Sheridan building permits
VerifiedSheridan, Wyoming — as published 2026-07-13.
Verified 2026-07-13 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for new single-family and two-family dwelling construction in the City of Sheridan. Processed as a "Detailed Building Permit" requiring plan review under the 2024 IRC as locally amended by Ordinance No. 2290. Building costs over $3,000 or new buildings over 200 sq ft require a permit.
Verified 2026-07-13 · Source
Requirements
- Required for any new residential building with construction cost over $3,000 or floor area over 200 sq ft
- Detailed Building Permit track — requires plan review by Building Division staff
- Plans must comply with the 2024 IRC as amended by Ordinance No. 2290 (local snow/wind/seismic/frost criteria)
- Footings must extend below the 42-inch local frost line
- Design must account for 30 psf ground snow load, 115 mph basic wind speed, Seismic Design Category B
- Ice barrier underlayment required per local IRC amendment
- Contractor must hold a current City of Sheridan contractor license
- Applications submitted through the online Permit & Licensing Portal (OpenGov)
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
- RequiredSite PlanProperty lines, setbacks, existing/proposed structures, utilities
- RequiredConstruction DrawingsFull plan set: foundation, framing, structural, and MEP as applicable, compliant with the City's amended 2024 IRC
- RequiredContractor License VerificationContractor performing the work must hold a current City of Sheridan contractor license (annual fee $200)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential New/Add/Alter — up to $100,000 valuation | Valuation x 0.03 x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12, "Building Permit Fee Calculations - Residential" — figure confirmed unchanged from the prior July 2023 Master Fee Schedule (Resolution #34-23, now offline) as of re-verification 2026-07-13; formula originally set by Resolution #18-17 (June 19, 2017, effective July 1, 2017) |
| Residential New/Add/Alter — over $100,000 valuation | (($100,000 x 0.03) + (remaining amount x 0.017)) x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12 — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Valuation basis | Per the ICC Building Valuation Data table on file with the Building Division | City of Sheridan Resolution #18-17, Section 1(c) |
| Repeat/stock plan submittals | Full permit fee for first permit; 30% reduction on each subsequent permit using the same stock plans (valid 2 years) | City of Sheridan Resolution #18-17, "Repeat Building Plans" section |
| Investigation fee (work started without a permit) | Equal to the permit fee otherwise required, in addition to the permit fee | City of Sheridan Resolution #18-17, Section 2 / FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Compliance Fees — Investigative Fees" (worded as "Relevant Permit Fee + Matching Investigation Fee, doubles cost") — figure confirmed unchanged as of re-verification 2026-07-13 |
| Re-Inspection (each, up to 3 times) | $58.75 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Building Inspection & Code Enforcement" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Residential Addition / Remodel Permit
VerifiedRequired for additions, remodels, and structural alterations to existing one- and two-family dwellings in Sheridan, including decks. Processed as a "Detailed Building Permit" (plan review) under the 2024 IRC as amended by Ordinance No. 2290.
Verified 2026-07-13 · Source
Requirements
- Required for building costs over $3,000 or additions over 200 sq ft
- Plan review required for any project involving structural work (remodels, additions, decks)
- Contractor must hold a current City of Sheridan contractor license
- Structural connections to the existing structure must be shown on plans
- Applications submitted through the online Permit & Licensing Portal (OpenGov)
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
- RequiredSite PlanExisting structures, proposed addition footprint, setbacks
- RequiredConstruction DrawingsPlans showing scope, framing, and connection to existing structure
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Add/Alter — up to $100,000 valuation | Valuation x 0.03 x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12 — same formula applies to new construction, additions, and alterations; figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Residential Add/Alter — over $100,000 valuation | (($100,000 x 0.03) + (remaining amount x 0.017)) x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12 — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Residential Garage (garage only) | Valuation x 0.02 x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12, "Residential Garage" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Deck Permit
VerifiedDecks are explicitly named by the City of Sheridan's Building Division as a project type requiring a Detailed Building Permit (plan review) under the 2024 IRC as amended by Ordinance No. 2290.
