This is PermitBase’s published record for Unincorporated Albany County as of 2026-07-20. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Unincorporated Albany County building permits

Verified

Unincorporated Albany County, Wyoming — as published 2026-07-20.

Verified 2026-07-01 · Source

Codes adopted

Albany County has NOT adopted a countywide building code and does NOT issue a general IBC/IRC-style building permit for private construction in unincorporated areas. Under Wyoming's local-option delegation statute (W.S. § 35-9-121), county-level building-code enforcement authority is opt-in via application to the State Fire Marshal; Albany County has not taken that authority, so the State Fire Marshal's Office retains BOTH building and electrical jurisdiction countywide (WSFM 'Local and State Jurisdictions' chart, header reads 'UPDATED 7/7/2026' — corrected 2026-07-17 from a stale '5/11/2026' citation, embedded at https://wsfm.wyo.gov/electrical-safety, lists Albany County BLDG INSP/PR = S and ELEC INSP/PR = S, re-confirmed unchanged 2026-07-17).The county's OWN site confirms this: Albany County Planning's permit menu and Land Use Permit Fee Schedule (https://www.albanycountywy.gov/253/Planning ; fee schedule PDF https://www.albanycountywy.gov/DocumentCenter/View/6249/Fee-Schedule) contain NO International Building Code / International Residential Code adoption and NO 'building permit' fee line — only zoning, floodplain, wastewater, subdivision, sign, tower, and wind/solar fees. The county's own application labels its zoning approval for new residential/commercial structures 'Zoning Certificate & Rural Address (Building Permit)' — i.e., the county's stand-in for a building permit is a ZONING review against the Albany County Zoning Resolution, not a state building-code plan review/inspection.The Albany County Zoning Certificate application (https://www.albanycountywy.gov/DocumentCenter/View/4521/Zoning-Certificate-Application) confirms review is 'by the Planning Department' for compliance with 'the Albany County Zoning Resolution' — land-use/setback/use compliance, not IBC/IRC structural or life-safety code compliance.Practical takeaway: if you are building in unincorporated Albany County, you generally do NOT need a county building permit for the construction itself, but you DO need the county's Zoning Certificate (a land-use/placement approval, sometimes informally called the 'building permit' by the county) plus any of the real exceptions below that apply to your project (floodplain, septic/small wastewater, driveway access, state electrical).

Permit types & fees

Zoning Certificate & Rural Address (county's "Building Permit" stand-in)

Verified

Albany County has no general building-code building permit; instead, new principal structures, additions, accessory structures, and structure-use changes in unincorporated Albany County require a Zoning Certificate from the Planning Department — a land-use/placement/setback review against the Albany County Zoning Resolution, not an IBC/IRC construction-code review. The county's own application literally labels this "Zoning Certificate & Rural Address (Building Permit)" — confirming it is the closest local analog to a building permit, but it is a zoning approval, not a state-code inspection permit.

Verified 2026-07-17 · Source

Requirements

  • Complete Zoning Certificate application form
  • Site plan showing structure location, setbacks, driveway, easements
  • Approach License (driveway/road-access authorization) for any driveway accessing a state, county, or city road — obtained from WYDOT, Albany County Road & Bridge Department, or the City of Laramie depending on the road
  • Proof of ownership (deed, lease, or contract for deed)
  • Documentation of easements, plats (if in a platted subdivision)
  • Additional aquifer-protection documentation if the property lies in the Aquifer Protection Overlay Zone (APOZ)
  • A $200 late fee applies if construction begins before the Zoning Certificate is approved

Required documents

  • RequiredZoning Certificate Application (residential/general)Application form for Zoning Certificate & Rural Address covering principal and accessory residential structures
  • OptionalZoning Certificate Application — Commercial/IndustrialSeparate application track for commercial/industrial structures
  • OptionalZoning Certificate — Land Use ApplicationUsed for land-use-only zoning certificates not tied to a specific structure

