You are viewing the permanent link for the record currently in effect, published 2026-09-16.
Wenatchee building permits
VerifiedWenatchee, Washington — as published 2026-09-16.
Verified 2026-09-16 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for new one- and two-family dwellings and townhouses in Wenatchee, reviewed under the International Residential Code as adopted at WCC 2.04.010 — which names the 2018 edition.
Verified 2026-09-16 · Source
Requirements
- “The 2018 International Residential Code … with amendments as set forth in Chapter 51-51 WAC as the same exists now or may hereafter be amended” (WCC 2.04.010), with Appendix J and Appendix M (Home Day Care) specifically adopted
- THE NAMED YEAR IS 2018 AND THE CITED WAC CHAPTER CURRENTLY CARRIES 2021 — confirm the operative edition with the building official
- Only Class A, B or C roofing assemblies may be installed within the city limits (R902.1 as amended)
- Sheds up to 200 sq ft are exempt but must sit five feet from all property lines and one foot clear of other structures, or they count as attached and need a permit
- Permits expire if work does not start within 180 days, if work stops for 180 days, or two years after issuance regardless of progress (WCC 2.06.010)
Required documents
- RequiredBuilding Permit ApplicationWCC 2.06.010 requires a written application on a city form that identifies and describes the work, describes the land by legal description or street address, indicates the intended use and occupancy, is accompanied by construction documents per the city's submittal requirements, and is signed by the applicant or agent.
- RequiredConstruction Documents“as required by the submittal requirements established by the city” (WCC 2.06.010).
- OptionalSpecial Inspection Agency DocumentationWhere special inspections apply: written documentation to the building official BEFORE permit issuance showing accreditation to ASTM E329, ASTM D 3740 or ASTM C 1077 as applicable, or registration in the WABO Special Inspection Registration Program (IBC 1704.2.1 as amended).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee | Not published in code; ask the city | NO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Show full citationHideNO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Neither WCC Chapter 2.04 (all three sections) nor WCC Chapter 2.06 (Permits, its single section) states a permit fee or points to one. The only fee reference found anywhere in Title 2 is an ADMINISTRATIVE APPEAL fee — the International Property Maintenance Code as amended provides that “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010”. WCC 1.99.010 sits in Title 1 and was NOT opened for this entry. Ask the city for the current schedule. |
| Administrative appeal | Set by WCC 1.99.010; ask the city | IPMC Sections 109.6 and 111.1 as amended: “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010.” That section sits in WCC Title 1 and was not opened for this entry, so no amount is asserted. |
Commercial Building Permit
VerifiedRequired for commercial construction, alteration, demolition and change of occupancy in Wenatchee, under the International Building Code as adopted at WCC 2.04.010 — which names the 2018 edition.
Verified 2026-09-16 · Source
Requirements
- “The 2018 International Building Code … with amendments as set forth in Chapter 51-50 WAC as the same exists now or may hereafter be amended” (WCC 2.04.010); Appendix H, Signs, is specifically adopted
- THE NAMED YEAR IS 2018 AND THE CITED WAC CHAPTER CURRENTLY CARRIES 2021 — confirm with the building official
- A conflict rule is built into the adoption: “the first named code shall govern over those following”, and the IBC is first
- Special inspection agencies must be ASTM-accredited or WABO-registered, documented before permit issuance
- Sheds are exempt only to 120 square feet under the IBC amendment, with a 10-foot separation from other structures and property lines
Required documents
- RequiredBuilding Permit ApplicationPer WCC 2.06.010 — written, on a city form, identifying the work, land, intended use and occupancy, with construction documents, signed by applicant or agent.
- OptionalSpecial Inspection Agency DocumentationAccreditation to ASTM E329, D 3740 or C 1077 as applicable, or WABO Special Inspection Registration Program membership, provided to the building official before the permit issues (IBC 1704.2.1 as amended).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee | Not published in code; ask the city | NO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Show full citationHideNO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Neither WCC Chapter 2.04 (all three sections) nor WCC Chapter 2.06 (Permits, its single section) states a permit fee or points to one. The only fee reference found anywhere in Title 2 is an ADMINISTRATIVE APPEAL fee — the International Property Maintenance Code as amended provides that “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010”. WCC 1.99.010 sits in Title 1 and was NOT opened for this entry. Ask the city for the current schedule. |
| Administrative appeal | Set by WCC 1.99.010; ask the city | IPMC Sections 109.6 and 111.1 as amended: “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010.” That section sits in WCC Title 1 and was not opened for this entry, so no amount is asserted. |
Mechanical Permit
VerifiedRequired for mechanical work in Wenatchee under the International Mechanical Code as adopted at WCC 2.04.010, which names the 2018 edition.
