Codes adopted

UPMC 14.05.030 opens: “The following codes are hereby adopted by this reference as if fully set forth in this chapter and as specifically modified or amended as set forth in this chapter:”IBC — “The 2021 Edition of the International Building Code, including Appendix E, and ICC/ANSI A117.1-2017, and the 2021 International Existing Building Code and International Swimming Pool and Spa Code published by the International Code Council, is hereby adopted b…” (extract ends there). Three codes and an accessibility standard in one sentence.IRC — “The 2021 Edition of the International Residential Code including Appendices F, Q and U as published by the International Code Council is hereby adopted as amended by the Washington State Building Code Council in Chapter 51-51 WAC…” Appendices F (Radon), Q (Tiny Houses) and U (Dwelling Unit Fire Sprinkler Systems) — the same three Issaquah takes, where Lake Stevens takes only F and Q.IMC / FUEL GAS — “The 2021 Edition of the International Mechanical Code, including adoption of and amendments to the 2021 International Fuel Gas Code (NFPA 54), published by the International Code Council, and the 2021 Liquefied Petroleum Gas Code (NFPA 58), published by the National Fire Protection Association, is hereby adopted by reference with the exceptions noted in Chapter 5152 WAC.” NOTE TWO THINGS AS PUBLISHED: NFPA 58 is named at 2021 here, and the WAC chapter is printed “5152” without its hyphen.IFC — “The 2021 Edition of the International Fire Code, including Appendix B, published by the International Code Council is hereby adopted by reference with the additions, deletions, and exceptions co…” and those amendments run to roughly half the chapter.UPC — “The 2021 Edition of the Uniform Plumbing Code, including Appendices A, B, I and M, published by the International Association of Plumbing and Mechanical Officials, is hereby adopted by reference with the additions, deletions and exceptions contained in Chapter 51-56 WAC.” Four appendices, where Lake Stevens takes A, B and I.ENERGY — “The 2021 Edition of the Washington State Energy Code, including commercial and residential provisions and appendices, is hereby adopted by reference with the additions, deletions and exceptions contained in Chapters 51-11C and 51-11R WAC.”NO ELECTRICAL CODE APPEARS in the UPMC 14.05.030 list as read. The absence is bounded: the adoption paragraphs were read in sequence and cover the IBC/IEBC/ISPSC, IRC, IMC/IFGC/NFPA 58, IFC, UPC and energy code. Electrical permitting in Washington is the Department of Labor and Industries' under Chapter 19.28 RCW; this entry does not establish the arrangement for University Place.NOT OPENED FOR THIS ENTRY: UPMC 14.10 (Moving of Buildings), 14.15 (Flood Damage Prevention), 14.20 (RETAINING WALLS — a whole chapter, §§ 14.20.010–.080, unusual to find separated out), UPMC 14.05.090 (Administrative provisions), 14.05.100 (Building code amendments), 14.05.120 (Penalties and enforcement), 14.05.130 (Liability), 14.05.140 (Hearings Examiner) and UPMC § 9.05.040, which the construction-hours section cross-references.

Permit types & fees

Residential Building Permit (New Construction)

Verified

Required for new one- and two-family dwellings in University Place, under the 2021 International Residential Code as adopted at UPMC 14.05.030.

Verified 2026-09-16 · Source

Requirements

  • “The 2021 Edition of the International Residential Code including Appendices F, Q and U … as amended by the Washington State Building Code Council in Chapter 51-51 WAC” (UPMC 14.05.030)
  • Appendix U (Dwelling Unit Fire Sprinkler Systems) is adopted, alongside F (Radon) and Q (Tiny Houses)
  • Sprinklers are required for any Group R-3 “requiring 2,000 gallons per minute of fire flow per Appendix B of the International Fire Code”
  • A fire flow modification is available for NFPA 13D-protected dwellings where a hydrant is within 500 feet (IFC 507.3 as amended)
  • Residential address numerals: 4 inches high under fifty feet from the street, 6 inches over fifty feet, minimum .05 inch stroke

Required documents

  • RequiredBuilding Permit ApplicationFiled under UPMC Chapter 14.05. Administrative provisions come from IBC Chapter 1 as adopted (UPMC 14.05.090, not opened for this entry).
  • RequiredFire Flow CalculationDetermines whether the 2,000 gpm sprinkler trigger applies under IFC Appendix B, which the city adopts expressly.
  • OptionalNFPA 13D Sprinkler PlansWhere sprinklers are required, or where you are seeking the residential fire flow modification, which is conditional on an approved NFPA 13D system and a hydrant within 500 feet.

Fee schedule

Fee typeAmountNotes
Permit feeSet by city council fee resolution
UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. Show full citation

UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. The fire code amendments add a parallel provision at IFC 105.2.15: “The City shall collect fees for permits, plan review and inspection services as prescribed in the City of University Place ‘Fee Schedule.’” Across this Washington set the instrument varies — resolution here and in Edmonds and Lake Stevens, a fee ORDINANCE in Lynnwood, an EXECUTIVE ORDER in Puyallup, a PUBLISHED TABLE in Issaquah, a master fee schedule in Longview, and nothing at all in Wenatchee.

