Skip to main content
PermitBase

You are viewing the permanent link for the record currently in effect, published 2026-08-26.

Unincorporated Sheridan County building permits

Verified

Unincorporated Sheridan County, Wyoming — as published 2026-08-26.

Verified 2026-07-01 · Source

Codes adopted

NO countywide building code / NO general building permit for private construction in unincorporated Sheridan County. Per the Wyoming State Fire Marshal's 'Local and State Jurisdictions' chart, Sheridan County (county-level row) is listed BLDG INSP/PR = STATE and ELEC INSP/PR = STATE — the county has NOT taken general countywide building-code delegation under W.S. § 35-9-121, so the State Fire Marshal / state program has building and electrical jurisdiction across most of unincorporated Sheridan County.IMPORTANT NUANCE (confirmed on the county's own site): Sheridan County DOES have an adopted 'Building Standards, Sheridan County, Wyoming' rule (adopted Nov. 18, 1991; last amended May 16, 2023, filed as County Clerk doc. #2023-785780) that adopts the 2021 International Building Code, 2021 IRC, 2021 IMC, 2021 IFGC, 2021 IPC, 2021 International Fire Code, the 2022 National Electrical Code, and the Uniform Code for the Abatement of Dangerous Buildings — but ARTICLE I, Section 3 (Applicability) confirms this code applies ONLY within a mapped 'Sheridan County Building Standards Area' (a defined zone around/adjoining the City of Sheridan shown on the Appendix A Planning Map), PLUS specific legacy subdivisions the BOCC imposed permitting/inspection on before Dec. 5, 2006, all NEW subdivisions approved after Dec. 5, 2006, and any structure built under a Conditional Use Permit. It does NOT apply countywide.Farms and ranches on 40 acres or more of deeded land are specifically EXEMPT from the Building Standards code entirely (Article I, Sec. 3(b)(1)), as are county hospitals, mines/oilfield/refinery facilities, and railway buildings.Where the Building Standards DO apply (the mapped area / qualifying subdivisions / CUP structures): a building permit is required before construction of any building/structure valued over $5,000 (Article III, Sec. 1), enforced by the Sheridan County Building Official.Where the Building Standards do NOT apply (the vast majority of unincorporated Sheridan County — rural and agricultural land outside the mapped area): there is no county building permit for private construction; a Zoning Permit (land-use/setback compliance, not a structural building-code permit) is still required countywide for new construction or change of use.Electrical: wiring permits/inspections are issued by the Wyoming State Fire Marshal's Office — Dept. of Fire Prevention & Electrical Safety (Chief Electrical Inspector), not Sheridan County, per the county's own Zoning Permit application which directs applicants doing new electrical work to WSFM.

Permit types & fees

Zoning Permit

Verified

The baseline land-use permit required countywide in unincorporated Sheridan County before new construction, additions, accessory structures, or a change of use — regardless of whether the parcel falls inside the mapped Building Standards (building-code) area. Verifies zoning district compliance, setbacks, access, and floodplain location; is NOT a structural building-code review outside the mapped Building Standards Area.

Verified 2026-07-16 · Source

Requirements

  • Required prior to new construction (single-family, multi-family, accessory dwelling, commercial, industrial, or accessory building) or any change of use with no new construction
  • Plot plan (to scale, no larger than 11x17) showing property lines/bearings/distances, point of access to public road/easement, easements/ditches/floodplain/water bodies, proposed and existing structure setbacks, building layout, and required parking
  • Proof of ownership (recorded deed copy) and documentation of when the parcel was legally established
  • Notarized authorization if an agent applies on the owner's behalf; LLC ownership requires documentation of signing authority
  • Affidavit of Occupancy required if the structure is an accessory dwelling
  • Copy of an approved access permit from the applicable agency (WYDOT for state highways, or the county driveway permit) must accompany the application
  • Allow 10 business days for the county to determine the application is complete; issuance can take up to 30 days after the application is deemed complete
  • A site inspection is performed upon permit approval; new construction must be staked out per the plot plan
  • Each new building/structure/addition placed on a property requires a separate permit

Required documents

  • RequiredSheridan County Zoning Permit Application (revised 5/1/2026)Official application form with zoning checklist, fee, and list of related state permits

Fee schedule

Fee typeAmountNotes
Zoning Permit fee (nonrefundable, due upon submittal)$150.00Sheridan County Zoning Permit Application (rev. 5/1/2026)
Zoning Permit fee — new construction commenced prior to permit approval$300.00Penalty-rate fee per the Zoning Permit Application when work starts before approval

Building Permit (Sheridan County Building Standards Area ONLY)

