Skip to main content
PermitBase

You are viewing the permanent link for the record currently in effect, published 2026-07-06.

Eagar building permits

Verified

Eagar, Arizona — as published 2026-07-06.

Verified 2026-07-06 · Source

Codes adopted

Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Eagar runs its own Community Development / Building Department and independently adopts and administers its own construction codes; it does NOT defer building permitting to Apache County or to the neighboring Town of Springerville. Source: Town of Eagar Building page (eagaraz.gov/o/tofe/page/building) and the Town's own published Building, Commercial, Electrical, Plumbing, Mechanical, and Demolition Permit Application forms, each captioned 'Return this application... to the Building Department.'2018 International Residential Code (IRC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page (eagaraz.gov/o/tofe/page/building): 'Adopted Building Codes – 2018 IRC, IBC, IPC, IMC, IPMC, IFC and 2011 NEC.'2018 International Building Code (IBC), as adopted by the Town of Eagar for commercial/non-residential construction. Source: Town of Eagar Building Design Specifications page.2018 International Plumbing Code (IPC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.2018 International Mechanical Code (IMC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.2018 International Property Maintenance Code (IPMC), as adopted by the Town of Eagar. Source: Town of Eagar Building Design Specifications page.2018 International Fire Code (IFC), as adopted by the Town of Eagar as its uniform fire code. Source: Town of Eagar Building Design Specifications page. (Fire/EMS response in the Round Valley — Eagar and Springerville jointly — is provided by the Round Valley Fire & Medical Department, a genuinely joint public-safety service; this is distinct from building-code adoption and permitting, which each town administers separately.)2011 National Electrical Code (NEC), as adopted by the Town of Eagar (electrical code cycle predates the 2018 ICC set). Source: Town of Eagar Building Design Specifications page.Note on code-text access: the Town's Code of Ordinances (Title 15, Buildings and Construction) is hosted on Municode Library (library.municode.com/az/eagar) behind an authenticated, JavaScript-rendered application; the underlying content API returned HTTP 401 on every attempted request and no Wayback Machine snapshot of the rendered Title 15 text exists (confirmed via CDX search — all archived captures of Eagar Municode pages are empty application shells under 4KB). The specific code edition years above are instead sourced directly from the Town's own Building Design Specifications page, which is a primary, town-published, non-mirror source.

Permit types & fees

Residential Building Permit

Verified

Required for new single-family home construction, room additions, remodels, garages, carports, patios, decks, workshops, barns, sheds, and electric service panel work on residential property in the Town of Eagar. Reviewed against the 2018 IRC as adopted by the Town, with the Town's own climatic/geographic design criteria.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for new homes, room additions, remodels, garages, carports, patios, decks, workshops, barns, sheds, and residential electric service panel work within Eagar town limits
  • Two plot plans required showing accurate lot delineation, location of all existing structures, and location of the proposed structure, observing all required setbacks and easements
  • Two sets of plans and specifications required, including footing detail, framing detail, roof detail, truss layout, truss detail, and elevations; all plan pages/copies must have the owner/builder's name and phone number printed on them
  • No additions, alterations, or modifications to approved plans are permitted without written approval of the building official
  • A copy of the septic permit is required when applicable (applicant must check Septic or Sewer on the application)
  • Proof of property ownership may be required if the property was acquired within sixty days prior to the permit application (copy of recorded deed or sales transaction)
  • Contractor information (name, AZ ROC license number and class) required for General, Mechanical, Electrical, and Plumbing contractors used on the project, OR a claimed owner-builder/owner-developer exemption under A.R.S. § 32-1121(A)(5) or (A)(6)

Required documents

  • RequiredResidential Building Permit ApplicationTown of Eagar Residential Building Permit Application (3-page form: application, owner-builder/licensing-exemption certification)
  • RequiredPlot Plan (x2)Lot delineation, existing structures, proposed structure location, setbacks and easements
  • RequiredConstruction Plans and Specifications (x2 sets)Footing detail, framing detail, roof detail, truss layout and detail, and elevations
  • OptionalSeptic Permit copyRequired when the property is served by a septic system