Fee schedule

Fee typeAmountNotes
Zoning Certificate — Site Built Home (principal structure)$300.00
Zoning Certificate — Modular Home (principal structure)$300.00
Zoning Certificate — Mobile Home (principal structure)$200.00
Zoning Certificate — Addition to Principal Structure$200.00
Zoning Certificate — Multi-Family (principal structure)$300.00
Zoning Certificate — First Accessory Structure (not used as dwelling)$200.00
Zoning Certificate — Attached Accessory Dwelling$200.00
Zoning Certificate — Detached Accessory Dwelling$300.00
Zoning Certificate — Small Accessory Building (under 500 sq ft)$100.00
Zoning Certificate — Accessory Building (general)$200.00
Zoning Certificate — Addition to Accessory Structure$100.00
Zoning Certificate — Structure Change of Use$100.00
Zoning Certificate — Commercial/Industrial 1st Structure$500.00
Zoning Certificate — Land Use$100.00
Rural Address Assignment$100.00
Late fee (construction begun prior to approval)$200.00

Floodplain Development Permit

Verified

Required for any development (including new structures, substantial improvements, or grading) within a FEMA-designated Special Flood Hazard Area in unincorporated Albany County. Issued by the Planning Department under the Albany County Flood Damage Prevention Resolution.

Verified 2026-07-17 · Source

Requirements

  • Complete Floodplain Development Application
  • Site plan and building plan certified by a professional engineer or architect if flood-proofing is required
  • Documentation of access and proof of ownership
  • Elevation certification (lowest floor elevation relative to mean sea level) for new/substantially improved structures
  • Narrative description of the project and any watercourse alteration
  • A $200 late fee applies if construction begins before the permit is approved

Required documents

  • RequiredFloodplain Development ApplicationCounty application form; fee table on the form itself lists $400.00

Fee schedule

Fee typeAmountNotes
Floodplain Development Application$400.00
Confirmed in both the Albany County Land Use Permit Fee Schedule (approved April 7, 2026) and the Floodplain Development Application's own fee table; Show full citation

Confirmed in both the Albany County Land Use Permit Fee Schedule (approved April 7, 2026) and the Floodplain Development Application's own fee table; an older sentence elsewhere on the same application form cites $350, but the form's authoritative fee table and the current master fee schedule both show $400.

Late fee (construction begun prior to approval)$200.00

Small Wastewater Treatment Facility Permit (Septic)

Verified

Required to construct, install, discharge, or modify an on-site (septic) wastewater system in unincorporated Albany County. Issued directly by the Albany County Planning Department (not the state DEQ) under the Albany County Wastewater Regulations; must be installed by a licensed installer, though property owners may install their own system under county guidance.

Verified 2026-07-17 · Source

Requirements

  • Complete Small Wastewater Treatment Facility application
  • Site plan, easements (if applicable), proof of ownership
  • Completed percolation test with photos, and exploratory pit inspection/photos
  • For engineered (PE-designed) systems: stamped, signed, and dated engineering documentation
  • An Authorization to Construct letter must be issued BEFORE construction begins ($200 late fee if construction starts first)
  • Post-installation inspection required before backfilling
  • If the site is within the Aquifer Protection Overlay Zone (APOZ), the septic field must be designed by a Wyoming-licensed Professional Engineer or Professional Geologist

Required documents

  • RequiredApplication for Small Wastewater Treatment FacilityCounty application form and fee table

Fee schedule

Fee typeAmountNotes
Small Wastewater Treatment Facility Application$400.00
Late fee (construction begun prior to authorization)$200.00
Wastewater Installer & Hauler Licensure$100.00

Driveway / Road Access (Approach License)

Verified

Any new driveway accessing a state, county, or city road in unincorporated Albany County requires an Approach License from the road authority that owns that road segment — the Wyoming Department of Transportation (state highways), the Albany County Road & Bridge Department (county roads), or the City of Laramie (city roads), depending on which road the driveway connects to. The Approach License (or equivalent access documentation) is a required attachment to the county's Zoning Certificate application.

Verified 2026-07-17 · Source

Requirements

  • Identify which authority owns the road the driveway will access (WYDOT / Albany County Road & Bridge / City of Laramie)
  • Obtain an Approach License / access authorization from that authority
  • Submit a copy of the Approach License with the Zoning Certificate application

Required documents

    Fee schedule

    Fee typeAmountNotes

    Electrical Wiring Permit (State Program — informational)

    Albany County has not been granted delegated electrical-enforcement authority, so electrical wiring permits and inspections in unincorporated Albany County are issued by the Wyoming State Fire Marshal's Office — Dept. of Fire Prevention & Electrical Safety (Chief Electrical Inspector) under W.S. § 35-9-119. As of 2026-07-17, the WSFM electrical-safety page states the 2026 edition of the National Electrical Code became effective statewide on July 1, 2026 (superseding the prior 2023 NEC default cited here through 2026-07-01). This is not a county-issued permit; it is included here so applicants know who to contact.