Verified

A true structural building-code permit under the adopted 2021 I-Codes package IS required, but ONLY for structures within the mapped 'Sheridan County Building Standards Area' (a zone around/adjoining the City of Sheridan — see Appendix A Planning Map), specific legacy subdivisions the BOCC already imposed permitting/inspection on before Dec. 5, 2006, all subdivisions approved after Dec. 5, 2006, and any structure built under a Conditional Use Permit. Outside that defined area, unincorporated Sheridan County generally has NO county building permit for private construction. COMMERCIAL SCOPE: this single permit covers COMMERCIAL construction too. In the recorded Building Standards ordinance, Article I, Sec. 3(a) applies the rules to 'all structures' in the covered areas with no commercial/residential distinction, Article III, Sec. 1 requires the permit for 'any building or structure' valued over $5,000, and the 2021 International Building Code (the commercial code) is adopted in whole under Article II, Sec. 1. Sheridan County has NO separate commercial building permit, commercial fee line, or commercial-specific process anywhere in the county — neither the ordinance, nor the county's Building in the County page, nor its Required Permits page distinguishes commercial from residential. Commercial projects OUTSIDE the covered areas get no county structural permit at all; they are governed by the countywide Zoning Permit plus, for qualifying occupancies, mandatory Wyoming State Fire Marshal fire/life-safety plan review and a state Permit to Construct under W.S. § 35-9-108 (see tips).

Verified 2026-08-02 · Source

Requirements

  • Required before construction of any building or structure valued over $5,000 (new construction, remodeling, repair, additions, or demolition) — ONLY for parcels within the mapped Building Standards Area, qualifying legacy/post-2006 subdivisions, or Conditional Use Permit structures
  • All construction, regardless of value, must conform to the adopted codes if the parcel is within scope
  • Codes adopted (per 'Building Standards, Sheridan County, Wyoming,' filed as County Clerk doc. #2023-785780, effective May 30, 2023, Article II and the Exhibit 1 revision table): 2021 International Building Code, 2021 International Residential Code, 2021 International Mechanical Code, 2021 International Fuel Gas Code, 2021 International Plumbing Code, 2022 National Electrical Code, 2021 International Fire Code, and the Uniform Code for the Abatement of Dangerous Buildings, plus the current International Code Council Building Valuation Data
  • Farms/ranches on 40+ deeded acres, county hospitals, mines/oilfield/refinery facilities, and railway buildings/equipment are exempt from these codes even within the mapped area
  • Commercial buildings are covered by this SAME permit within the covered areas — Article I, Sec. 3(a) applies to 'all structures' and Article III, Sec. 1 to 'any building or structure' over $5,000, with the 2021 IBC adopted in whole; unincorporated Sheridan County has no separate county commercial permit, application, or fee (recorded ordinance, pages 6 and 9 of County Clerk doc. #2023-785780)
  • Commercial projects ANYWHERE in unincorporated Sheridan County (inside or outside the Building Standards Area) that meet W.S. § 35-9-108 thresholds additionally require Wyoming State Fire Marshal plan review and a state Permit to Construct BEFORE work begins: state/local government owned or leased buildings, schools, buildings over 5,000 sq ft total area with public access (such as a business), child care centers for more than 10 children, multi-story buildings, places of assembly regardless of size, and alterations/remodels of any of those valued at $40,000+ (per ICC Building Valuation Data) — per wsfm.wyo.gov/fire-prevention/plan-review, fetched 2026-08-01
  • Enforced by the Sheridan County Building Official

Required documents

  • RequiredBuilding App & Submittal Requirements (rev. 5/1/2026)Sheridan County's building permit application and submittal checklist for parcels within the Building Standards Area
  • RequiredBuilding Code Enforcement Area MapConfirms whether a given parcel falls within the mapped Building Standards Area

Fee schedule

Fee typeAmountNotes
Building permit feeNot published as a flat or valuation-based fee schedule on the county's public site
Article IV County Amendments (IBC Sec. 109.3 / IRC Sec. Show full citation

Article IV County Amendments (IBC Sec. 109.3 / IRC Sec. R108.2) of the Building Standards ordinance ties the fee to Table AL 101.1, Appendix AL Permit Fees of the 2021 International Residential Code, plus a separate plan-review fee (set by Sheridan County, not to exceed 67% of the building permit fee) — but the county's public site does not itself publish a standalone flat or valuation-based fee table. Contact Sheridan County Public Works at (307) 674-2920 to confirm current fees for parcels within the mapped area.