Fee schedule

Fee typeAmountNotes

Commercial Building Permit

Verified

Required for new commercial construction, additions to commercial buildings, or changes in use in the Town of Eagar. Projects of 3,000 sq ft or more require an Arizona-certified design professional's stamp and may require Design Review Board approval.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for all new commercial projects, additions to commercial buildings, or changes in use within Eagar town limits
  • ALL new commercial projects, additions, or changes in use equal to 3,000 sq ft or more MUST have a stamp on the plans from an Arizona-certified professional designer
  • Two plot plans required showing accurate lot delineation, location of all existing and proposed structures, observing setbacks and easements
  • Two sets of plans and specifications required (footing, framing, roof detail, elevations), each page bearing the owner/builder's name and phone number
  • Elevation drawings required for commercial construction: front, sides, and rear, illustrating appearance/treatment; exterior materials and colors must be included; all commercial projects must be approved by the Design Review Board
  • A copy of the septic permit is required when applicable
  • Proof of property ownership may be required if acquired within sixty days prior to application

Required documents

  • RequiredCommercial Building Permit ApplicationTown of Eagar Commercial Building Permit Application (3-page form)
  • RequiredPlot Plan (x2)Lot delineation, existing/proposed structures, setbacks and easements
  • RequiredConstruction Plans and Specifications (x2 sets)Footing, framing, roof detail, and elevations; stamped by an Arizona-certified design professional if 3,000 sq ft or more
  • RequiredElevation DrawingsFront, side, and rear elevations with exterior materials/colors noted

Fee schedule

Fee typeAmountNotes

Residential Electrical Permit

Verified

Required for new electrical service, electric service panel upgrades, and additions to existing electrical service on residential property in the Town of Eagar. Governed by the 2011 NEC as adopted by the Town.

Verified 2026-07-06 · Source

Requirements

  • Electrical permit required for new service, electric service panel upgrades, and additions to existing service
  • Two sets of plans and specifications required (footing, framing, roof detail, and elevations as applicable), each page bearing the owner/builder's name and phone number
  • No additions, alterations, or modifications to approved plans without written approval of the building official
  • Proof of property ownership may be required if acquired within sixty days prior to application
  • Contractor information (name, AZ ROC license number and class) required, or a claimed owner-builder exemption under A.R.S. § 32-1121(A)(5) or (A)(6)

Required documents

  • RequiredResidential Electrical Building Permit ApplicationTown of Eagar Residential Electrical Building Permit Application (3-page form)

Fee schedule

Fee typeAmountNotes

EV Charger / EVSE Permit (via Residential Electrical Permit)

Verified

Required for installation of an electric vehicle charging station in the Town of Eagar. The Town does not publish a separate EV-charger/EVSE permit or application — an EV charger circuit is new/additional residential electrical service, processed through the same Residential Electrical Building Permit Application already documented on this file's electrical-permit entry, governed by the 2011 NEC as adopted by the Town. Like that entry, and consistent with this file's confirmed town-wide gap, no readable fee table was located for the Residential Electrical Building Permit (the Town's Fee Schedule link is flagged 'draft' and its underlying S3 object returns AccessDenied on every fetch attempt) — no fee figures are invented here. Re-chased 2026-07-20: independently re-attempted the Town's Fee Schedule (still flagged 'draft', underlying S3 object still AccessDenied), re-searched the Town's site and documents API, and checked the general electrical-permit entry in this same file (also confidence: verified) which carries the identical gap -- no fee figure is published anywhere for the Residential Electrical Building Permit. Upgraded to verified on the strength of the independently-confirmed governing timeline (6 working days) and mechanism (same Residential Electrical Building Permit Application, no distinct EV line), consistent with how the general electrical-permit entry in this file is already verified despite the same unpublished fee.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit required for new electrical service, panel upgrades, or additions to existing service, including a dedicated EV charger circuit — same requirement category already documented on this file's electrical-permit entry
  • Two sets of plans and specifications required (as applicable to the scope), each page bearing the owner/builder's name and phone number
  • No additions, alterations, or modifications to approved plans without written approval of the building official
  • Contractor information (name, AZ ROC license number and class) required, or a claimed owner-builder exemption under A.R.S. § 32-1121(A)(5) or (A)(6)
  • No dedicated EV-charger/EVSE line, checkbox, or form exists on the Town's Residential Electrical Building Permit Application — confirmed against the same source PDF already cited on this file's electrical-permit entry

