Santa Clara building permits
VerifiedSanta Clara, Utah — as published 2026-07-16.
Verified 2026-07-08 · Source
Codes adopted
Permit types & fees
Residential Building Permit
VerifiedRequired for new single-family residential construction and any work regulated by the statewide-adopted 2021 IRC and 2024 IBC with Utah amendments (Utah Code § 15A-2-103, effective 7/1/2026 for IBC; IRC unchanged). Santa Clara's Building Fee is valuation-based (current ICC rates) plus a 10% Plan Review Fee and 1% Utah State Surcharge, and the city's own municipal code sets a 10-day plan-review return requirement.
Verified 2026-07-20 · Source
Requirements
- New single-family residential construction
- Any work regulated by the adopted 2021 IRC with Utah state amendments
- Building permit application with plans/specifications submitted in duplicate plus one PDF digital copy, verified by the person performing or in charge of the work (waivable by the building official), per Santa Clara City Code § 15.04.020
- Exempt only where retail material cost is under $500 AND the work does not enlarge the structure or affect its walls, per § 15.04.010(B)
Required documents
- RequiredBuilding Permit Application (plans and specifications, duplicate + 1 PDF)Submitted in duplicate with one PDF digital copy, verified by the person who will perform or be in charge of the construction, per Santa Clara City Code § 15.04.020. Applications are processed through the city's online permit portal.
- RequiredClimatic & Geographic Design CriteriaSanta Clara City's published structural design criteria document (snow load, seismic, wind, frost depth), available in the Building Department's document library.
- OptionalGrading & Drainage Plan ChecklistRequired for site grading and drainage plan submittals, per Santa Clara City's Building Department document library.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Fee | Based on Valuation (current ICC rates) | Santa Clara City Building Permit Fees, effective January 2026: 'Building Fees — Based on Valuation.' Source: https://cdn.santaclarautah.gov/file/scweb-prod/2026/02/Building-Permit-Fees-Effective-Jan-2026.pdf. Valuation determined using current ICC Building Valuation Data rates (specific per-square-foot table not separately published by the city; the city's fee sheet references 'current ICC rates' generally rather than reproducing the ICC table). |
| Plan Review Fee | 10% of Building Fee | Santa Clara City Building Permit Fees, effective January 2026: 'Plan Review Fee — 10% of Building Fee.' |
| Utah State Surcharge | 1% of Building Fee | Santa Clara City Building Permit Fees, effective January 2026: 'Utah State Surcharge — 1% of Building Fee.' This is the statewide Uniform Building Code Commission surcharge collected by all Utah jurisdictions per Utah Code § 15A-1-403. |
| Minimum Building Inspection Fee | $56.00 | Santa Clara City Building Permit Fees, effective January 2026, 'Building Inspection Fees' section: 'Minimum Bldg. Inspection Fee — $56.00.' |
| New Home Maintenance Deposit | $500.00 | Santa Clara City Building Permit Fees, effective January 2026, 'Maintenance Deposits' section: 'New Home — $500.00.' |
| Water Connect (Culinary), 3/4-inch meter or less | $327.00 | Santa Clara City Building Permit Fees, effective January 2026. Larger meter sizes scale up to $5,900.00 for a 6-inch meter; see source document for full table. |
| Water Impact Fee, 3/4-inch meter or less | $3,057.00 | Santa Clara City Building Permit Fees, effective January 2026. Larger meter sizes scale up to $196,412.00 for a 6-inch meter; see source document for full table. |
| Sewer Connection Fee (City) | $774.00 | Santa Clara City Building Permit Fees, effective January 2026. |
| Electrical Connect (Underground, up to 200 amp) | $758.00 | Santa Clara City Building Permit Fees, effective January 2026. 400 amp underground service is $820.00. |
| Electrical Impact Fee (200 amp) | $4,454.00 | Santa Clara City Building Permit Fees, effective January 2026. 400 amp service is $8,908.00. |
| Street Impact Fee | $3,776.00 | Santa Clara City Building Permit Fees, effective January 2026. Multiplex rate is $2,324.00. |
| Parks & Trails Impact Fee | $2,372.00 | Santa Clara City Building Permit Fees, effective January 2026. |
| Public Safety Impact Fee | $1,230.00 | Santa Clara City Building Permit Fees, effective January 2026. |
| Storm Water Impact Fee (Fixed Rate by Zone, single-family) | R-1-10(.23): $2,163.98 | R-1-10(.18): $1,693.55 | R-1-6(.14): $1,317.21 | Santa Clara City Building Permit Fees, effective January 2026, 'Storm Water Impact' section, fixed rate by zoning designation. A variable per-acre rate of $9,408.62 also applies for larger/non-standard parcels (RA zone). |