Commercial Building Permit

Verified

Required for commercial construction and alteration in University Place, under the 2021 International Building Code — with locally lowered sprinkler thresholds that catch most buildings.

Verified 2026-09-16 · Source

Requirements

  • “The 2021 Edition of the International Building Code, including Appendix E, and ICC/ANSI A117.1-2017, and the 2021 International Existing Building Code and International Swimming Pool and Spa Code” (UPMC 14.05.030)
  • SPRINKLERS ABOVE 5,000 SQUARE FEET for Groups A-1 to A-4, B, E, F, M and S — far below the model code
  • 2,500 square feet for woodworking generating finely divided combustible waste, and for manufacture or display and sale of upholstered furniture or mattresses
  • 12,000 square feet for Groups B, F-2 and S-2 in Type IA/IB, IIA/IIB, IV/VA or IIB/IIIB construction
  • Commercial address numerals must be at least 12 inches high, with unit or suite numbers at 4 inches
  • Fire lane striping and signage are specified to the inch (IFC 503.3.1 and 503.3.2 as added)

Required documents

  • RequiredBuilding Permit ApplicationFiled under UPMC Chapter 14.05.
  • OptionalAutomatic Sprinkler System PlansRequired for most commercial buildings above 5,000 square feet under the amended IFC Section 903.2 thresholds.
  • OptionalFire Apparatus Access and Lane Marking PlanStriping and signage must meet added IFC Sections 503.3.1 and 503.3.2, which specify paint width, lettering size, sign dimensions, mounting height and spacing.

Fee schedule

Fee typeAmountNotes
Permit feeSet by city council fee resolution
UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. Show full citation

UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. The fire code amendments add a parallel provision at IFC 105.2.15: “The City shall collect fees for permits, plan review and inspection services as prescribed in the City of University Place ‘Fee Schedule.’” Across this Washington set the instrument varies — resolution here and in Edmonds and Lake Stevens, a fee ORDINANCE in Lynnwood, an EXECUTIVE ORDER in Puyallup, a PUBLISHED TABLE in Issaquah, a master fee schedule in Longview, and nothing at all in Wenatchee.

Mechanical Permit

Verified

Mechanical and fuel gas work in University Place, under the 2021 International Mechanical Code together with the 2021 fuel gas codes.

Verified 2026-09-16 · Source

Requirements

  • “The 2021 Edition of the International Mechanical Code, including adoption of and amendments to the 2021 International Fuel Gas Code (NFPA 54) … and the 2021 Liquefied Petroleum Gas Code (NFPA 58) … with the exceptions noted in Chapter 5152 WAC” (UPMC 14.05.030)
  • NFPA 58 IS NAMED AT 2021 HERE, where Lake Stevens and Issaquah both name it at 2020 — three cities, two values, not adjudicated by this project
  • The WAC chapter is printed “5152” without its hyphen, reproduced as published
  • New and existing spray booths and spraying rooms “shall be protected by an approved automatic fire-extinguishing system” (added IFC 903.2.13)

Required documents

  • RequiredMechanical Permit ApplicationFiled under UPMC Chapter 14.05.

Fee schedule

Fee typeAmountNotes
Permit feeSet by city council fee resolution
UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. Show full citation

UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. The fire code amendments add a parallel provision at IFC 105.2.15: “The City shall collect fees for permits, plan review and inspection services as prescribed in the City of University Place ‘Fee Schedule.’” Across this Washington set the instrument varies — resolution here and in Edmonds and Lake Stevens, a fee ORDINANCE in Lynnwood, an EXECUTIVE ORDER in Puyallup, a PUBLISHED TABLE in Issaquah, a master fee schedule in Longview, and nothing at all in Wenatchee.

Plumbing Permit

Verified

Plumbing work in University Place, under the 2021 Uniform Plumbing Code with four appendices adopted.

Verified 2026-09-16 · Source

Requirements

  • “The 2021 Edition of the Uniform Plumbing Code, including Appendices A, B, I and M, published by the International Association of Plumbing and Mechanical Officials, is hereby adopted by reference with the additions, deletions and exceptions contained in Chapter 51-56 WAC.” (UPMC 14.05.030)
  • FOUR appendices — A, B, I and M — where Lake Stevens adopts A, B and I
  • Not the International Plumbing Code: this is a UPC jurisdiction

Required documents

  • RequiredPlumbing Permit ApplicationFiled under UPMC Chapter 14.05.

Fee schedule

Fee typeAmountNotes
Permit feeSet by city council fee resolution
UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. Show full citation

UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. The fire code amendments add a parallel provision at IFC 105.2.15: “The City shall collect fees for permits, plan review and inspection services as prescribed in the City of University Place ‘Fee Schedule.’” Across this Washington set the instrument varies — resolution here and in Edmonds and Lake Stevens, a fee ORDINANCE in Lynnwood, an EXECUTIVE ORDER in Puyallup, a PUBLISHED TABLE in Issaquah, a master fee schedule in Longview, and nothing at all in Wenatchee.