Building Permit (Commercial New Construction, Additions, Remodels & Tenant Improvements)

Verified

Sheridan County publishes no separate commercial building permit, application, or fee. Within the mapped Sheridan County Building Standards Area (Appendix A Planning Map to Building Standards, Sheridan County, Wyoming, County Clerk doc. #2023-785780), qualifying legacy subdivisions the county already permits, all subdivisions approved after December 5, 2006, and Conditional Use Permit structures, a commercial building or structure valued over $5,000 uses the same Building Permit issued for residential construction: the ordinance applies to 'all structures' (Article I, Sec. 3(a)), requires a permit for 'any building or structure' over $5,000 (Article III, Sec. 1), and adopts the 2021 International Building Code in whole (Article II, Sec. 1) alongside the county's other 2021-2022 codes. The county's own Building & Zoning Permit Plan Submittal Requirements add one commercial-specific condition: plans for a structure intended for business, commercial, or industrial use must be designed and certified by an engineer or architect licensed in the State of Wyoming. Outside the mapped area, outside those subdivisions, and absent a Conditional Use Permit, the county issues no structural building permit for commercial construction at all; the project instead needs the countywide Zoning Permit and, for an occupancy meeting Wyoming State Fire Marshal thresholds under W.S. § 35-9-108, a separate state fire/life-safety plan review and Permit to Construct.

Verified 2026-08-26 · Source

Requirements

  • Required for construction of any building or structure valued over $5,000, per Article III, Sec. 1 of Building Standards, Sheridan County, Wyoming (County Clerk doc. #2023-785780) — applies to commercial and residential construction alike within the mapped Building Standards Area, qualifying pre-December 5, 2006 subdivisions the county already permits, all subdivisions approved after that date, and Conditional Use Permit structures
  • Reviewed under the 2021 International Building Code, adopted in whole by Article II, Sec. 1 of the same ordinance, together with the 2021 International Residential, Mechanical, Fuel Gas, and Plumbing Codes, the 2022 National Electrical Code, and the 2021 International Fire Code, except where Article IV County Amendments specifically modify a section
  • Plans for a structure intended for business, commercial, or industrial use must be designed, drawn, and certified as code-compliant by an engineer and/or architect licensed in the State of Wyoming, per the Building & Zoning Permit Plan Submittal Requirements (rev. 5/1/2026); this certification is not required of ordinary residential plans
  • Building valuation and the permit fee are set from the same valuation-banded table used for residential construction — no separate commercial fee tier exists — per the Sheridan County Land Use Fee Schedule (adopted June 6, 2023)
  • A plan review fee is charged in addition to the building permit fee, set at 47 percent of the building permit fee per the Land Use Fee Schedule (adopted June 6, 2023) — within the up-to-67-percent ceiling Article IV sets for the amended 2021 IBC Section 109.3
  • Farms and ranches on 40 or more deeded acres, county hospitals, mines and oilfield/refinery facilities, and railway buildings are exempt from these codes even within the mapped area, per Article I, Sec. 3(b)
  • Sheridan County conducts no fire-district or county fire plan review for a commercial building permit; a project meeting Wyoming State Fire Marshal thresholds under W.S. § 35-9-108 — a building over 5,000 square feet with public access, a place of assembly of any size, a school, a government building, a child care center for more than 10 children, a multi-story building, or a $40,000-or-more alteration of any of these — additionally needs a Wyoming State Fire Marshal fire/life-safety plan review and state Permit to Construct before work begins, whether or not the parcel is within the mapped Building Standards Area
  • Outside the mapped Building Standards Area, outside the qualifying subdivisions, and absent a Conditional Use Permit, the county issues no structural building permit for commercial construction; the project instead needs the countywide Zoning Permit and, where the Wyoming State Fire Marshal thresholds above are met, the state plan review and Permit to Construct
  • Enforced by the Sheridan County Building Official; the Building & Zoning Permit form itself states occupancy is not allowed until final inspection and a Certificate of Occupancy are issued

Required documents

  • RequiredSheridan County Building & Zoning PermitThe county's single combined building-and-zoning permit form, used for residential and commercial construction alike; Sheridan County publishes no separate commercial or tenant-improvement application
  • RequiredBuilding & Zoning Permit Plan Submittal Requirements (rev. 5/1/2026)Site/plot plan, foundation plan, floor framing plan, floor plan, roof framing plan, cross section, and elevation view requirements; plans for business, commercial, or industrial structures must additionally be designed and certified by a Wyoming-licensed engineer or architect
  • RequiredBuilding Code Enforcement Area Map (Appendix A Planning Map)Confirms whether a given parcel falls within the mapped Sheridan County Building Standards Area

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $5,000 to $40,000$69.00 for the first $2,000 plus $11.00 for each additional $1,000 or fraction thereof, up to and including $40,000
Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table — the same table used for residential construction. Show full citation

Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table — the same table used for residential construction. Building Standards, Sheridan County, Wyoming, Article IV separately ties this fee to Table AL 101.1, Appendix AL of the 2021 IRC; this schedule is the county's current, standalone dollar figure.