Solar PV Permit
VerifiedRequired for residential rooftop, pole-mount, or ground-mount solar photovoltaic (PV) installations up to 12 kW AC that interconnect with Santa Clara City's municipal electric utility. Santa Clara City is its own power provider (not Rocky Mountain Power), so this permit bundles the building permit, a dedicated Solar Permit Application, and a required Renewable Net Metering & Interconnection Agreement into one process administered jointly by the Building Department and City Power Department. Commercial solar systems are not covered under this residential net metering policy and require a separate review/system impact study.
Verified 2026-07-19 · Source
Requirements
- Residential system limited to a maximum of 12 kW AC installed capacity under the City's Net Metering Policy (adopted February 24, 2016); commercial customers are reviewed separately and are not eligible under this policy
- All equipment, signage, and installation practices must meet NEC Articles 690 and 705
- Completed Building Permit Application plus the dedicated Solar Permit Application and signed Net Metering Agreement
- One-page site map and system one-line diagram showing solar module locations, inverter, batteries (if any), lockable disconnect switch, and utility point of connection, with installation address and installer's name/phone
- Structural load design and letter from a structural engineer licensed in the State of Utah
- Pre-operation inspection and written City approval required before the Facility may begin parallel operation with the City's electric distribution system
Required documents
- RequiredSolar Permit ApplicationSanta Clara City's dedicated solar application form (distinct from the general building permit form), capturing system type (utility interactive/dedicated circuit/stand-alone), kW AC installed capacity, module/inverter manufacturer and model, array location (rooftop/pole mount/ground mount), and inverter location.
- RequiredSite Map and System One-Line DiagramOne-page diagram indicating the location of the solar electric modules, inverter, batteries (if any), lockable disconnect switch, and point of connection with the utility system, with all electrical equipment specifications and calculations shown.
- RequiredEquipment DatasheetsDatasheets for all proposed equipment (solar panels, inverters, cable, etc.).
- RequiredStructural Load Design LetterStructural load design and letter from a structural engineer licensed in the State of Utah.
- RequiredRenewable Net Metering & Interconnection AgreementSigned agreement between the customer and Santa Clara City (City Power Department) governing net metering billing, the Solar Reliability Charge, Renewable Power Rate, disconnect device requirements, and pre-operation inspection.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Application Fee | $25.00 | Santa Clara City Solar Permit Application form, Building Fee Schedule section: 'Application Fee — $25.00.' |
| Net Meter Fee | $275.00 | Santa Clara City Solar Permit Application form, Building Fee Schedule section: 'Net Meter Fee — $275.00.' |
| Maintenance Deposit (Solar) | $500.00 | Santa Clara City Building Permit Fees, effective January 2026, 'Maintenance Deposits' section: 'Solar — $500.00' (confirmed consistent with the $500.00 Maintenance Deposit pre-printed on the Solar Permit Application form). Refundable after final inspection if the site is kept clean and the inspection is passed. |
| Building Fee | Based on Valuation (current ICC rates) | Santa Clara City Solar Permit Application form and Building Permit Fees schedule both list a valuation-based Building Fee line, calculated the same as the general residential building permit. |
| Plan Review Fee | 10% of Building Fee | Santa Clara City Building Permit Fees, effective January 2026: 'Plan Review Fee — 10% of Building Fee' (same rate applied on the Solar Permit Application form). |
| State Fee | 1% of Building Fee | Santa Clara City Solar Permit Application form, Building Fee Schedule section: 'State Fee (1%).' Matches the statewide Uniform Building Code Commission surcharge (Utah Code § 15A-1-403). |
Accessory Dwelling Unit (ADU) Conditional Use Permit
VerifiedRequired for construction of an Accessory Dwelling Unit in Santa Clara, in addition to the standard building permit. Governed by Zoning Ordinance #2022-04; reviewed by a weekly Technical Review Committee (TRC) as an Administrative Conditional Use.