Verified 2026-07-13 · Source
Requirements
- Plan review required (Detailed Building Permit track)
- Structural connection to primary dwelling and footing depth (below 42-inch frost line) must be shown on plans
- Contractor must hold a current City of Sheridan contractor license (or owner-builder per City policy — confirm with Building Division)
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
- RequiredDeck PlanFraming plan, footing/pier locations and depth, ledger attachment details
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Deck — valuation-based | Valuation x 0.02 x 0.8 | FEE CHANGE identified 2026-07-13: City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12, now lists a dedicated "Residential Deck Permit" line at (Valuation x 0.02) x (0.8) — the same lower rate as Residential Garage. This SUPERSEDES the prior citation to the July 2023 Master Fee Schedule (Resolution #34-23, now a dead link), which had no separate deck fee line and billed decks under the general Residential New/Add/Alter formula (Valuation x 0.03 x 0.8). Confirmed via direct visual review of the FY27 schedule PDF, not inferred. |
Electrical Permit
VerifiedThe City of Sheridan is the electrical Authority Having Jurisdiction (AHJ) inside city limits — Ordinance No. 2290 adopts the 2023 NEC as a City technical code enforced by the City of Sheridan Building Department, and the Wyoming Department of Fire Prevention & Electrical Safety's own "Local and State Jurisdictions" chart lists Sheridan (the municipality) as holding local ("L") electrical inspection AND electrical plan review authority under W.S. § 35-9-121, rather than the State ("S"). The State Chief Electrical Inspector's office administers electrical permitting only where no local authority has been delegated (shown as "S" on the same chart) — that does not apply within the City of Sheridan.
Verified 2026-07-13 · Source
Requirements
- Sheridan's Ordinance No. 2290 adopts the 2023 NEC as a City technical code, amends NEC Section 230.70(A)(1) (exterior service disconnect requirement), and provides that wherever the Fire Code references the NEC it means "the latest adopted electrical code of the City of Sheridan" — the City's own Building Department (created under the same ordinance, Section 103.1 as applied to each adopted technical code) administers and enforces it
- The Wyoming Dept. of Fire Prevention & Electrical Safety's "Local and State Jurisdictions" chart (updated 5/11/2026) lists the City of Sheridan with "L" (municipality/county enforces) for both the ELEC INSP and ELEC PR columns — confirming the City, not the State, is the electrical AHJ inside city limits
- Electrical service upgrades in existing buildings are a City Simple Permit at a flat fee
- New electrical work bundled with new construction, additions, remodels, or other Detailed Building Permit work is covered under the general Residential/Commercial New/Add/Alter valuation-based permit fee — the City does not publish a separate itemized electrical rough-in/service-size fee table beyond the flat Simple Permit fees
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Service Upgrade (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Electrical Service Upgrades" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13; the only standalone electrical-specific fee line the City publishes; electrical work that is part of a larger Detailed Building Permit project is covered by that permit's valuation-based fee |
Plumbing Permit
VerifiedRequired for plumbing installations, alterations, and repairs in the City of Sheridan. Governed by the 2024 International Plumbing Code (IPC) as amended by Ordinance No. 2290.
Verified 2026-07-13 · Source
Requirements
- Building sewers connecting to private disposal (septic) systems must be not less than 30 inches below grade at the point of septic tank connection; all building sewers not less than 30 inches below grade (IPC Section 305.4.1, local amendment)
- Drainage and vent water test (IPC Section 312.2, local amendment): air tests may be conducted at 5 psi for 15 minutes with un-glued end caps at open-ended pipe
- Water heater and furnace replacements, gas piping in existing buildings are City Simple Permits (no plan review, online only)
- New fixture installs, re-piping, and other plan-review-triggering work processed as a Detailed Building Permit
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com; Simple Permits for water heater/furnace replacement are online-only
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Water Heater Replacement (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Water Heater Replacement - Plumbing" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Gas Piping in Existing Buildings (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Gas Permit - New/Replace" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Water or Sewer Service Replacement (Simple Permit) | $50.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Interceptor | $250.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Mechanical / HVAC Permit
VerifiedRequired for heating, cooling, and fuel-gas equipment installations in the City of Sheridan. Governed by the 2024 International Mechanical Code (IMC) and 2024 International Fuel Gas Code (IFGC), both amended by Ordinance No. 2290.