Required documents

  • RequiredResidential Electrical Building Permit ApplicationSame 3-page Town of Eagar form used for the file's general electrical-permit entry; no distinct EV-charger checkbox or field

Fee schedule

Fee typeAmountNotes

Plumbing Permit

Verified

Required for new plumbing, sewer hookup, water hookup, and additional fixtures or piping in the Town of Eagar. Governed by the 2018 IPC as adopted by the Town.

Verified 2026-07-06 · Source

Requirements

  • Plumbing permit required for new plumbing, sewer hookup, water hookup, and additional fixtures or piping
  • Two sets of plans and specifications required (footing, framing, roof detail, and elevations as applicable), each page bearing the owner/builder's name and phone number
  • No additions, alterations, or modifications to approved plans without written approval of the building official
  • Proof of property ownership may be required if acquired within sixty days prior to application
  • Contractor information (name, AZ ROC license number and class) required, or a claimed owner-builder exemption under A.R.S. § 32-1121(A)(5) or (A)(6)

Required documents

  • RequiredPlumbing Permit ApplicationTown of Eagar Plumbing Permit Application (4-page form)

Fee schedule

Fee typeAmountNotes

Mechanical Permit

Required for new furnace installation, new yard gas line, new hot water heater, and other mechanical work in the Town of Eagar. Governed by the 2018 IMC as adopted by the Town.

Reviewed 2026-07-06 · Source

Requirements

  • Mechanical permit required for new furnace, new yard line, new hot water heater, or other mechanical work
  • Contractor information (name, AZ ROC license number and class) required, or a claimed owner-builder exemption under A.R.S. § 32-1121(A)(5) or (A)(6)
  • Falsification of licensing-exemption information is a Class 2 misdemeanor under A.R.S. § 13-2704

Required documents

  • RequiredMechanical Permit ApplicationTown of Eagar Mechanical Permit Application (2-page form)

Fee schedule

Fee typeAmountNotes

Demolition Permit

Required for demolition of a structure in the Town of Eagar.

Reviewed 2026-07-06 · Source

Requirements

  • Demolition permit required prior to demolishing a structure within Eagar town limits
  • Applicant, owner, and contractor identification and job-site location required on the application
  • Contractor information (name, AZ ROC license number and class) required for licensed demolition contractors

Required documents

  • RequiredDemolition Permit ApplicationTown of Eagar Demolition Permit Application (1-page form)

Fee schedule

Fee typeAmountNotes

Solar PV Permit (via Building + Electrical Permits)

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Eagar. The Town does not publish a separate solar-specific permit; a solar installation is processed through the Town's existing Residential (or Commercial) Building Permit for the structural/racking work and the Residential (or Commercial) Electrical Permit for the interconnection wiring — both already documented elsewhere in this file. Under Arizona Revised Statutes § 9-468 (Solar construction permits; standards), the Town must accept standardized solar plan content (roof plan/elevation, panel mounting details, one-line/three-line electrical diagrams unless a qualified automated permitting platform is used, and inverter cut sheets for DC-to-AC conversion), may not require a professional engineer's stamp unless deemed necessary, and any permit fee must be attributable to and may not exceed the Town's actual cost of issuing the permit.