Verified 2026-07-08 · Source
Requirements
- ADU must be located on the same lot as an existing single-family owner-occupied dwelling on residentially zoned property
- ADU must contain complete cooking and bathroom facilities independent from the primary dwelling
- ADU must maintain the single-family appearance and character of the neighborhood
- ADU must be served by the same power and culinary water meters as the primary dwelling
- ADU must be rented for periods of 30 consecutive days or more (short-term rental use is prohibited)
- One ADU per property is permitted
- One additional off-street parking space required
- Building permit required for all new, remodel, and finish work associated with the ADU; compliance with the adopted IRC and state amendments is required
Required documents
- RequiredAccessory Dwelling Unit (ADU) Conditional Use ApplicationOfficial city application form (rev. August 2025) requiring a site/plot plan (showing existing/proposed buildings, off-street parking, ADU location/dimensions) and floor plans (architectural layout, door/window sizes, ceiling height, smoke/CO detector locations).
- RequiredBuilding Permit ApplicationA separate building permit is required for all new construction, remodel, and finish work associated with the ADU, per the ADU Conditional Use Application form.
- RequiredLegal Description of Property (Washington County Recorder's Office)Required on a separate single-sided original page for recording, per the ADU application's Washington County Recorder's Office requirements.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| ADU Conditional Use Filing Fee | $100.00 | Santa Clara City ADU Conditional Use Application (rev. August 2025): 'Filing Fees: $100.00,' as provided by Santa Clara, Utah Zoning Ordinance #2022-04. This is separate from and in addition to the standard building permit fees for the ADU construction itself (see residential-building-permit entry). |
Commercial Building Permit
Required for new commercial construction in Santa Clara, regulated by the 2024 IBC (current statewide per Utah Code § 15A-2-103, effective 7/1/2026). Santa Clara City's own 'Building Permit Fees' schedule (effective January 2026) sets Building Fees as valuation-based per current ICC rates, with a 10% Plan Review Fee and a 1% Utah State Surcharge — the schedule does not publish a separate residential/commercial split or a dedicated commercial valuation table distinct from these generic rates.
Reviewed 2026-07-19 · Source
Requirements
- New commercial construction regulated by the 2024 IBC (Utah Code § 15A-2-103(1)(a))
- Application submitted through the Santa Clara City Inspect online portal (utah.cityinspect.com)
- Project valuation stated on the application, based on current ICC Building Valuation Data rates per the city's own fee schedule
Required documents
- RequiredBuilding Permit Application (CityInspect)Submitted online via Santa Clara City's CityInspect portal. No dedicated commercial-specific submittal checklist document was located on santaclarautah.gov as of 2026-07-19 — the Building Department page's document library lists forms such as the Gas Sizing Installation Plan, Grading & Drainage Plan Checklist, and Climatic & Geographic Design Criteria, but no commercial-plan-submittal-specific checklist distinct from these general construction documents.
- RequiredGrading & Drainage Plan ChecklistSanta Clara City's published checklist for grading and drainage plans, applicable to commercial site development.