Building Permit — valuation $40,001 to $100,000$487.00 for the first $40,000 plus $9.00 for each additional $1,000 or fraction thereof, up to and including $100,000Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table.
Building Permit — valuation $100,001 to $500,000$1,027.00 for the first $100,000 plus $7.00 for each additional $1,000 or fraction thereof, up to and including $500,000Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table.
Building Permit — valuation $500,001 to $1,000,000$3,827.00 for the first $500,000 plus $65.00 for each additional $1,000 or fraction thereof, up to and including $1,000,000Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table. This tier's printed $65-per-$1,000 marginal rate does not reconcile with the $6,327.00 base the schedule states for the next tier; recorded as published, not corrected.
Building Permit — valuation $1,000,001 to $5,000,000$6,327.00 for the first $1,000,000 plus $3.00 for each additional $1,000 or fraction thereof, up to and including $5,000,000Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table.
Building Permit — valuation $5,000,001 and up$18,327.00 for the first $5,000,000 plus $1.00 for each additional $1,000 or fraction thereofSheridan County Land Use Fee Schedule (adopted June 6, 2023), Building Permit valuation table.
Plan Review fee47% of the Building Permit feeSheridan County Land Use Fee Schedule (adopted June 6, 2023): 'plan review fee is set at 47% of the building permit fee' — within the up-to-67% ceiling Article IV of Building Standards, Sheridan County, Wyoming sets for the amended 2021 IBC Section 109.3.
Inspection fee — work commenced before permit issuanceThe calculated Building Permit fee plus 33%Sheridan County Land Use Fee Schedule (adopted June 6, 2023), Inspection Fees section.
Wyoming State Fire Marshal fire/life-safety plan review and Permit to Construct fee (occupancies meeting W.S. § 35-9-108 thresholds only)Not published as a flat dollar figure
Wyoming State Fire Marshal's Plan Review page states the fee is calculated from Dept. Show full citation

Wyoming State Fire Marshal's Plan Review page states the fee is calculated from Dept. of Fire Prevention & Electrical Safety Rules, Chapter 2, Section 3, and the applicant is notified of the specific amount once plans are accepted. Contact the Wyoming State Fire Marshal's Office at (307) 777-7288 to confirm current fees.

Flood Plain Development Permit

Verified

Required countywide (including outside the Building Standards Area) for development activity within the mapped Special Flood Hazard Area, under Sheridan County's Rules and Regulations Governing Flood Plain Management. Covers new construction, substantial improvements, fill placement, and other development in the floodplain.

Verified 2026-07-16 · Source

Requirements

  • Required for new construction, substantial improvement, fill placement, storage of materials/equipment, or drainage facility work within the mapped floodplain
  • Plans in duplicate, drawn to scale, showing elevations of the project area and nature/location/dimensions of existing and proposed structures
  • Elevation (NAVD 88) of the lowest floor level (including crawl space or basement) of all proposed structures
  • Base Flood Elevation (BFE), with method and supporting documentation
  • Design certification from a registered PE or architect for any flood-proofed non-residential structure
  • Description of the extent to which any watercourse will be altered or relocated
  • As-built Elevation Certificate (FEMA form) required immediately after the lowest floor/flood-proofing level is completed
  • Permit expires one year after issuance unless the permitted activity has substantially begun and is pursued to completion

Required documents

  • RequiredFlood Plain Development Permit ApplicationSheridan County Public Works application form, including the Floodway No-Rise Certificate template

Fee schedule

Fee typeAmountNotes
Flood Plain Development Permit fee (nonrefundable)$100.00Sheridan County Flood Plain Development Permit Application

Septic / Small Wastewater System Permit

Verified

Required countywide for installation of a new conventional septic tank and leachfield system (or other small wastewater disposal system) in unincorporated Sheridan County, under the county's Rules and Regulations Governing Wastewater Systems (aligned with WY DEQ Water Quality Rules and Regulations Chapter 25).

Verified 2026-07-16 · Source

Requirements

  • Covers conventional systems only: wastewater flow under 2,000 gallons/day of domestic sewage, standard trench/bed disposal (stone-and-pipe or chambers), seasonal high groundwater/bedrock/impervious clay 4+ feet below the proposed leachfield bottom, and soil percolation rate between 5 and 60 minutes per inch
  • Non-conventional systems (outside those parameters) require direct consultation with Sheridan County Public Works; systems over 2,000 gal/day or non-domestic waste route to the WY DEQ Underground Injection Control (UIC) Program
  • Groundwater test pit dug 4 feet deeper than the bottom of the proposed leachfield, open at least 24 hours, and inspected by a Sheridan County representative prior to submission
  • Percolation test performed per county instructions
  • Proof of ownership (recorded deed) required; notarized authorization needed if applicant is not the owner
  • 24-hour notice required to schedule the final inspection prior to backfilling the system
  • Fee due upon submission; starting installation before approval is subject to a fine

Required documents

  • RequiredSeptic System Permit Application (Sheridan County / WY DEQ design forms, Water Quality Division)22-page combined application, site suitability, percolation test, and leachfield design worksheet package

Fee schedule

Fee typeAmountNotes
Septic permit fee (due upon submission)$250.00Sheridan County Septic System Permit Application

Driveway / Road-Use (Access) Permit

Verified

Required countywide for any driveway or subdivision road entering a Sheridan County-maintained road; issued by Sheridan County Engineering at no charge. Driveways accessing a STATE highway instead require a WYDOT access permit, not a county permit.