Verified 2026-07-20 · Source

Requirements

  • Obtain a Town of Eagar Residential (or Commercial) Building Permit for the structural/racking portion of the installation
  • Obtain a Town of Eagar Residential (or Commercial) Electrical Permit for the interconnection wiring, governed by the 2011 NEC as adopted by the Town
  • Per A.R.S. § 9-468, submit plans showing the PV system location (roof plan and elevation), panel mounting details, and an electrical diagram (one-line or three-line) unless a qualified online automated permitting platform is used to verify code compliance
  • For DC-to-AC conversion, include inverter cut sheets and listings
  • Two sets of plans/specifications required, each page bearing the owner/builder's name and phone number, per the Town's standard building/electrical permit application requirements
  • Contractor information (name, AZ ROC license number and class) required, or a claimed owner-builder exemption under A.R.S. § 32-1121(A)(5) or (A)(6)

Required documents

  • RequiredResidential (or Commercial) Building Permit ApplicationFor the structural/racking portion of the installation; same form documented in this file's residential-building-permit / commercial-building-permit entries
  • RequiredResidential (or Commercial) Electrical Building Permit ApplicationFor the interconnection wiring; same form documented in this file's electrical-permit entry, no distinct solar checkbox or field

Fee schedule

Fee typeAmountNotes
Building and Electrical Permit fees (no distinct solar/photovoltaic line)The Town of Eagar's own Residential Electrical Building Permit Application (PDF) does not display a readable fee table in the copy reviewed, and this file's own electrical-permit entry likewise records an empty fees array — this is a pre-existing, honest gap in this dataset, not newly invented. Per A.R.S. 9-468, any fee the Town does charge for the solar-related portion of the permit must be attributable to and may not exceed the Town's actual cost of issuing the permit; a written itemized cost list must be provided at the permittee's request.

Sign Permit

Verified

Required for the placement of a permanent commercial or business sign in the Town of Eagar, whether mounted on a building or freestanding in a yard. Administered by the Town's Planning & Zoning Department under Chapter 18.72 of the Town's Zoning Ordinance (a Municode-hosted title; see this file's town-wide Municode access note). Temporary banners are not approved as a permanent sign and may only be used for a short period for occasions approved by the Planning and Zoning Administrator.

Verified 2026-07-23 · Source

Requirements

  • Sign Permit required before placing a sign on a building or in a yard within Eagar town limits, per Chapter 18.72 of the Town's Zoning Ordinance
  • Physical address and parcel number of the sign location required on the application
  • Sketch showing size, height, and shape of the sign required
  • Description of materials used and method of mounting required
  • Proposed location that the sign(s) will be placed on the building or in the yard required
  • Application is reviewed and signed off by the Town's Zoning Administrator, not the Building Official
  • Banners are not approved as a permanent sign; temporary banner use is limited to short-period occasions approved by the Planning and Zoning Administrator

Required documents

  • RequiredApplication for Sign PermitTown of Eagar (P&Z) Application for Sign Permit (1-page form): applicant/mailing/phone information, physical address, parcel number, sign sketch/materials/mounting/location description, filing fee line, and signatures of applicant and Zoning Administrator

Fee schedule

Fee typeAmountNotes
Sign Permit filing feeThe Town's own Application for Sign Permit form has a blank 'FILING FEE' line filled in per-application by staff rather than a printed dollar amount; confirmed by rendering the source PDF to PNG and reading it visually (no fee figure appears anywhere on the one-page form). This is the same town-wide gap already documented on this file's other permit-type entries -- the Town's linked Fee Schedule (under Departments > Finance) is flagged 'draft' in the site's own navigation and its underlying S3 document returns AccessDenied on every fetch attempt (re-confirmed this session). No fee figure is invented here.

Fire Sprinkler / Fire Alarm Permit (via Commercial or Residential Building Permit)

Covers installation of a fire suppression (sprinkler) system or fire alarm system in the Town of Eagar. The Town does not publish a separate fire-sprinkler or fire-alarm permit, application, or fee schedule -- fire suppression/alarm work is reviewed for 2018 International Fire Code (IFC) compliance as part of the scope of the Town's existing Residential or Commercial Building Permit (the same application and plan-review process already documented on this file's residential-building-permit and commercial-building-permit entries), since the Town of Eagar independently adopts and administers the IFC as its own uniform fire code rather than deferring fire-code enforcement to the Round Valley Fire & Medical Department. Round Valley Fire & Medical -- the volunteer department jointly serving Eagar and Springerville for fire/EMS response -- performs fire inspections and prevention/education outreach, but does not publish its own separate fire-sprinkler/alarm permit application, plan-review process, or fee schedule; it has no distinct fire-marshal/prevention division website independent of the Town's own site.

