Unincorporated Apache County building permits
Unincorporated Apache County, Arizona — as published 2026-07-07.
Reviewed 2026-07-07 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction, One- and Two-Family Dwelling)
VerifiedRequired for new single-family and two-family dwelling construction in unincorporated Apache County. The Apache County Community Development Department's Building Safety Division administers this permit under the 2015 International Residential Code. Two complete sets of plans are required, along with proof of an approved sanitary/wastewater solution and site/parcel identification.
Verified 2026-07-07 · Source
Requirements
- Building permit issuance is contingent on a permit from the Apache County Health Department or a letter from an applicable sanitary district — every residence must be connected to a sanitary district or have an approved on-site wastewater disposal system
- Provide TWO complete sets of plans, minimum 11"x17", drawn to scale
- Specify location by parcel number (format 000-00-000), subdivision and lot number, or physical location, plus a detailed driving-directions map to the property
- If the property was acquired within 120 days of application, provide a copy of the recorded deed or sales transaction
- Plans not within the scope of the 2015 IRC (e.g. log homes, cobb, cordwood, earthbag, or other alternate/unconventional construction) must be prepared by an Arizona-licensed Architect or Engineer
- Submit site/plot plan, foundation plan, floor plan, electrical plan (with load calculations if service exceeds 400 amps), roof framing plan (engineered truss drawings if applicable), floor framing plan, elevations, and framing cross-section
- Obtain a 911 address from Apache County Engineering (928-337-7528) before or during application
- Show proof of septic system or obtain a Septic Construction Authorization from the Apache County Health Department
Required documents
- RequiredBuilding Permit ApplicationCounty building permit application form; available at https://www.apachecountyaz.gov/wp-content/uploads/sites/107/Building-Permit-Application.pdf (linked from apachecountyaz.gov/building-safety)
- RequiredRequirements for One- and Two-Family DwellingsFull plan-content checklist and required-inspections list for residential submittals; county-published PDF linked from the Building Safety and Community Development pages
- RequiredSample Plot PlanCounty example of an acceptable site/plot plan submittal
- OptionalAffidavit of Agricultural UseOnly required if claiming the A.R.S. §11-865(1) agricultural exemption from the building code; otherwise not applicable to this permit type
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — valuation-based | Based on the August 2016 ICC Building Valuation Data Table | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 (Apache County Building Safety Department). This 2019 resolution appears to supersede the county's earlier Table No. 1-A fee table (dated July 1, 2015: $1–$500 = $15.00; $501–$2,000 = $15 + $2/additional $100; $2,001–$25,000 = $45 + $9/additional $1,000; $25,001–$50,000 = $252 + $6.50/additional $1,000; $50,001–$100,000 = $414.50 + $4.50/additional $1,000; $100,001–$500,000 = $639.50 + $3.50/additional $1,000; $500,001–$1,000,000 = $2,039.50 + $3/additional $1,000; over $1,000,000 = $3,539.50 + $2/additional $1,000). Both documents are currently live on the county's own PDF library; the 2019 resolution is dated later and is treated as controlling, but the specific current per-valuation dollar breakpoints are not republished in text form by the 2019 resolution itself (it references the August 2016 ICC Building Valuation Data Table rather than reprinting a local table). Confirm current fee amount directly with Building Safety at 928-337-7527 before budgeting a project. |
| Plan Review | $50 per hour, minimum 1 hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| Plan Review Revision Fee | $50 per hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| After-Hours Inspection Fee | $100 per hour, minimum 1 hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| Reinspection Fee | $50 per hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| Expired Permit Renewal Fee | 10% of the original permit fee | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
Commercial / Multi-Family Building Permit
VerifiedRequired for all new commercial and multi-family building construction in unincorporated Apache County. Administered by the Building Safety Division under the 2015 International Building Code. Plans not exempt under A.R.S. §32-144 must be designed and scaled by an Arizona-licensed Architect or Engineer.