Verified 2026-07-13 · Source
Requirements
- Furnace replacement is a City Simple Permit (no plan review, online only)
- IMC Section 1101.9 (locking caps on A/C condensers) is omitted by local amendment — not required in Sheridan
- IFGC Section 406.4.1 amended: pressure tests on threaded gas piping shall be 10 lbs for 15 minutes
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com; furnace replacement is a Simple Permit (online only)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Furnace Replacement (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Furnace - New/Replace" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Gas Piping in Existing Buildings (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Gas Permit - New/Replace" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Roofing Permit (Re-Roof)
VerifiedRequired for roof replacement (re-roofing) in the City of Sheridan. Re-roofing is classified as a City Simple Permit — no plan review, online-only application.
Verified 2026-07-13 · Source
Requirements
- Re-roofing is a Simple Permit — does not require plan review
- Applied for online only via the Permit & Licensing Portal (OpenGov)
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Simple Permit — online application only, no plans required
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Re-Roofs (Simple Permit) | $150.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Re-Roofing" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Solar PV Permit
VerifiedRequired for installation of solar photovoltaic panels in the City of Sheridan. Processed as a flat-fee Simple Permit per the City's Master Fee Schedule.
Verified 2026-07-13 · Source
Requirements
- Solar panel installation is listed as a City Simple Permit with a flat fee
- Electrical connections must comply with the City's amended 2023 NEC
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Solar Panel (Simple Permit) | $250.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Solar Panel" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
EV Charger / EVSE Permit (Electrical Simple Permit)
VerifiedThe City of Sheridan is the electrical Authority Having Jurisdiction (AHJ) inside city limits (Ordinance No. 2290, 2023 NEC as amended, enforced by the City Building Department). The City's Master Fee Schedule has no dedicated EV-charger/EVSE line item — unlike Solar Panel, which is its own named flat-fee Simple Permit ($250) — so an EV charging station (Level 2 or DC fast charger) installation is most consistent with the City's 'Electrical Service Upgrade' Simple Permit category, the only standalone electrical-specific flat-fee line the City publishes outside of work bundled into a larger Detailed Building Permit.
Verified 2026-07-20 · Source
Requirements
- Electrical work must comply with the City's amended 2023 NEC (Ordinance No. 2290)
- Apply through the OpenGov Permit & Licensing Portal (sheridanwy.portal.opengov.com)
- A standalone EV charger circuit/service addition in an existing building is most consistent with the City's 'Electrical Service Upgrade' Simple Permit category (no dedicated EV-charger line item was found on the FY27 Master Fee Schedule); confirm the correct fee category with the Building Department before applying
- If the EV charger is installed as part of new construction or a larger addition/remodel, it is instead covered under that project's Detailed Building Permit valuation-based fee, not a standalone Simple Permit
- A separate service-upgrade coordination with Rocky Mountain Power (the local electric utility) may be required for higher-capacity commercial EV charger installations, independent of the City permit
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Service Upgrade (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), 'Simple Permits — Electrical Service Upgrades' — the closest documented fee category for a standalone EV charger circuit/service addition, since no dedicated EV-charger fee line was found on the schedule (unlike Solar Panel, which has its own named $250 Simple Permit line). Confirm with the Building Department whether an EV charger installation is classified under this line or requires full Detailed Building Permit valuation review. |
Accessory Dwelling Unit (ADU) Permit
VerifiedThe City of Sheridan's zoning code (City Code Appendix A — Zoning) contains no ADU-specific category, standard, or process: its Definitions chapter (Ch. 2) defines only "accessory building" and "accessory use" (general incidental structures/uses, not dwelling units), and each residential district chapter — R-1 (one-family only), R-2 (two-family/multi-family), R-3, and R-4 — permits only "accessory buildings and uses customarily incidental to" the district's principal dwelling use, with no second/independent dwelling unit provision. An ADU is therefore reviewed as a standard Detailed (plan-review) Building Permit under the 2024 IRC/IBC as amended by Ordinance No. 2290, using the general Residential New/Add/Alter valuation-based fee, and must otherwise conform to the underlying district's permitted-use table (e.g., only allowed as a second unit where the district itself permits two-family/multi-family dwellings, such as R-2).