Verified 2026-07-16 · Source

Requirements

  • Required before performing any work within county right-of-way for a new or modified driveway/subdivision road access onto a county-maintained road
  • Application specifies road name/number, township/range/section, mile point, and side of road
  • County Engineer determines minimum culvert/drainage-structure size (minimum 18-inch round or equivalent pipe-arch, 24 feet long) and whether a Road-Use Agreement is required
  • Gravel minimum 4 inches deep required on the driveway for at least 150 feet (or the driveway length, whichever is less) from the county road edge
  • Permit is void if the driveway is not constructed within 6 months of approval
  • Call (307) 674-2920 for County inspection once construction is complete
  • Driveways onto STATE highways instead require a WYDOT Access Permit — not this county permit

Required documents

  • RequiredSheridan County Application for Driveway Permit (updated 3/22)Combined application, policy statement, and administration/design standards packet

Fee schedule

Fee typeAmountNotes
Driveway permit feeNo charge — "There will not be a charge for issuing a driveway permit"Sheridan County Application for Driveway Permit (updated 3/22), Administration item 1

Electrical Permit (State Program)

Verified

Electrical wiring permits and inspections for unincorporated Sheridan County are issued by the Wyoming State Fire Marshal's Office — Dept. of Fire Prevention & Electrical Safety (Chief Electrical Inspector) under W.S. § 35-9-119, not by Sheridan County. Sheridan County's own Zoning Permit application directs applicants with new electrical work to the state program.

Verified 2026-07-16 · Source

Requirements

  • New electrical work may require a permit through the WY Dept. of Fire Prevention & Electrical Safety (WSFM) prior to construction and inspection by the state electrical inspector
  • 2026 NEC enforced statewide by the WSFM electrical program by default, effective July 1, 2026 per wsfm.wyo.gov/electrical-safety (2023 NEC was in effect before that date)
  • Apply online via wyelectrician.imagetrendlicense.com; Sheridan has a regional WSFM inspector office

Required documents

  • RequiredWyoming State Fire Marshal Electrical Wiring Permit ApplicationState-issued application via the WSFM online portal

Fee schedule

Fee typeAmountNotes
Standard wiring permit$50.00 (temporary/90-day permit: $40.00)Permit fee waived if an inspection is requested and paid for. WY State Fire Marshal electrical fee schedule.
Residential inspection fee — 100A service$70.00 (includes the $50 permit)
Guaranteed Inspection Fee Schedule linked from the Wyoming State Fire Marshal Wiring Permits page — Residential & Mobile Homes (Single Family) table, 100 Amp Service; Show full citation

Guaranteed Inspection Fee Schedule linked from the Wyoming State Fire Marshal Wiring Permits page — Residential & Mobile Homes (Single Family) table, 100 Amp Service; equals the W.S. 35-9-120(c)(i)(A) statutory maximum of $20.00 plus $0.50 per ampere. Unincorporated Sheridan County is State-enforced for electrical inspection and plan review under the Department's LOCAL AND STATE JURISDICTIONS chart (the City of Sheridan is locally enforced), so the State schedule is the operative one

Residential inspection fee — 200A service$120.00 (includes the $50 permit)Guaranteed Inspection Fee Schedule linked from the Wyoming State Fire Marshal Wiring Permits page — Residential & Mobile Homes (Single Family) table, 200 Amp Service; equals the W.S. 35-9-120(c)(i)(A) statutory maximum of $20.00 plus $0.50 per ampere

Solar PV Permit

Verified

Sheridan County has no dedicated solar permit or fee category. A residential rooftop or ground-mounted PV installation is processed under the same baseline Zoning Permit ($150) required countywide for any new construction or accessory structure, verifying setbacks and zoning-district compliance — no solar-specific accessory-use classification or setback distance was found published in the county's zoning materials. A true structural building-code permit additionally applies ONLY if the parcel falls within the mapped Sheridan County Building Standards Area (near the City of Sheridan), a pre-2006 legacy subdivision the county already permits, a post-2006 subdivision, or a Conditional Use Permit structure — otherwise the county has no structural building-code review at all for private construction. Electrical interconnection is handled by the Wyoming State Fire Marshal's Office (WSFM) — Dept. of Fire Prevention & Electrical Safety, not the county, per the same statewide mechanism documented in this jurisdiction's Electrical Permit entry.