- RequiredConstruction Plans and EngineeringFull architectural, structural, electrical, mechanical, and plumbing plans reflecting the 2024 IBC and Utah's adopted Climatic & Geographic Design Criteria (2021).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Fees (valuation-based) | Based on Valuation, using current ICC rates | Santa Clara City 'Building Permit Fees' schedule (effective January 2026), 'Building Fee Valuation: Based on current ICC rates.' Not split by residential vs. commercial in the published document. |
| Plan Review Fee | 10% of Building Fee | Santa Clara City 'Building Permit Fees' schedule (effective January 2026): 'Plan Review Fee — 10% of Building Fee.' No commercial-specific percentage is separately published. |
| Utah State Surcharge | 1% of Building Fee | Santa Clara City 'Building Permit Fees' schedule (effective January 2026): 'Utah State Surcharge — 1% of Building Fee.' |
| Minimum Building Inspection Fee | $56.00 | Santa Clara City 'Building Permit Fees' schedule (effective January 2026): 'Minimum Bldg. Inspection Fee — $56.00.' |
| Re-Inspection Fee | $56.00 | Santa Clara City 'Building Permit Fees' schedule (effective January 2026): 'Re-Inspection Fee — $56.00.' |
| Maintenance Deposit (commercial, catch-all 'All Others' category) | $100.00 | Santa Clara City 'Building Permit Fees' schedule (effective January 2026), 'Maintenance Deposits' table: 'All Others — $100.00' (distinct from the $500.00 deposit for New Home, Pool, or Solar) — commercial construction is presumed to fall under this catch-all category, though the schedule does not explicitly label it as commercial. |
Commercial Tenant Improvement / Tenant Finish Permit
Required for tenant improvement and tenant finish work in existing commercial buildings in Santa Clara. No dedicated tenant-improvement checklist, application category, or fee line distinct from new commercial construction was found published on santaclarautah.gov as of 2026-07-19 — the same generic 'Building Permit Fees' schedule (effective January 2026) that governs the Commercial Building Permit entry in this file is the only identified fee mechanism.
Reviewed 2026-07-19 · Source
Requirements
- Commercial remodel or tenant improvement work in an existing commercial structure
- Application submitted through the Santa Clara City Inspect online portal (utah.cityinspect.com)
- Project valuation stated on the application, based on current ICC Building Valuation Data rates
Required documents
- RequiredBuilding Permit Application (CityInspect)Submitted online via Santa Clara City's CityInspect portal. No tenant-improvement-specific checklist document was located on santaclarautah.gov as of 2026-07-19.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Fees (valuation-based), inferred mechanism | Based on Valuation, using current ICC rates | Santa Clara City's 'Building Permit Fees' schedule publishes only one generic valuation-based Building Fee line, with no tenant-improvement-specific rate. This entry assumes the same mechanism applies to TI work, but that has not been independently confirmed against a TI-specific line item. |
| Plan Review Fee | 10% of Building Fee | Santa Clara City 'Building Permit Fees' schedule (effective January 2026): 'Plan Review Fee — 10% of Building Fee' — not split by permit type. |
| Utah State Surcharge | 1% of Building Fee | Santa Clara City 'Building Permit Fees' schedule (effective January 2026). |
Fire Sprinkler System Permit
Required for new fire sprinkler system installations and for remodel/tenant-finish sprinkler work in Santa Clara. Plan review and inspection are handled not by the Building Department but by Santa Clara-Ivins Fire Rescue (SCIFRU) — the joint fire agency serving both Santa Clara and Ivins — under Santa Clara City Code § 2.28.140 and the fee schedule adopted by Santa Clara City Council Resolution No. 2024-01R (effective January 10, 2024).