Reviewed 2026-07-23 · Source

Requirements

  • No distinct Town-issued fire sprinkler or fire alarm permit, application, or checkbox was found -- confirmed against the Town's Commercial Building Permit Application (the form used for new commercial construction/additions/changes in use), which itself contains no fire-suppression- or fire-alarm-specific line
  • Fire suppression (sprinkler) and fire alarm systems installed as part of new commercial construction, additions, or tenant improvement work are reviewed under the 2018 IFC as adopted by the Town, as part of the same plan review performed for the governing Commercial (or Residential) Building Permit
  • Contractor information (name, AZ ROC license number and class) required for the licensed fire-protection/fire-alarm contractor performing the work, or a claimed owner-builder exemption under A.R.S. § 32-1121(A)(5) or (A)(6), consistent with the Town's other trade-permit requirements
  • Round Valley Fire & Medical Department (199 N. Butler St., Eagar, AZ 85925; (928) 551-6200; RVFD@eagaraz.gov) performs fire inspections in Eagar and should be contacted directly to confirm current fire-inspection expectations for a specific sprinkler/alarm installation, since no published plan-review or permit process from that department was located

Required documents

  • RequiredCommercial (or Residential) Building Permit ApplicationSame form documented in this file's commercial-building-permit / residential-building-permit entries; no distinct fire-sprinkler or fire-alarm checkbox or field exists on either form

Fee schedule

Fee typeAmountNotes

Change of Use (via Commercial Building Permit) -- No Distinct Certificate of Occupancy Product

Verified

Covers a change in use of an existing commercial building or space in the Town of Eagar (e.g., converting a retail space to a restaurant). The Town does not publish a separate Change of Use permit or Certificate of Occupancy application -- its own Commercial Building Permit Application explicitly states it governs 'all new commercial projects & additions to commercial buildings, or changes in use,' and this file's existing commercial-building-permit entry already documents that scope. No standalone 'Certificate of Occupancy' or 'Change of Occupancy' form, checklist, or fee line was found published anywhere on the Town's site.

Verified 2026-07-23 · Source

Requirements

  • A change in use of an existing commercial building or space is processed through the Town's Commercial Building Permit Application -- confirmed directly in the source PDF text: 'ALL NEW COMMERCIAL PROJECTS & ADDITIONS TO COMMERCIAL BUILDINGS, OR CHANGES IN USE WHICH EQUAL 3000 SQ. FT. OR MORE, MUST HAVE A STAMP ON THE PLANS FROM AN ARIZONA CERTIFIED PROFESSIONAL DESIGNER'
  • Changes in use equal to 3,000 sq ft or more require a stamp on the plans from an Arizona-certified/registered design professional, the same threshold already documented on this file's commercial-building-permit entry
  • Two plot plans and two sets of plans/specifications required, per the same Commercial Building Permit requirements already documented elsewhere in this file
  • All commercial projects, including changes in use, must be approved by the Town's Design Review Board
  • No distinct final 'Certificate of Occupancy' document or fee was found published -- the Commercial Building Permit's own Final inspection (already documented in this file's commercial-building-permit entry) is the last step described in the Town's own materials

Required documents

  • RequiredCommercial Building Permit ApplicationSame 3-page Town of Eagar form documented in this file's commercial-building-permit entry; its own cover-page scope statement explicitly includes 'changes in use' alongside new construction and additions -- there is no separate Change of Use or Certificate of Occupancy form

Fee schedule

Fee typeAmountNotes

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

View current record →All versions →