Fire Sprinkler and Alarm Permit

Verified

Required for automatic sprinkler and fire alarm systems in University Place, under the 2021 International Fire Code as heavily amended by UPMC 14.05.110.

Verified 2026-09-16 · Source

Requirements

  • “The 2021 Edition of the International Fire Code, including Appendix B” (UPMC 14.05.030), with amendments running to roughly half of Chapter 14.05
  • Sprinkler thresholds are lowered to 5,000 sq ft across Groups A-1 to A-4, B, E, F, M and S; 2,500 sq ft for two named uses
  • Alarm systems with 30+ actuating devices must be ADDRESSABLE; more than 75 smoke detectors or 200 total devices must be ANALOG INTELLIGENT
  • Existing systems are exempt unless a remodel or expansion exceeds 30 percent; above 50 percent, compliance is required “within 18 months of permit application”
  • A fire alarm panel must report a signal's location “written in English, not code” (added IFC 907.1.4)
  • Where a new building has a suppression system, an occupant notification alarm system must also be installed — including tenant improvements in sprinklered buildings (IFC 907.5 as amended)

Required documents

  • OptionalSprinkler System PlansTo the amended IFC Section 903 thresholds. Note added Section 903.2.13: new and existing spray booths and spraying rooms must be protected by an approved automatic fire-extinguishing system.
  • OptionalFire Alarm System PlansMust meet the device-count technology requirements in added IFC Section 907.1.5 and the plain-English annunciation requirement in 907.1.4.
  • OptionalFire Apparatus Access PlanAdded IFC 503.2.1.1 allows the city to require more than one emergency vehicle access for commercial developments where a single street access “may be impaired by vehicle congestion, condition of terrain, climatic conditions or other factors”.

Fee schedule

Fee typeAmountNotes
Permit feeSet by city council fee resolution
UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. Show full citation

UPMC 14.05.060: “All fee schedules shall be listed in a fee resolution adopted by the City Council of the City of University Place.” No dollar amount appears in the code. The fire code amendments add a parallel provision at IFC 105.2.15: “The City shall collect fees for permits, plan review and inspection services as prescribed in the City of University Place ‘Fee Schedule.’” Across this Washington set the instrument varies — resolution here and in Edmonds and Lake Stevens, a fee ORDINANCE in Lynnwood, an EXECUTIVE ORDER in Puyallup, a PUBLISHED TABLE in Issaquah, a master fee schedule in Longview, and nothing at all in Wenatchee.

False alarm responseChargeable after 2 in any 90 days
Added IFC Section 901.11: “In the event of more than two false alarms in any 90-day period the Chief may charge a fee for fire department response as specified in the City of University Place ‘Fee… Show full citation

Added IFC Section 901.11: “In the event of more than two false alarms in any 90-day period the Chief may charge a fee for fire department response as specified in the City of University Place ‘Fee Schedule.’” The panel must carry “an approved sign indicating such fees will be imposed.” No amount is published in the code.

Fire watchFacility pays per the fee scheduleUPMC 14.05.110 amends IFC 901.7.0.1 so the Fire Code Official determines when a fire watch is required and “the person responsible for the facility shall pay a fee per the fee schedule for associated costs”, with a further fee where more than one person is required.

Electrical Permit

Verified

University Place adopts no electrical code in its building and construction chapter.

Verified 2026-09-16 · Source

Requirements

  • NO ELECTRICAL CODE APPEARS in the UPMC 14.05.030 adoption list as read — the paragraphs cover the IBC/IEBC/ISPSC, IRC, IMC/IFGC/NFPA 58, IFC, UPC and Washington State Energy Code
  • The absence is bounded by what was read; UPMC 14.05.090 and 14.05.100 were not opened
  • Electrical permitting in Washington is generally the Department of Labor and Industries' under Chapter 19.28 RCW; THIS ENTRY DOES NOT ESTABLISH the arrangement for University Place
  • CONFIRM WITH THE CITY OR L&I before filing

Required documents

  • RequiredElectrical Permit ApplicationNOT ESTABLISHED. Ask the city and the Washington State Department of Labor and Industries which issues for your project.

Fee schedule

Fee typeAmountNotes
Electrical permitNot established; ask city or L&INo electrical code and no electrical fee appear in the sections of UPMC Chapter 14.05 read for this entry. The absence is bounded rather than asserted as complete: UPMC 14.05.090 (Administrative provisions) and 14.05.100 (Building code amendments) were not opened.

Sources & verification

Verified against official sources. Last reviewed 2026-09-16.

Department & other records

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the University Place building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

View current record →All versions →

Permalink: /washington/pierce-county/university-place/as-of/2026-09-16/

Snapshot date: 2026-09-16

Commit: 0f10392

Reproducible from PermitBase’s version-controlled dataset, commit 0f10392.