Reviewed 2026-07-20 · Source
Requirements
- New fire sprinkler system installations are billed by sprinkler head count tier, all at the same hourly plan review rate
- Remodel or tenant-finish sprinkler work uses a separate, lower-tiered fee track based on head count
- Underground flush and hydrostatic/acceptance testing required before final sign-off
- Installation without a permit triggers double the applicable fee plus a $100.00 penalty, per the SCIFRU fee schedule
- Governed by Santa Clara City Code § 2.28.140 (adopting the SCIFRU fee schedule by resolution) and Resolution No. 2024-01R
Required documents
- RequiredFire Sprinkler Plan SubmittalPlans submitted to Santa Clara-Ivins Fire Rescue for review; no dedicated online application form distinct from this fee-schedule-driven review was found published on santaclarautah.gov as of 2026-07-20 (the department's 'Popular Forms' list includes only Burn Permit and Special Event Permit applications). Confirm current submittal method directly with SCIFRU.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plan Review, New System (100 heads or fewer) | $126.00 per hour | Santa Clara-Ivins Fire Rescue fee schedule, Resolution No. 2024-01R (effective 1/10/2024), 'Fire Sprinkler Systems Plan Review' section, confirmed via direct page-image render (page 11): 'Plan Review (100 heads or fewer) — $126.00 per hour.' The same $126.00/hour rate applies at every published head-count tier (101-199, 200-299, over 300 heads) — the schedule does not step the rate up by system size. |
| Plan Review, Remodel or Tenant Finish (fewer than 5 heads) | $65.00 flat | Resolution No. 2024-01R, 'Fire Sprinkler Systems Plan Review — Remodel or Tenant Finish' section: 'Plan Review (fewer than 5 heads) — $65.00.' Confirmed via direct page-image render (page 11). |
| Plan Review, Remodel or Tenant Finish (5-50 heads) | $126.00 flat | Resolution No. 2024-01R: 'Plan Review (5 – 50 heads) — $126.00' (flat fee, not hourly, at this tier). Systems over 50 heads revert to $126.00 per hour. Confirmed via direct page-image render (page 11). |
| Underground Flush / Hydrostatic / Acceptance Testing (first 2 tests) | $60.00 each | Resolution No. 2024-01R, 'Acceptance Testing' section: 'Underground Flush — $60.00,' 'Hydrostatic Testing for First 2 Tests — $60.00,' 'Acceptance Testing for First 2 Tests — $60.00'; further tests are $60.00 each. Confirmed via direct page-image render (page 11). |
| Standpipe | $100.00 | Resolution No. 2024-01R, 'Acceptance Testing' section: 'Standpipe — $100.00.' Confirmed via direct page-image render (page 11). |
| Fire Sprinkler Inspection / Re-Inspection | $135.00 each | Resolution No. 2024-01R, 'Inspection and Enforcement Fees' section: 'Fire Sprinkler Inspection — $135.00' and 'Re-Inspection — $135.00.' Confirmed via direct page-image render (page 14). |
| Stop Work Order / Installation Without a Permit | Stop Work Order $100.00; Installation without a permit = double the applicable fee plus $100.00 | Resolution No. 2024-01R, 'Inspection and Enforcement Fees' section: 'Stop Work Order — $100.00' and 'Installation without a Permit — Double fee plus $100.00.' These two figures are identical everywhere they recur in the fee table. Confirmed via direct page-image render (page 14). |