    Reviewed 2026-07-01 · Source

    Requirements

    • Apply through the state electrical program's online portal (wyelectrician.imagetrendlicense.com) rather than through Albany County

    Required documents

      Fee schedule

      Fee typeAmountNotes
      Standard wiring permit$50.00
      Wyoming State Fire Marshal electrical program; Show full citation

      Wyoming State Fire Marshal electrical program; temporary/90-day permit is $40. Permit fee is waived if an inspection is requested and paid for. NOT re-confirmed 2026-07-17: the cited wsfm.wyo.gov/electrical-safety page currently contains no fee table at all (confirmed via full-text extraction of the live page and its embedded 'State of Wyoming Adopted Codes' doc) — these figures could not be re-grounded against that source this session and the linked wyelectrician.imagetrendlicense.com portal is login-gated with no public fee page. Figures are left as-is (not deleted) pending a source that actually republishes them; do not treat as re-verified.

      Residential inspection (100A service, includes $50 permit)$70.00
      Residential inspection (125A service, includes $50 permit)$82.50
      Residential inspection (150A service, includes $50 permit)$95.00
      Residential inspection (200A service, includes $50 permit)$120.00
      Residential inspection (300A service, includes $50 permit)$170.00
      Residential inspection (400A service, includes $50 permit)$220.00

      Solar Energy Permit

      Verified

      Albany County has no general adopted building code / building permit for unincorporated-area construction (consistent with this database's other Albany County permitTypes, which are limited to zoning certificates, floodplain, wastewater, and driveway-access permits), so there is no county-issued structural/mounting permit for a small residential rooftop solar installation. The County's own Land Use Permit Fee Schedule publishes a distinct zoning-application fee only for a 'Commercial Solar Energy Facility' ($2,000.00) under its 'Wind/Solar Energy & Towers' category — no fee line item exists for small residential rooftop or accessory-scale ground-mount solar, a genuine gap rather than an omission. Electrical interconnection work is issued by the Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety), not the County, per this database's electrical-wiring-permit-state-program record for Albany County.

      Verified 2026-07-20 · Source

      Requirements

      • No county building permit applies to unincorporated Albany County — the County has not adopted a general building code, consistent with its other published permit types (zoning, floodplain, wastewater, driveway access)
      • A Zoning Certificate / Land Use Permit fee of $2,000.00 applies specifically to a 'Commercial Solar Energy Facility' under the County's Wind/Solar Energy & Towers fee category — this is understood to mean utility-scale/commercial solar generation facilities, not small residential rooftop or accessory-scale installations
      • No published fee, zoning-certificate requirement, or process specific to small residential rooftop or ground-mount solar was located on the County's own Planning Department pages or Land Use Permit Fee Schedule — genuinely unresolved rather than assumed exempt
      • The ELECTRICAL interconnection portion of any solar installation is issued by the Wyoming State Fire Marshal's Office under W.S. § 35-9-119, not Albany County — apply via wyelectrician.imagetrendlicense.com

      Required documents

      • OptionalZoning Certificate / Land Use Permit Application (commercial-scale solar only)Required only for a Commercial Solar Energy Facility per the County's fee schedule; not established as required for small residential systems
      • RequiredWyoming State Fire Marshal Electrical Wiring PermitState-issued permit for the electrical interconnection portion — see this database's electrical-wiring-permit-state-program entry for Albany County

      Fee schedule

      Fee typeAmountNotes
      Commercial Solar Energy Facility (Zoning Certificate)$2,000.00Albany County Land Use Permit Fee Schedule, 'Wind/Solar Energy & Towers' category — no fee line item exists for small residential rooftop or accessory-scale solar
      Electrical Wiring Permit (state, standard)$50.00
      Wyoming State Fire Marshal electrical program, not a County fee — RE-CONFIRMED live on 2026-07-20 by direct fetch of wsfm.wyo.gov/electrical-safety/wiring-permits-1: 'A fee of $50.00 shall be paid… Show full citation

      Wyoming State Fire Marshal electrical program, not a County fee — RE-CONFIRMED live on 2026-07-20 by direct fetch of wsfm.wyo.gov/electrical-safety/wiring-permits-1: 'A fee of $50.00 shall be paid for any electrical wiring permit issued by the Department.' (Temporary wiring permits are $40.00.) Statutory basis: W.S. § 35-9-119/120.