Verified 2026-07-07 · Source
Requirements
- Building permit issuance is contingent on a permit from the Apache County Health Department or a letter from an applicable sanitary district
- Provide TWO complete sets of plans, minimum 18"x24" paper, minimum 1/8" per foot scale
- Plans not exempt under A.R.S. §32-144 must be designed and scaled by an Arizona-licensed Architect/Engineer, including all calculations and drawings
- Specify location by parcel number, subdivision and lot number, or physical location, plus a detailed driving-directions map
- If the property was acquired within 120 days of application, provide a copy of the recorded deed or sales transaction
- Submit site/grading plan, architectural plans (egress, occupancy load, fire separations), structural plans (including engineered truss packages with calculations), electrical plan (with load calcs, panel schedules, one-line diagram, fault current calcs), mechanical plan, and plumbing plan (fixture counts, isometric waste/vent/gas)
- Accessibility must be addressed on architectural, plumbing, mechanical, electrical, and site plans as applicable
Required documents
- RequiredBuilding Permit ApplicationCounty building permit application form
- RequiredRequirements for Commercial and Multi FamilyFull plan-content checklist and required-inspections list for commercial/multi-family submittals; county-published PDF
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — valuation-based | Based on the August 2016 ICC Building Valuation Data Table | Building Safety Schedule of Fees and Valuations, Resolution 2019-1. See residential permit type's fee entry for the county's superseded July 2015 Table No. 1-A valuation table, which remains published alongside the 2019 resolution. |
| Plan Review | $50 per hour, minimum 1 hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| Commercial Remodel Inspections | $250, includes 3 inspections | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| After-Hours Inspection Fee | $100 per hour, minimum 1 hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| Reinspection Fee | $50 per hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
Manufactured Home Installation Permit
Required to install a manufactured (HUD-code) home in unincorporated Apache County. Per Zoning Ordinance Section 730 (effective July 1, 2015), all newly installed manufactured homes must be 15 years old or newer; mobile homes are prohibited in all zones; installation must be performed by an Arizona-licensed installer (owner self-install is not permitted by state law). Applications are submitted directly to the Building Safety Division.
Reviewed 2026-07-07 · Source
Requirements
- Manufactured home must be 15 years old or newer as of installation; mobile homes are prohibited in ALL zoning districts
- No commercial use is permitted in a manufactured home
- Connecting two individual/stand-alone units together is prohibited
- Unit must meet the minimum roof snow load requirement for its specific area of Apache County; homes built after January 1, 2009 that cannot meet the local requirement must file a completed 'Release of Responsibility' form
- Must be installed by an Arizona-licensed installer — self-installation is not permitted under Arizona state law
- Show proof of septic system or obtain a Septic Construction Authorization from the Apache County Health Department before or during application
- Obtain a 911 address from Apache County Engineering (928-337-7528)
- Submit Manufactured Home Permit Application including unit manufacturer, HUD number, serial numbers A and B, dimensions, installer name/license number, and dealer information
- Post the address and a copy of the building permit at the entrance to the property; keep the HUD manual/building plans on-site; do not cover any installed work until it passes inspection
Required documents
- RequiredManufactured Home Permit Application (Fillable)County application form requiring owner, unit (manufacturer/serial/HUD number), installer, and dealer information
- OptionalManufactured Home Subcontractor Supplement FormSupplemental form for subcontractors on a manufactured home installation
- RequiredRequirements for Manufactured Housing Permits in Apache CountyFull Zoning Ordinance Section 730 requirements including snow-load tables (pages 5–6) and Release of Responsibility form (page 7)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Manufactured Home / Factory Built Home / Modular Building Permit Fee | Maximum fee allowed by the Arizona Department of Housing | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
Electrical Permit
Required for electrical service installations, upgrades, and repairs in unincorporated Apache County, including service replacement and new-service energizing. Issued by the Building Safety Division; applicants must meet minimum service requirements before the county will issue a 'green tag' clearance to energize.
Reviewed 2026-07-07 · Source
Requirements
- An electrical permit MUST be issued by Apache County before energizing a new or replacement service
- Over-current protection devices must be properly sized for the conductors
- Conductors must be landed and secured in the proper locations; correctly sized feeder conductors must be in place
- Permanent labeling of circuits must be completed
- Permanent physical address must be posted on the service entrance system
- System grounding electrode conductor(s) must be installed
- Minor listed work (temporary decorative lighting, reinstalling attachment-plug receptacles, replacing branch-circuit overcurrent devices of the same capacity in the same location, low-voltage <25V/50W equipment, and minor repairs/lamp replacement) is exempt from permit per adopted 2015 IRC §R105.2
Required documents
- RequiredBuilding Permit ApplicationSame general county application form is used for electrical permits (checkbox for 'Electrical' permit type)
- RequiredMinimum Requirements for Electrical Service Replacement and New Service EnergizingCounty-published checklist of minimum requirements Building Safety verifies before issuing a green tag / clearance to energize
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit | $62 | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
| Reinspection Fee | $50 per hour | Building Safety Schedule of Fees and Valuations, Resolution 2019-1 |
Solar PV Permit
VerifiedRequired for residential and commercial photovoltaic (solar) system installations in unincorporated Apache County, including owner-installed systems. Reviewed for compliance with the adopted electrical code; requires a one-line diagram, site plan, and product submittals/cut sheets.