| Plan Review Expedited (Alarm or Sprinkler) — figure uncertain | Published inconsistently as either $252.00 per hour or $314.00 per hour | Resolution No. 2024-01R's 'Inspection and Enforcement Fees' table (page 14, confirmed via direct page-image render) lists 'Plan Review for Sprinkler System Expedited' TWICE with two different values: $252.00 per hour in the first listing (grouped with 'Plan Review for Alarm Expedited,' also $252.00/hour), and $314.00 per hour in a second, separately-repeated block further down the same table. A parallel 'Fire Watch' line item shows the same pattern ($75.00/hour + $150.00 minimum in the first block vs. $57.00/hour + $150.00 minimum in the second block). This could not be reconciled from the published PDF alone — both figures are quoted here rather than guessing which supersedes; confirm the current expedited-review rate directly with SCIFRU before relying on either number. Re-chased 2026-07-20: re-fetched the live cdn.santaclarautah.gov PDF fresh (still the only fee document on file) and re-rendered page 14 to a 200dpi PNG independently — the same duplicate '$252.00 per hour' / '$314.00 per hour' entries are still both present, confirming this is a genuine typo/duplication in the City's own adopted resolution, not a fetch or column-alignment artifact. Checked Santa Clara Municipal Code § 2.28.140 (American Legal Publishing codelibrary.amlegal.com) for a newer superseding fee resolution — it still cites 'Ord. 2024-01' as the governing fee-schedule ordinance, with no newer 2025/2026 resolution found via direct search or web search. Genuinely unresolvable without contacting SCIFRU directly. A second re-chase on 2026-07-20 checked whether SCIFRU's own dedicated website (scifire.us, distinct from Santa Clara's city site) or the joint agency's other member city, Ivins, hosts a cleaner or corrected copy: (1) SCIFRU's live site returned a Cloudflare 520 error at the time of this check, so its 'Fees, Forms & Permits' page (scifire.us/fees-permits/), 'About > Finance' page, and 'Risk Reduction' program page were all instead fetched via Wayback Machine archives (Aug-Oct 2024 snapshots) -- none host an independent fee-schedule document; the Fees/Forms/Permits page links only to the same Santa Clara-hosted PDF, a GRAMA records-request form, and the MedUSA ambulance-billing portal, with no alternate PV of the plan-review fee table. (2) Checked whether Ivins City (SCIFRU's other member city) separately adopted or re-published the same fee schedule under its own resolution numbering -- confirmed Ivins numbers its resolutions independently from Santa Clara (Ivins' own 'Resolution 2024-01R' is an unrelated solid-waste billing-fee increase, not the fire fee schedule), and no Ivins-hosted copy of the SCIFRU fire fee table was found via its Consolidated Fee Schedule documents (2021-18R and the 2024 amending Ordinance 2024-12, neither of which contains any fire/SCIFRU line items at all -- Ivins appears to defer entirely to Santa Clara's resolution as the single governing document, with no parallel copy to cross-check against). The $252/$314 duplication remains confirmed as an error in the sole surviving copy of the governing resolution, not a fetch artifact, and is not resolvable without a direct records request to SCIFRU or the Santa Clara City Recorder for the original signed/adopted version. |
Fire Alarm System Permit
VerifiedRequired for new fire alarm system installations, remodels, and additional-floor expansions in Santa Clara. Like the Fire Sprinkler System Permit, this is reviewed by Santa Clara-Ivins Fire Rescue (SCIFRU) under Santa Clara City Code § 2.28.140, with fees set by Resolution No. 2024-01R (effective January 10, 2024) — a fully distinct fee category from sprinkler plan review in the resolution's own table structure, though the published hourly rates happen to match.