Verified 2026-07-20 · Source

Requirements

  • Zoning Permit required countywide before installing a rooftop or ground-mounted solar system, as new construction/an accessory structure — submit a plot plan (to scale, ≤11x17) showing property lines, setbacks, and the array's location relative to existing structures
  • Proof of ownership (recorded deed copy) and documentation of when the parcel was legally established
  • A true structural building-code permit (2021 I-Codes) additionally applies ONLY if the parcel is within the mapped Sheridan County Building Standards Area, a specific pre-Dec. 5, 2006 legacy subdivision, any subdivision approved after Dec. 5, 2006, or a Conditional Use Permit structure
  • Electrical interconnection (arrays, inverters, disconnects, point of connection) requires a separate Wyoming State Fire Marshal Electrical Wiring Permit — apply online via wyelectrician.imagetrendlicense.com — not issued by Sheridan County
  • Copy of an approved access permit must accompany the Zoning Permit application if the project changes driveway/road access

Required documents

  • RequiredSheridan County Zoning Permit Application (revised 5/1/2026)The county's baseline land-use permit application, used for solar installations since no dedicated solar form exists
  • RequiredWyoming State Fire Marshal Electrical Wiring Permit ApplicationState-issued application via the WSFM online portal, for the PV interconnection/wiring

Fee schedule

Fee typeAmountNotes
Zoning Permit fee (nonrefundable, due upon submittal)$150.00
Sheridan County Zoning Permit Application (rev. Show full citation

Sheridan County Zoning Permit Application (rev. 5/1/2026) — same baseline fee documented in this jurisdiction's Zoning Permit entry; no rate specific to residential rooftop or ground-mounted PV is published. The county's Land Use Fee Schedule (adopted 6-6-2023) does publish a Solar Energy Permit at $2,400.00, but only for Commercial Solar Energy Facilities, governed by the separate Rules and Regulations Governing the Permitting of Commercial Solar Energy Facilities — a different product from a household installation.

Structural building-code permit (only within the mapped Building Standards Area, legacy/post-2006 subdivisions, or CUP structures)Not published as a flat or valuation-based fee schedule on the county's public site
Tied to Table AL 101.1, Appendix AL Permit Fees of the 2021 IRC per Article IV County Amendments, plus a plan-review fee not to exceed 67% of the building permit fee — same gap already documented in… Show full citation

Tied to Table AL 101.1, Appendix AL Permit Fees of the 2021 IRC per Article IV County Amendments, plus a plan-review fee not to exceed 67% of the building permit fee — same gap already documented in this jurisdiction's building-permit-limited-area entry. Contact Sheridan County Public Works at (307) 674-2920 to confirm.

WSFM Electrical Wiring Permit (interconnection)$50.00 standard ($40.00 temporary/90-day); residential inspection fees $70 (100A service, includes permit) or $120 (200A service, includes permit)Wyoming State Fire Marshal electrical fee schedule. The Wiring Permits page (wsfm.wyo.gov/electrical-safety/wiring-permits-1) states: ‘A fee of $50.00 shall be paid for any electrical wiring permit issued by the Department.’

EV Charger / EVSE Permit

Verified

Unincorporated Sheridan County does not run its own electrical inspection program — electrical wiring permits are issued by the Wyoming State Fire Marshal's Office (WSFM), Dept. of Fire Prevention & Electrical Safety, under W.S. § 35-9-119, confirmed by the county's own Zoning Permit application, which routes new electrical work to the state program. An EV charger/EVSE installation therefore requires a State of Wyoming Electrical Wiring Permit through WSFM, not a county permit. WSFM publishes no distinct EV charger/EVSE fee line; a residential EVSE circuit is billed under the same standard wiring permit and residential service inspection fee structure used for all electrical work.

Verified 2026-07-20 · Source

Requirements

  • State of Wyoming Electrical Wiring Permit (WSFM) required for EV charger/EVSE circuit installation in unincorporated Sheridan County — apply online via wyelectrician.imagetrendlicense.com
  • A Sheridan regional WSFM inspector office handles local inspections
  • Installation must comply with the 2026 NEC as enforced statewide by WSFM effective July 1, 2026 (2023 NEC was in effect before that date)
  • No distinct EV charger/EVSE fee line, expedited timeline, or SolarAPP+-style instant-permitting platform was found published by WSFM as of the last verification

Required documents

  • RequiredWyoming State Fire Marshal Electrical Wiring Permit ApplicationState-issued application via the WSFM online portal, covering EV charger/EVSE circuit installation

Fee schedule

Fee typeAmountNotes
Standard wiring permit$50.00 (temporary/90-day permit: $40.00)WY State Fire Marshal electrical fee schedule — same base permit fee documented on this jurisdiction's Electrical Permit entry; no distinct EV charger/EVSE fee line is published. Permit fee is waived if an inspection is requested and paid for.
Residential inspection fee — 100A service (typical for a Level 2 EV charger circuit)$70.00 (includes the $50 permit)WY State Fire Marshal electrical fee schedule.
Residential inspection fee — 200A service$120.00 (includes the $50 permit)WY State Fire Marshal electrical fee schedule — applicable if the EV charger installation requires a larger service upgrade.

