fork. Spanish Fork has a specific 'Basements' permit application in CitizenServe. The building FAQ states verbatim: 'There is no fee for a basement permit.'

Verified 2026-06-30 · Source

Requirements

  • Framing walls in an unfinished basement
  • Adding a bedroom (requires egress window per 2021 IRC)
  • Adding a bathroom (requires plumbing permit)
  • Electrical wiring for new rooms
  • Basement entrance modifications (structural engineering required for new foundation openings)

Required documents

  • RequiredBasement Permit Application (CitizenServe)Spanish Fork has a specific basement permit type in CitizenServe. Apply at citizenserve.com/spanishforkcity.
  • RequiredFloor PlanLayout showing room sizes, egress window locations, and door locations.
  • OptionalBasement Entrance Plans (if applicable)For new or widened basement entrances: show foundation remaining above door, footing/foundation detail with engineering, stair details (rise/run), handrail/guardrail detail, storm drain management, and landings at top and bottom. Engineering required for new or widened foundation openings; NOT required for existing window openings.

Fee schedule

Fee typeAmountNotes
Basement PermitNo feeSpanish Fork Building Department FAQ, verbatim: 'What does a basement permit cost and how do I apply? There is no fee for a basement permit.' Source: spanishfork.gov/departments/community_development/building/index.php, retrieved 2026-06-30.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Accessory Dwelling Unit (ADU) Permit

Required for construction of an accessory dwelling unit in Spanish Fork. The building department FAQ references a dedicated ADU page and ADUs require a building permit. CitizenServe has an ADU permit type.

Reviewed 2026-06-30 · Source

Requirements

  • New ADU construction (attached or detached)
  • Conversion of existing space to an ADU
  • Must meet Spanish Fork Municipal Code requirements — contact Community Development for current eligibility and size limits

Required documents

  • RequiredADU Permit Application (CitizenServe)Apply via CitizenServe at citizenserve.com/spanishforkcity. Spanish Fork has an ADU-specific permit type.
  • RequiredConstruction PlansFloor plan, elevations, sections, and structural details.
  • RequiredSite PlanShowing ADU placement, setbacks, parking, and access.
  • RequiredEnergy ComplianceREScheck or equivalent per 2021 IECC (2024 IECC effective statewide 07/01/2026).

Fee schedule

Fee typeAmountNotes
ADU Building PermitValuation-based per 2021 IRC Appendix AL. Contact (801) 804-4540 for a fee estimate.Spanish Fork Building Fees page, FY2026: 'Building Permit — As set by 2021 IRC.' ADUs follow the standard building permit valuation table.
Plan Check — Residential$499 per plan; $129 per hour beyond 3 hoursSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Fence Permit

Required for fence installation in Spanish Fork. Fences are explicitly listed as permit-required on the city's permits page. Spanish Fork has a specific fence permit application in CitizenServe. Fence regulations are in Municipal Code § 15.4.16.150.

Reviewed 2026-06-30 · Source

Requirements

  • Any new fence construction
  • Replacement of existing fence (confirm with building department whether like-for-like replacement requires a permit)
  • Fences in any residential zone

Required documents

  • RequiredFence Permit Application (CitizenServe)Apply at citizenserve.com/spanishforkcity. Select the fence permit type.
  • RequiredSite PlanShowing fence location relative to property lines and easements.

Fee schedule

Fee typeAmountNotes
Fence PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current fence permit fee.Spanish Fork's fees.php page does not list a separate fence permit fee. Contact the building department.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Water Heater Permit

Required for water heater installation, replacement, or conversion in Spanish Fork. The city's FAQ explicitly lists 'water heater change outs/new installation' as permit-required.

Reviewed 2026-06-30 · Source

Requirements

  • Water heater replacement (including like-for-like swaps)
  • New water heater installation
  • Conversion from tank to tankless water heater
  • Gas line modification for water heater

Required documents

  • RequiredPermit Application via CitizenServeApply at citizenserve.com/spanishforkcity.
  • OptionalContractor LicenseValid Utah plumbing contractor license (Utah DOPL) if not performed by the homeowner on their own primary residence.

Fee schedule

Fee typeAmountNotes
Water Heater PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current water heater permit fee.Spanish Fork's fees.php page does not list a separate water heater permit fee.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Swimming Pool Permit

Required for pool installation in Spanish Fork. The city's permits page explicitly lists 'pools over 24 inches deep' as permit-required. Spanish Fork has a specific swimming pool permit application in CitizenServe.

Reviewed 2026-06-30 · Source

Requirements

  • Above-ground pools with a depth over 24 inches
  • In-ground swimming pool construction
  • Hot tubs and spas over applicable size thresholds
  • Pool barrier/fence installation (required for all pools)

Required documents

  • RequiredSwimming Pool Permit Application (CitizenServe)Spanish Fork has a specific swimming pool permit type in CitizenServe. Apply at citizenserve.com/spanishforkcity.
  • RequiredSite PlanPool location with setbacks, equipment pad, and barrier/fence layout.
  • RequiredBarrier PlanPool fence/barrier details meeting 2021 IRC Chapter 31 requirements.
  • RequiredElectrical PlanPool pump, lighting, bonding, and GFCI protection details per 2023 NEC Article 680.

Fee schedule

Fee typeAmountNotes
Swimming Pool PermitValuation-based per 2021 IRC Appendix AL. Contact (801) 804-4540 for a fee estimate.Spanish Fork Building Fees page, FY2026: 'Building Permit — As set by 2021 IRC.' Pool permits are valuation-based.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Demolition Permit

Required for partial or complete demolition of structures in Spanish Fork, including utility disconnection coordination and required asbestos surveys for older structures.

Reviewed 2026-06-30 · Source

Requirements

  • Complete demolition of any structure
  • Partial demolition involving structural elements
  • Removal of load-bearing walls
  • Demolition of structures with potential asbestos or lead paint (pre-1980 construction)

Required documents

  • RequiredDemolition Permit Application (CitizenServe)Apply at citizenserve.com/spanishforkcity. Include scope of demolition and disposal plan.
  • OptionalAsbestos SurveyFederal NESHAP asbestos inspection required for structures built before approximately 1980.
  • RequiredUtility Disconnect ConfirmationProof that gas, electric, water, and sewer are disconnected prior to demolition.

Fee schedule

Fee typeAmountNotes
Demolition PermitNot individually listed on Spanish Fork's FY2026 fee schedule page. Contact (801) 804-4540 for the current demolition permit fee.Spanish Fork's fees.php page does not list a separate demolition permit fee.
Building Re-inspection$132 flat fee per tripSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).

Sources & verification

Key facts verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Spanish Fork building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-06-27)Later version (2026-07-01) →View current record →All versions →

Permalink: /utah/utah-county/spanish-fork/as-of/2026-06-30/

Snapshot date: 2026-06-30

Commit: dda7c46

Reproducible from PermitBase’s version-controlled dataset, commit dda7c46.