Verified 2026-07-20 · Source
Requirements
- Applies to new fire alarm system installations, remodels of existing systems, and additional-floor expansions
- Installation without a permit triggers double the applicable fee plus a $100.00 penalty
- Governed by Santa Clara City Code § 2.28.140 and Resolution No. 2024-01R
Required documents
- RequiredFire Alarm Plan SubmittalPlans submitted to Santa Clara-Ivins Fire Rescue for review; no dedicated online application form distinct from this fee-schedule-driven review was found published on santaclarautah.gov as of 2026-07-20. Confirm current submittal method directly with SCIFRU.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plan Review, New System | $126.00 per hour | Resolution No. 2024-01R, 'Fire Alarm Systems Plan Review' section, confirmed via direct page-image render (page 11): 'Plan Review New System — $126.00 per hour.' |
| Plan Review, Remodel or Additional Floors | $126.00 per hour | Resolution No. 2024-01R: 'Plan Review Remodel — $126.00 per hour' and 'Plan Review Additional Floors — $126.00 per hour.' Confirmed via direct page-image render (page 11). |
| Acceptance Testing (first two tests) / Further Acceptance Tests | $60.00 / $60.00 each | Resolution No. 2024-01R, 'Fire Alarm Systems Plan Review' section: 'Acceptance Testing for First Two Tests — $60.00' and 'Further Acceptance Tests — $60.00 each.' Confirmed via direct page-image render (page 11). |
| Fire Alarm Inspection / Re-Inspection | $135.00 each | Resolution No. 2024-01R, 'Inspection and Enforcement Fees' section: 'Fire Alarm Inspection — $135.00' and 'Re-Inspection — $135.00.' Confirmed via direct page-image render (page 14). |
| Stop Work Order / Installation Without a Permit | Stop Work Order $100.00; Installation without a permit = double the applicable fee plus $100.00 | Resolution No. 2024-01R, 'Inspection and Enforcement Fees' section: 'Stop Work Order — $100.00' and 'Installation without a Permit — Double fee plus $100.00.' Confirmed via direct page-image render (page 14). |
| Plan Review for Alarm Expedited | $252.00 per hour | Resolution No. 2024-01R, 'Inspection and Enforcement Fees' section: 'Plan Review for Alarm Expedited — $252.00 per hour.' Confirmed via direct page-image render (page 14). Unlike the sprinkler-side expedited line item, this figure appears only once in the table with no conflicting duplicate. |
Sign Permit
VerifiedRequired for monument, wall, free-standing, and temporary signs in Santa Clara City, per the city's Sign Permit Application and City Code Chapter 17.44 (Signs). Unlike most other permit types in this file, signs carry a distinct, directly published per-square-foot fee rather than a valuation-based building fee. Signs may not be installed until the permit is issued, and Planning & Zoning approval may be required before the application can be processed.
Verified 2026-07-20 · Source
Requirements
- Applies to Monument (low profile) signs, Wall signs, Free-standing signs, and Temporary signs (maximum 30-day display)
- Sign(s) may NOT be installed until the permit is issued
- Incomplete applications will not be accepted
- Planning & Zoning approval may be required before the application can be processed
- Real estate for-sale/lease signs are exempt from the sign permit requirement per City Code — such signs must be no more than 4' x 8' (32 sq ft), top of sign/support no higher than 8', set at least 2' inside the property line, and removed within 30 days of sale or lease
- Temporary signs (general, non-real-estate) may not exceed 6 sq ft in area or 4 ft in height, must sit at least 2' behind the property line, and are limited to one per parcel (except up to 3 per parcel in the 60 days preceding an election)
Required documents
- RequiredSign Permit ApplicationSanta Clara City Sign Permit Application (August 2025 version); includes sign location, business name, sign company/license info, sign type, total square footage, and value of sign.
- RequiredDimensioned, Scaled DrawingsRequired for ALL sign types: height, color, square footage, dimensions, sign composition, type of illumination, and how the sign will appear from the street.
- RequiredDetails of Sign ConstructionRequired for all sign types.
- RequiredElectrical SchematicsRequired for all sign types.
- OptionalPlot Plan (Monument, Free-Standing, and Temporary Signs)Shows relationship of sign to buildings, property lines, setback from public rights-of-way, intersections, easements, and driveways. Monument/free-standing signs additionally require number of acres and length of lineal property frontage.
- OptionalProfile Drawing (Wall Signs)Shows how the sign will appear from the street/parking area and on the building; must show all existing signs on wall faces plus the proposed sign(s).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sign Permit Fee | $3.00 per square foot | Santa Clara City Sign Permit Application (August 2025): 'SIGN PERMIT APPLICATION Fee: $3 per sq. ft.' This is a distinct, directly published per-square-foot fee — the city's separate Building Permit Fees schedule (effective January 2026) does not contain a sign-specific line item, consistent with signs being priced off this dedicated application form rather than the general ICC valuation table used for building permits under City Code § 15.08.020. |
EV Charger / EVSE Permit
VerifiedSanta Clara City's Building Permit Fees schedule (effective January 2026) has no standalone "Electrical Permit," "EV Charger," or "EVSE" line item. Building Fees are assessed purely on construction valuation ("Based on Valuation," using current ICC rates), with a Plan Review Fee of 10% of the Building Fee — meaning EV charger/EVSE installation is billed through the same valuation-based Building Fee as any other permitted work, with no distinct electrical or EV carve-out. (The schedule's "Electrical Connect" and "Electrical Impact" entries are utility meter-size connection/impact fees for new water/power service, unrelated to permitting a charger installation.)