Sign Permit (WYDOT Outdoor Advertising Permit — no county-level sign permit)

Sheridan County's own official Required Permits page (which lists only Building & Zoning, Driveway, Septic, and Flood Plain permits) and its Land Use Fee Schedule (adopted Oct. 4, 2011) contain no county-issued sign permit or sign-specific fee line. A sign large enough to qualify as new construction or an accessory structure would fall under the same baseline countywide Zoning Permit ($150, documented in this jurisdiction's Zoning Permit entry). The one confirmed, distinct sign permit that DOES apply is the Wyoming Department of Transportation (WYDOT) Outdoor Advertising Permit, a state-level permit required for off-premise advertising signs (billboards) visible from a state highway or interstate — separate from, and not administered by, Sheridan County.

Reviewed 2026-07-22 · Source

Requirements

  • Sheridan County has no distinct county-issued sign permit or sign-specific fee — confirmed against the county's own Required Permits page (lists only Building & Zoning, Driveway, Septic, and Flood Plain permits) and the Sheridan County Land Use Fee Schedule (adopted Oct. 4, 2011), neither of which lists a sign or signage fee
  • A sign meeting the general threshold of 'new construction' or an accessory structure would be captured by the same countywide Zoning Permit ($150) documented in this jurisdiction's Zoning Permit entry — confirm with Sheridan County Public Works whether a specific proposed sign requires this
  • WYDOT Outdoor Advertising Permit required for off-premise advertising signs (billboards) visible from a state highway or interstate — a separate application and fee is required per sign
  • Written permission from the landowner on whose property the sign will be located
  • Proof of zoning from local (county or city) authorities
  • Detailed sketch showing the proposed sign location and distances to nearby existing signs and businesses
  • Local permit approval if required by the county or city
  • Placing any sign or object within a state highway right-of-way is prohibited outright, regardless of permit status

Required documents

  • RequiredWYDOT Outdoor Advertising Permit ApplicationState application for an off-premise advertising sign visible from a state highway or interstate; a separate application is required per sign

Fee schedule

Fee typeAmountNotes
WYDOT Outdoor Advertising Permit — initial application fee (per sign, nonrefundable)$100.00WYDOT Outdoor Advertising program page, dot.state.wy.us
WYDOT Outdoor Advertising Permit — annual maintenance fee$15.00/yearBilling for this fee begins in the fourth year of the permit, per WYDOT's Outdoor Advertising program page
Sheridan County sign-specific feeNone published
No sign line-item appears on the Sheridan County Land Use Fee Schedule (adopted Oct. Show full citation

No sign line-item appears on the Sheridan County Land Use Fee Schedule (adopted Oct. 4, 2011) or the county's Required Permits page; a sign large enough to be a 'structure' falls under the general $150 Zoning Permit fee already documented in this jurisdiction's Zoning Permit entry.

Fire Sprinkler / Fire Alarm Permit (State Program)

Verified

Sheridan County and its constituent volunteer rural fire protection districts (Big Horn, Clearmont, Dayton, Sheridan Area Rural, Story, and Tongue River) do not run a fire-protection-system plan-review or permitting program of their own. Installation, addition, or alteration of a fire alarm, fire sprinkler, fire suppression, or special hazard system anywhere in Wyoming — including unincorporated Sheridan County — is permitted and inspected by the Wyoming State Fire Marshal's Office (WSFM), Dept. of Fire Prevention & Electrical Safety, the same state agency that runs the electrical wiring permit program already documented in this jurisdiction's Electrical Permit entry.

Verified 2026-07-22 · Source

Requirements

  • State of Wyoming fire protection system plan review and Permit to Construct required through WSFM for installation, addition, or alteration of a fire alarm, fire sprinkler, fire suppression, or special hazard system — required 'regardless of size or valuation' per WSFM's Plan Review program page
  • Apply through the WSFM eLicensing, ePermit, and ePayment Portal
  • Plans are accepted or rejected within 5 business days of receipt
  • Complete submittals are reviewed within 21 further business days of acceptance; if WSFM requests additional information, review completes within 10 business days of receiving it or the original 21-day window, whichever is later
  • Review fees are calculated from the fee schedule in Dept. of Fire Prevention & Electrical Safety Rules, Chapter 2, Section 3; the applicant is notified of the exact fee once plans are accepted, and payment is due before the Permit to Construct is issued
  • Upon completion and passing of all required inspections, WSFM issues a Certificate of Occupancy or Letter of Compliance
  • None of the six rural fire protection districts serving unincorporated Sheridan County administer their own sprinkler/alarm permitting or plan review — confirmed on Sheridan County's own Fire Protection Districts page, which lists only district governance/meeting contacts, not a permitting function