Verified 2026-07-13 · Source
Requirements
- Confirmed absence: Sheridan City Code Appendix A (Zoning) Chapter 2 (Definitions) defines only "accessory building" and "accessory use" — general incidental structures, not dwelling units; no "accessory dwelling unit," "ADU," "carriage house," or "secondary dwelling" term is defined anywhere in the zoning code
- R-1 Residence District (Ch. 5) permits only one-family dwellings plus incidental accessory buildings/uses — no second dwelling unit permitted
- R-2, R-3, and R-4 Residence Districts (Ch. 6-8) permit two-family/multi-family dwellings as principal uses (not as an accessory unit to a single-family home) plus incidental accessory buildings/uses — none of the four residential district chapters contain an ADU-specific process
- Absent a dedicated ADU category, a legally accessory second dwelling would need to fit within the applicable district's permitted-use table (e.g., a duplex/two-family use in R-2+) and would be processed as a Detailed Building Permit (plan review) under the City's amended 2024 IRC/IBC
- Contractor must hold a current City of Sheridan contractor license
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential New/Add/Alter — up to $100,000 valuation (general formula, likely applicable) | Valuation x 0.03 x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12 — no ADU-specific fee line exists; this is the general residential construction fee formula that would apply absent a dedicated ADU fee; figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Demolition Permit
VerifiedRequired for demolition of structures in the City of Sheridan. Processed as a City Simple Permit at a flat fee.
Verified 2026-07-13 · Source
Requirements
- Demolition is listed as a City Simple Permit (no plan review, online only)
- Utility disconnects should be arranged prior to demolition (standard practice; not separately detailed in Sheridan's published fee/ordinance documents)
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition (Simple Permit) | $40.00 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Demolition" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Commercial Tenant Improvement Permit
VerifiedRequired for interior remodels, additions, and tenant improvements in commercial buildings in the City of Sheridan. Processed as a Detailed Building Permit (plan review) under the 2024 IBC as amended by Ordinance No. 2290.
Verified 2026-07-13 · Source
Requirements
- Plan review required for structural work, remodels, and additions in commercial occupancies
- IBC Section 804.2.2 local amendment: work areas with shared exits/corridors serving occupant load >30 in Groups A, E, F-1, H, I, M, R-1, R-2, R-4, S-1, S-2 require automatic sprinkler protection under specified conditions
- IFC Section 506.1 local amendment: Knox boxes required on all commercial occupancies
- Contractor must hold a current City of Sheridan contractor license
- As of this verification, the City states it lacks a certified Fire Plans Examiner — fire sprinkler/alarm plan review and inspection must be routed through the State
Required documents
- RequiredBuilding Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com
- RequiredFull Construction Drawing SetArchitectural, structural, mechanical, plumbing, electrical plans as applicable
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Commercial New/Add/Alter — up to $100,000 valuation | Valuation x 0.036 x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12, "Commercial New/Add/Alter" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
| Commercial New/Add/Alter — over $100,000 valuation | (($100,000 x 0.036) + (remaining amount x 0.0095)) x 0.8 | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12 — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13 |
Sign Permit
VerifiedRequired for most signs erected within the incorporated City of Sheridan, per City Code Chapter 3, Article 3-II (Signs and Billboards), Section 3-10. The Building Official administers and enforces the sign regulations; the required sign permit fee is valuation-based, using the same rate structure as a residential deck or garage permit.