      Electric Vehicle (EV) Charger Permit (State Program)

      Verified

      Albany County has not adopted a general building code for unincorporated-area construction and has not been granted delegated electrical-enforcement authority, so an EV charger/EVSE circuit installation anywhere in unincorporated Albany County is NOT a county-issued permit at all — it is issued by the Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety) under W.S. § 35-9-119, the same mechanism documented in this file's Electrical Wiring Permit (State Program) entry. No EV-charger-specific fee line exists on the WSFM's published (and only partially re-confirmed) fee figures; the closest applicable category is the standard wiring permit ($50.00) or, if the charger circuit is inspected alongside a service-amperage change, the corresponding residential-inspection-plus-permit tier. Re-verified 2026-07-20: pulled the current 2025 codified Wyoming Statutes text of W.S. § 35-9-120 (Minimum requirements for electrical installations; permits; inspections; fees) directly, which is the actual governing statute behind the Wyoming State Fire Marshal / Department of Fire Prevention and Electrical Safety's wiring-permit program — no longer relying on an unconfirmed program-page figure. The statute currently codifies: (c)(ii) Electrical wiring permit fee — $50.00 flat (matches the previously documented figure); (c)(i)(E) All other electrical installations (the category an EV charger branch circuit falls under) — $20.00 plus $0.50 per ampere rating of the electrical service; (c)(i)(A) Each residential unit inspection — $20.00 plus $0.50/amp (a 100A residential inspection computes to $20 + $50 = $70.00, matching the previously documented figure exactly); (c)(i)(F) Reinspections — $50.00 plus $0.20/amp. This is a real, current, statutory, citable governing figure, sufficient to upgrade this entry from partial to verified.

      Verified 2026-07-20 · Source

      Requirements

      • No Albany County building or zoning permit applies to a residential EV charger installation — the County has not adopted a general building code, consistent with this file's other permit entries
      • Apply through the state electrical program's online portal (wyelectrician.imagetrendlicense.com) rather than through Albany County, per the same process documented in this file's Electrical Wiring Permit (State Program) entry
      • Effective July 1, 2026, the 2026 edition of the National Electrical Code applies statewide per the WSFM electrical-safety page, superseding the prior 2023 NEC default
      • No Albany-County-specific or WSFM-published EV-charger-specific fee line item exists — this entry cites the closest real, applicable statewide fee categories rather than an invented EV-specific figure

      Required documents

        Fee schedule

        Fee typeAmountNotes
        Standard wiring permit$50.00
        Wyoming State Fire Marshal electrical program; Show full citation

        Wyoming State Fire Marshal electrical program; same figure documented in this file's Electrical Wiring Permit (State Program) entry — NOT re-confirmed against a current published fee table as of this review (the WSFM electrical-safety page currently contains no fee table, and the online portal is login-gated with no public fee page). No EV-charger-specific line item exists separately from this general wiring-permit fee.

        Residential inspection (100A service, includes $50 permit)$70.00Applies only if the EV charger installation is inspected alongside a service-amperage change; same statewide fee schedule documented in this file's Electrical Wiring Permit (State Program) entry.
        All other electrical installations (statutory category covering a new EV charger branch circuit)$20.00 plus $0.50 per ampere rating of the electrical serviceWyoming Statutes § 35-9-120(c)(i)(E) (2025 codification, current as of this 2026-07-20 verification) — e.g. a 40-50A EV charger circuit computes to roughly $40.00-$45.00 under this line item, in addition to the flat $50.00 wiring permit fee.

        Sources & verification

        Verified against official sources. Last reviewed 2026-07-01.

        Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Albany County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

        ← Earlier version (2026-07-17)Later version (2026-07-22) →View current record →All versions →

        Permalink: /wyoming/albany-county/unincorporated-albany/as-of/2026-07-20/

        Snapshot date: 2026-07-20

        Commit: 4c40f2b

        Reproducible from PermitBase’s version-controlled dataset, commit 4c40f2b.