Verified 2026-07-20 · Source
Requirements
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Santa Clara City
- Work performed per Santa Clara City's adopted electrical code
Required documents
- RequiredBuilding Permit ApplicationSubmitted to Santa Clara City for electrical/trade work, valuation-based per the Building Permit Fees schedule.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Fee — valuation-based | Based on Valuation (current ICC rates) | Santa Clara City Building Permit Fees (Effective January 2026): "Building Fees — Based on Valuation." No standalone Electrical Permit or EV Charger fee line exists anywhere in the schedule (confirmed via full-text search); all trade work including EVSE installation is priced through this single valuation-based Building Fee. |
| Plan Review Fee | 10% of Building Fee | Santa Clara City Building Permit Fees (Effective January 2026). |
| Minimum Building Inspection Fee | $56.00 | Santa Clara City Building Permit Fees (Effective January 2026). |
Certificate of Occupancy / Change of Use Permit
Required before any land is used or occupied, or before a structurally altered or newly erected building is changed in use, per Santa Clara City Code § 17.04.070 'Occupancy Permit Required.' A certificate of occupancy must also be issued whenever the character or use of any building or land is proposed to change from one use to another, even where no new construction is involved. Santa Clara does not publish a standalone Change of Use or Certificate of Occupancy application, fee line, or review-timeline figure distinct from the general Building Permit Application/final-inspection process — this was checked directly against the city's Forms and Applications page, the Building Department page, and the January 2026 Building Permit Fees schedule on 2026-07-22, none of which list a dedicated product for this permit type.
Reviewed 2026-07-22 · Source
Requirements
- No land may be used or occupied, and no building structurally altered or erected may be changed in use, until a final inspection has been completed and a certificate of occupancy issued by the city, per City Code § 17.04.070
- The certificate of occupancy must state that the building, its proposed use, or the use of the land complies with Title 17 (Zoning), including the provisions governing the renewing, changing, or extending of a nonconforming use
- A certificate of occupancy is also required whenever the character or use of any building or land is proposed to be changed from one use to another use, independent of any construction scope
- Where the use change is paired with construction/tenant-finish work, the associated Building Permit Application (see commercial-building-permit and commercial-tenant-improvement-permit entries in this file) governs the construction side; the certificate of occupancy is issued at final inspection under that same permit
Required documents
- RequiredBuilding Permit Application (CityInspect)Where a use change accompanies construction or tenant-finish work, it is processed through the same online Building Permit Application (utah.cityinspect.com) as the underlying construction, with the certificate of occupancy issued at final inspection. No separate standalone 'Change of Use' or 'Certificate of Occupancy' application form was found published on santaclarautah.gov as of 2026-07-22 — confirm the correct submittal path with the Building Department for a pure use-change with no construction scope.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Certificate of Occupancy / Change of Use Fee — no dedicated line item found | Not published | The January 2026 'Building Permit Fees' schedule (cdn.santaclarautah.gov) contains no 'Occupancy,' 'Certificate of Occupancy,' or 'Change of Use' fee line (confirmed via direct full-text review of the two-page PDF on 2026-07-22). Where a use change is paired with construction, the standard valuation-based Building Fee, 10% Plan Review Fee, and 1% Utah State Surcharge apply to that underlying permit (see commercial-building-permit entry). For a pure use change with no construction scope, no fee mechanism is published; confirm directly with the Building Department, (435) 656-4690. |
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santa Clara building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.