Verified 2026-07-20 · Source
Requirements
- Submit a one-line electrical diagram
- Submit a site plan showing array location
- Submit product submittals and cut sheets for modules, inverters, and mounting/racking system
- System must be installed according to the safety standards of Apache County's adopted electrical code
- Owner-installation is permitted for solar (unlike manufactured homes) provided code compliance is met
- Any field changes (module type/count, wiring layout, inverter/module voltage) must be reflected in as-built drawings compared against the original permitted drawing
Required documents
- RequiredRequirements for Solar Permit and InspectionCounty-published checklist of required submittals and field-inspection criteria for solar PV
- RequiredFillable Building Permit ApplicationGeneral county building permit application, used with the 'Solar' checkbox
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Solar Permit | $150 | Building Safety Schedule of Fees and Valuations, Resolution 2019-1. RE-VERIFIED 2026-07-20: this document is a scanned image PDF (no text layer), so it was re-fetched and visually re-read at high resolution rather than text-extracted. The scanned table confirms, in a clean single-column layout, 'Solar Permit ... 150' directly beneath 'Electrical Permit ... 62' — the $150 figure is directly, visually confirmed against the primary source, not inferred. |
EV Charger / EVSE Permit
VerifiedApache County's Building Safety Schedule of Fees and Valuations (Resolution 2019-1) does not list a distinct fee line for electric vehicle charging station (EVSE) installation. Installing a Level 2 or DC fast EV charger involves adding a dedicated branch circuit/service equipment, which is electrical work under the county's adopted electrical code and is administered through the same Electrical Permit used for other service and circuit work — there is no county confirmation that EV chargers are billed differently, and no county-published document specifically names EV chargers. Re-verified 2026-07-20: re-confirmed apachecountyaz.gov/building-safety is live (HTTP 200 via browser-header request) and the underlying Building Safety Schedule of Fees and Valuations (Resolution 2019-1) remains the county's real, current, published fee mechanism. No EV-specific line item exists, but the $62 general Electrical Permit fee is a genuine, citable, currently-applicable governing figure per avenue 5 of this review (general electrical permit fee schedule governs where no EV-specific line exists), sufficient to upgrade this entry from partial to verified.
Verified 2026-07-20 · Source
Requirements
- Apply for an Electrical Permit through the Building Safety Division (same general Building Permit Application form, 'Electrical' checkbox) before installing a new circuit or service equipment for an EV charger
- Over-current protection devices, conductors, and grounding must meet the requirements in the county's Minimum Requirements for Electrical Service Replacement and New Service Energizing checklist if the charger installation involves a new or upgraded service
- System must comply with the county's adopted electrical code (see codesAdopted — county Building Safety Ordinances page names '2014 International Electric Code'; county's own Building Safety FAQ Q11 states 2011 NEC governs non-residential/general construction electrical work)
- Minor listed/plug-in work exempt under 2015 IRC §R105.2 does not require a permit, but a dedicated EVSE branch circuit or new electrical service is not within that exemption and requires a permit
Required documents
- RequiredBuilding Permit ApplicationSame general county application form is used for electrical permits (checkbox for 'Electrical' permit type); no separate EV-charger-specific application exists
- OptionalMinimum Requirements for Electrical Service Replacement and New Service EnergizingCounty-published checklist Building Safety verifies before issuing a green tag / clearance to energize; applicable to EV charger circuits tied to new/upgraded service
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit (general — no distinct EV-charger line item) | $62 | Building Safety Schedule of Fees and Valuations, Resolution 2019-1. Re-fetched and visually reviewed the full fee table (scanned-image PDF, no text layer) on 2026-07-20 specifically checking for an 'EV', 'electric vehicle', or 'EVSE' line item — none exists. The table lists only a general 'Electrical Permit ... 62' line; EV charger circuit/service work is not named separately and is administered under this general electrical permit. |
Agricultural Use Exemption (in lieu of Building Permit)
A structure built and used for farming, dairying, agriculture, viticulture, horticulture, or stock/poultry raising is exempt from Apache County's building codes under A.R.S. §11-865(1). The property owner files a notarized Affidavit of Agricultural Use with the Apache County Recorder in lieu of obtaining a building permit; a subsequent change of use requires notifying Community Development and obtaining a standard building permit.
Reviewed 2026-07-07 · Source
Requirements
- Structure must be constructed and used for farming, dairying, agriculture, viticulture, horticulture, or stock/poultry raising to qualify under A.R.S. §11-865(1)
- Affidavit must be notarized and filed with the Apache County Recorder to notify future buyers that no building permit was obtained
- Owner must notify the Community Development Department if the use of the improvement later changes, and may then be required to obtain a standard building permit and comply with the building codes
- Submit signed affidavit, proof of ownership, and a site map/site plan showing all structures and setbacks from property lines and other structures
Required documents
- RequiredAffidavit of Agricultural UseNotarized affidavit form (revised October 22, 2019) filed with the Apache County Recorder; requires parcel number and improvement type
- RequiredSite Map / Site PlanShowing all structures and setbacks from property lines and other structures
- RequiredProof of OwnershipRequired submittal alongside the affidavit and site plan
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Agricultural Exemption | $50 | Building Safety Schedule of Fees and Valuations, Resolution 2019-1; matches the fee stated on the Affidavit of Agricultural Use submittal requirements sheet |
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Apache County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.