Verified 2026-09-16 · Source
Requirements
- “The 2018 International Mechanical Code … with amendments as set forth in Chapter 51-52 WAC as the same exists now or may hereafter be amended, except that Table 403.3.1.1 published by the International Code Council, Inc., sha…” (WCC 2.04.010; the Table 403.3.1.1 exception continues past the extract read for this entry and is NOT reproduced)
- A permit is required to “erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system” (WCC 2.06.010)
- The IMC ranks third in the conflict order, behind the IBC and IRC
Required documents
- RequiredMechanical Permit ApplicationPer WCC 2.06.010.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee | Not published in code; ask the city | NO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Show full citationHideNO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Neither WCC Chapter 2.04 (all three sections) nor WCC Chapter 2.06 (Permits, its single section) states a permit fee or points to one. The only fee reference found anywhere in Title 2 is an ADMINISTRATIVE APPEAL fee — the International Property Maintenance Code as amended provides that “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010”. WCC 1.99.010 sits in Title 1 and was NOT opened for this entry. Ask the city for the current schedule. |
Plumbing Permit
VerifiedPlumbing work in Wenatchee is still regulated even though the plumbing CHAPTER was repealed in 2004 — the Uniform Plumbing Code is adopted through the referenced-codes chapter instead.
Verified 2026-09-16 · Source
Requirements
- WCC Chapter 2.20 PLUMBING CODE reads “(Repealed by Ord. 2004-25)”
- BUT the code survives elsewhere: “The 2018 Edition of the Uniform Plumbing Code (UPC), including Appendices A, B and I, and Uniform Plumbing Code Standards … with amendments as set forth in Chapter 51-56 WAC as the same exists now or …” (WCC 2.04.010)
- A permit is required to erect, install, alter, repair, remove, convert or replace any plumbing system (WCC 2.06.010)
- The UPC ranks fourth and last in the conflict order
Required documents
- RequiredPlumbing Permit ApplicationPer WCC 2.06.010.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Permit fee | Not published in code; ask the city | NO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Show full citationHideNO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Neither WCC Chapter 2.04 (all three sections) nor WCC Chapter 2.06 (Permits, its single section) states a permit fee or points to one. The only fee reference found anywhere in Title 2 is an ADMINISTRATIVE APPEAL fee — the International Property Maintenance Code as amended provides that “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010”. WCC 1.99.010 sits in Title 1 and was NOT opened for this entry. Ask the city for the current schedule. |
Electrical Permit
VerifiedWenatchee repealed its electrical chapter in 2021 and adopts no electrical code in its referenced-codes chapter.
Verified 2026-09-16 · Source
Requirements
- WCC Chapter 2.08 ELECTRICAL CODE reads “(Repealed by Ord. 2021-01)”
- NO ELECTRICAL CODE APPEARS in the WCC 2.04.010 list — unlike plumbing, which survives the repeal of its own chapter
- WCC 2.06.010 still requires a permit to “erect, install, enlarge, alter, repair, remove, convert or replace any electrical … system”, so the permit requirement outlived the code chapter
- CONFIRM WITH THE CITY AND WITH L&I who issues electrical permits; this entry does not establish it
Required documents
- RequiredElectrical Permit ApplicationNOT ESTABLISHED. WCC 2.06.010 still requires a permit for electrical system work while the electrical chapter is repealed and no electrical code is adopted in WCC 2.04.010. Ask the city and the Washington State Department of Labor and Industries before filing.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical permit | Not published in code; ask the city | No electrical fee is asserted. WCC Chapter 2.08 is repealed, no electrical code appears in the WCC 2.04.010 list, and no fee schedule appears in those sections. Show full citationHideNo electrical fee is asserted. WCC Chapter 2.08 is repealed, no electrical code appears in the WCC 2.04.010 list, and no fee schedule appears in those sections. NO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Neither WCC Chapter 2.04 (all three sections) nor WCC Chapter 2.06 (Permits, its single section) states a permit fee or points to one. The only fee reference found anywhere in Title 2 is an ADMINISTRATIVE APPEAL fee — the International Property Maintenance Code as amended provides that “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010”. WCC 1.99.010 sits in Title 1 and was NOT opened for this entry. Ask the city for the current schedule. |
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wenatchee building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.