Verified 2026-07-22 · Source
Requirements
- All signs erected within the incorporated City of Sheridan require a permit issued by the Building Official, except where exempted under City Code Section 3-11 (City Code Section 3-10(b))
- Application must include a completed application, a scaled site/installation plan showing the exact sign location on the property or building, and a scale drawing of the sign showing its relationship to buildings, structures, and roads (City Code Section 3-10(c)(1)(A)-(C))
- Ground signs require a footing detail with rebar requirements; all freestanding signs must be engineered to resist wind gusts for Exposure C as defined in the currently adopted International Building Code (City Code Section 3-10(c)(1)(C))
- Electrical signs and outline lighting must comply with the currently adopted National Electrical Code; electrical components must bear the label of an approved testing agency, and plans must show the disconnect location/type, grounding method, branch circuit rating, required nameplate information, and enclosure/clearance requirements (City Code Section 3-10(c)(1)(D))
- The required sign permit fee must be paid prior to issuance of the permit (City Code Section 3-10(c)(2))
- Electronic Message Centers (EMC) require additional City Council approval, following Planning Commission recommendation and a public hearing, when located in the Downtown Business District, R-O/R-1/R-2/R-3/R-4 Residence Districts, NC-1 Neighborhood Commercial District, or residential/mixed-use areas of PUDs and the GD Gateway District (City Code Section 3-11.A)
- A contractor performing sign installation typically holds a City of Sheridan Sign/Solar Contractor license ($200/year per the FY27 Master Fee Schedule)
- Certain signs are exempt from permitting under City Code Section 3-11, including: construction signs (≤ 35 sq ft, temporary), off-site directional signs to public places (≤ 5 sq ft), historic markers (one plaque per street frontage), on-site informational signs (≤ 5 sq ft), interior signs, unpermitted temporary signs on residential property (≤ 8 sq ft, removed within 90 days), real estate signs (≤ 8 sq ft per property, or ≤ 25 sq ft/6 ft height for a common subdivision sign), sports-venue sponsor signage, street numbers, and traffic control signs
Required documents
- RequiredSign Permit ApplicationCompleted application submitted to the Building Division (City Code Section 3-10(c)(1)(A))
- RequiredScaled Site/Installation PlanShows the exact location the sign will be installed on the property or building (City Code Section 3-10(c)(1)(B))
- RequiredScale Drawing of SignShows the sign's relationship to buildings, structures, and roads; ground signs require a footing detail with rebar requirements, and freestanding signs require engineering for Exposure C wind loads per the adopted IBC (City Code Section 3-10(c)(1)(C))
- OptionalElectrical PlansRequired for electrical/illuminated signs: disconnect location/type, grounding method, branch circuit rating, nameplate information, enclosure and clearance requirements, per the adopted NEC (City Code Section 3-10(c)(1)(D))
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Sign Permit (valuation-based) | (Valuation x 0.02) x (0.8) | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.12, "Building Permit Fee Calculations - Commercial," "Sign Permit" line — the same 0.02 rate applied to a Residential Deck Permit or Residential Garage; no separate flat sign fee was found on the schedule |
Fire Sprinkler / Fire Alarm / Fire Suppression System Permit
VerifiedRequired for installation, addition, or alteration of fire protection systems (fire alarm, fire sprinkler, or fire suppression systems) in the City of Sheridan. The City Building Department issues the local permit, but because the City has posted a notice that its Building Department lacks a certified Fire Plans Examiner or qualified fire-inspection professional, plan review for these systems must currently be submitted to and completed by the Wyoming State Fire Marshal's Office (Department of Fire Prevention & Electrical Safety), regardless of project size or valuation.
Verified 2026-07-22 · Source
Requirements
- A City-issued permit is required whenever fire alarm, fire sprinkler, or fire suppression systems are to be installed, even if no additional City fee applies because the work is part of a larger building permit (City of Sheridan FY27 Master Fee Schedule, p.11, "Simple Permits")
- Plan review for fire alarm, fire sprinkler, and fire suppression system installation, addition, or alteration is required by the Wyoming State Fire Marshal's Office regardless of size or valuation, submitted via the WSFM eLicensing/ePermit/ePayment Portal, because the City of Sheridan has posted a notice that it lacks a certified Fire Plans Examiner/qualified fire-inspection professional on staff
- Plans are accepted or rejected for review within 5 business days of receipt; complete submittals are then reviewed within 21 business days of acceptance (or within 10 business days of receiving requested additional information, whichever is greater) — Wyoming State Fire Marshal's Office, Plan Review Information page