Required documents

  • RequiredWSFM Fire Protection System Plan Review Application (eLicensing/ePermit portal)State application and plan submittal for a new or altered fire alarm, sprinkler, suppression, or special hazard system

Fee schedule

Fee typeAmountNotes
Fire protection system plan review / Permit to Construct feeNot published as a flat dollar figure
WSFM's Plan Review page states the fee is calculated from Dept. Show full citation

WSFM's Plan Review page states the fee is calculated from Dept. of Fire Prevention & Electrical Safety Rules, Chapter 2, Section 3, and the applicant is notified of the specific amount once plans are accepted; the current Chapter 2 rules text is available only as a scanned/image PDF, so its rate detail is not reproduced here. Contact WSFM at (307) 777-7288 to confirm current fees.

Change of Use / Certificate of Occupancy

Verified

Sheridan County does not operate a separate, standalone 'change of use' permit or issue its own Certificates of Occupancy for private construction. The county's own official Required Permits page folds change of use directly into the existing Building Permit & Zoning Permit line item — 'Construction of any new building, or addition to, or change of use of existing building' — meaning a change of use is processed through the SAME Zoning Permit ($150, documented in this jurisdiction's Zoning Permit entry) required countywide for new construction, or through the Building Permit (documented in this jurisdiction's building-permit-limited-area entry) if the parcel falls within the mapped Building Standards Area, a qualifying subdivision, or a Conditional Use Permit structure. Where a true Certificate of Occupancy or Letter of Compliance IS issued for a structure in unincorporated Sheridan County — i.e. one subject to Wyoming State Fire Marshal fire/life-safety plan review, such as a public building or a structure with a permitted fire alarm/suppression system — WSFM itself issues that certificate upon completion and passing of all required inspections, the same state mechanism documented in this jurisdiction's Fire Sprinkler/Alarm Permit entry.

Verified 2026-07-22 · Source

Requirements

  • No standalone 'change of use' permit exists in unincorporated Sheridan County — per the county's own Required Permits page, a change of use of an existing building is processed under the same Building Permit & Zoning Permit line item used for new construction
  • Where the parcel is OUTSIDE the mapped Building Standards Area (the large majority of unincorporated Sheridan County), a change of use is processed through the baseline Zoning Permit ($150) — same requirements, plot plan, and proof of ownership documented in this jurisdiction's Zoning Permit entry
  • Where the parcel is INSIDE the mapped Building Standards Area, a qualifying pre-2006/post-2006 subdivision, or a Conditional Use Permit structure, a change of use is instead processed through the county Building Permit documented in this jurisdiction's building-permit-limited-area entry
  • Sheridan County does not itself issue a separate 'Certificate of Occupancy' document for ordinary private construction — no such form or process is published on the county's Required Permits page, Building in the County page, or Land Use Fee Schedule
  • Where a Certificate of Occupancy or Letter of Compliance IS issued in unincorporated Sheridan County, it is issued by the Wyoming State Fire Marshal's Office upon completion and passing of all required fire/life-safety plan-review inspections — applicable to public buildings and structures with a permitted fire alarm/sprinkler/suppression system, per WSFM's Fire Prevention program page

Required documents

  • RequiredSheridan County Zoning Permit Application (revised 5/1/2026)Used for a change of use with no new construction outside the mapped Building Standards Area — same form documented in this jurisdiction's Zoning Permit entry
  • OptionalBuilding App & Submittal Requirements (rev. 5/1/2026)Used instead for a change of use within the mapped Building Standards Area, a qualifying subdivision, or a Conditional Use Permit structure — same form documented in this jurisdiction's building-permit-limited-area entry

Fee schedule

Fee typeAmountNotes
Change of use feeNo distinct fee — billed as a Zoning Permit ($150.00) or, within the mapped Building Standards Area, as a Building PermitSheridan County Land Use Fee Schedule (adopted Oct. 4, 2011) lists only a single 'Zoning Certificate' fee ($150.00) plus the separate Building Permit valuation table; no distinct change-of-use or certificate-of-occupancy line item exists.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Sheridan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-22)View current record →All versions →

Permalink: /wyoming/sheridan-county/unincorporated-sheridan/as-of/2026-08-26/

Snapshot date: 2026-08-26

Commit: 4e9b2b0

Reproducible from PermitBase’s version-controlled dataset, commit 4e9b2b0.