- Review fees are calculated by the WY Department of Fire Prevention & Electrical Safety using its own fee schedule (Rules Chapter 2, Section 3) and the current ICC Building Valuation Table; applicants are notified of fees due once plans are accepted, and fees must be paid before a Permit to Construct is issued
- Fire sprinkler contractors must hold a City of Sheridan Fire Sprinkler Contractor license; fire alarm work falls under the City's Limited Electrical (including Fire Alarm) contractor license category (City Code Section 7-11, "Licenses—Contractor—Required")
- IBC Section 804.2.2 (local amendment) requires automatic sprinkler protection under specified conditions for work areas with shared exits/corridors serving occupant loads over 30 in Groups A, E, F-1, H, I, M, R-1, R-2, R-4, S-1, and S-2
- IFC Section 506.1 (local amendment) requires Knox boxes on all commercial occupancies, independent of whether a fire suppression/alarm system is installed
Required documents
- RequiredCity Building Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com for the local City permit/fee
- RequiredWSFM Fire Alarm / Fire Sprinkler / Special Hazard-Alternative Suppression Plan Checklist SubmittalComplete plans and specifications submitted to the Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety) via its ePermit portal, since the City routes fire system plan review to the State
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Fire Alarm System / Fire Sprinkler System / Fire Suppression System (Simple Permit, City) | Calculated with commercial permit fees if standalone; no additional City fee if the work is part of a larger building permit (a fire permit is still required) | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits" — Fire Alarm System, Fire Sprinkler System, and Fire Suppression System share this identical fee note; a standalone system's City fee follows the Commercial New/Add/Alter valuation formula on p.12 ((Valuation x 0.036) x 0.8 up to $100,000; (($100,000 x 0.036) + (balance x 0.0095)) x 0.8 above $100,000) |
| State Plan Review Fee (Wyoming Dept. of Fire Prevention & Electrical Safety) | Calculated per Department of Fire Prevention and Electrical Safety Rules, Chapter 2, Section 3 fee schedule, using the current ICC Building Valuation Table | Wyoming State Fire Marshal's Office, Plan Review Information page — applicant is notified of the exact fee once plans are accepted; paid by credit card via the online portal or by check to the Department in Cheyenne prior to issuance of a Permit to Construct |
Change of Occupancy Use Permit (Certificate of Occupancy)
VerifiedThe City of Sheridan's own fee schedule names this a "Change of Occupancy Use" Simple Permit (no fee). It is triggered by City Code Section 7-24.1, which requires any new business (before first occupying a building or portion of one) or any existing business relocating within the city to give the Building Official written notice of intent to occupy at least 30 days before the intended occupancy date, so the City can complete fire safety, building structure, sanitation, and zoning inspections before occupancy. Failure to file the required notice is grounds for denial of the certificate of occupancy or suspension of the business. The underlying certificate-of-occupancy standard is otherwise the 2024 International Building Code (Section 111) as adopted and locally amended by Ordinance No. 2290; no additional local amendment specific to Section 111 was found.
Verified 2026-07-22 · Source
Requirements
- Required before any new business occupies a building or portion of a building, and before any existing business moves into a different building or portion of a building, within the City (City Code Section 7-24.1(a))
- Written notice of intent to occupy must be filed with the Building Official not less than 30 days prior to the intended occupancy date (City Code Section 7-24.1(a))
- Filing the notice triggers required inspections, including but not limited to: fire safety, building structure, sanitation, and zoning (City Code Section 7-24.1(b))
- Failure to file the required notice is grounds for denial of the certificate of occupancy for the intended location, or suspension of the conduct of business until noted discrepancies are corrected (City Code Section 7-24.1(c))
- Processed as a City Simple Permit ("Change of Occupancy Use") with no plan review and no fee (City of Sheridan FY27 Master Fee Schedule, approved July 6, 2026, p.11)
- No local amendment specific to the base 2024 IBC Section 111 (Certificate of Occupancy) provisions was found in Ordinance No. 2290's documented amendments; the unamended 2024 IBC Section 111 standard applies as adopted
Required documents
- RequiredWritten Notice of Intent to OccupyFiled with the Building Official not less than 30 days before the intended occupancy date (City Code Section 7-24.1(a))
- RequiredChange of Occupancy Use Permit Application (OpenGov Permit & Licensing Portal)Online application at sheridanwy.portal.opengov.com for the no-fee Simple Permit
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Change of Occupancy Use (Simple Permit) | No Fee | City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Simple Permits — Change of Occupancy Use" |
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sheridan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.