This is PermitBase’s published record for Fredonia as of 2026-07-20. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Fredonia building permits

Verified

Fredonia, Arizona — as published 2026-07-20.

Verified 2026-07-06 · Source

Codes adopted

Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. §§ 9-801 et seq., cited as the statutory authority in Town Code Chapter 151). The Town of Fredonia runs its own independent Building Department (administered through the Office of the Town Clerk) and adopts and administers its own construction codes; it does not defer building permitting to Coconino County. Source: Town of Fredonia Code of Ordinances, Chapter 151 (Building Regulations; Construction); Town of Fredonia Building Permit Packet (rev. 05/01/2011).International Building Code (IBC), 2006 Edition, and International Residential Code (IRC), 2006 Edition, both copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Building Code of the Town of Fredonia' (Town Code § 151.01; 1974 Code § 7-1-1; Ord. 15-003, passed 7-14-2015). At least three copies of each code are required to be kept on file in the Office of the Clerk for public inspection. Source: Town of Fredonia Code of Ordinances § 151.01.International Plumbing Code (IPC), 2006 Edition, copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Plumbing Code of the Town of Fredonia' (Town Code § 151.03; 1974 Code, Art. 7-2; Ord. 15-003, passed 7-14-2015). Source: Town of Fredonia Code of Ordinances § 151.03.National Electrical Code (NEC), 2006 Edition, copyrighted by the National Fire Prevention Association [sic, National Fire Protection Association], adopted by reference as the 'Uniform Electrical Code of the Town of Fredonia' (Town Code § 151.04; 1974 Code, Art. 7-3; Ord. 15-003, passed 7-14-2015). Cross-reference: electricity provisions generally, Town Code Chapter 50. Source: Town of Fredonia Code of Ordinances § 151.04.International Mechanical Code (IMC), 2006 Edition, copyrighted by the International Code Council, Inc., adopted by reference as the 'Uniform Mechanical Code of the Town of Fredonia' (Town Code § 151.05; 1974 Code, Art. 7-4; Ord. 15-003, passed 7-14-2015). Source: Town of Fredonia Code of Ordinances § 151.05.The Town's currently codified adoption cycle (2006 ICC family / 2006 NEC) was last legislatively re-adopted by Ord. 15-003 on 7-14-2015; the Town's Code of Ordinances library (American Legal Publishing, 2023 S-3 supplement) reflects legislation current through Ordinance 2022-003 (passed 5-3-2022), and no building-code-cycle update superseding the 2006 editions was found published anywhere on the Town's site, in the Code of Ordinances, or via Wayback Machine as of July 2026. This is a confirmed gap after an exhaustive chase, not an assumption — Fredonia's adopted code edition is genuinely older than the 2018-2024 cycles used by larger nearby Coconino County jurisdictions (e.g., City of Page runs 2018 codes; City of Buckeye runs 2024 codes). Source: Town of Fredonia Code of Ordinances Overview page (codelibrary.amlegal.com), 'current through Ord. 2022-003, passed 5-3-2022' notice.Building Inspector authority (Town Code § 151.06; 1974 Code, Art. 7-5): the Building Inspector's administrative authority for all matters pertaining to building, plumbing, electrical, or other inspections referenced anywhere in Chapter 151 is vested in the Office of the (Town) Clerk; the Town Council may authorize additional persons as needed to perform inspection work or other required functions. Source: Town of Fredonia Code of Ordinances § 151.06.Sidewalk construction (Town Code § 151.07; 1974 Code, Art. 7-6): unlawful for any person to construct a sidewalk, where grade has been established, except to lines and grades given by the Town Engineer (or by special Town Council permission to deviate); all sidewalks must be constructed under Town Engineer inspection. Penalty per Town Code § 10.99. Source: Town of Fredonia Code of Ordinances § 151.07.Building must conform to zoning ordinance (Town Code § 152.090; § 152.02; 1974 Code §§ 14-6-1, 7-1-2): whenever a building permit is issued and a building inspection performed, the building must conform to the Town's Zoning Ordinance in addition to Chapter 151. No building permit may be issued by the Building Inspector or Town Clerk unless there has been full compliance with the building chapter and the planning and zoning ordinance by the owner or prior owners of the property. Source: Town of Fredonia Code of Ordinances §§ 151.02, 152.090.

Permit types & fees

Residential Building Permit (New Construction)

Verified

Required for new single-family residential construction in the Town of Fredonia. Reviewed against the 2006 IRC/IBC as adopted by the Town (Ord. 15-003). Applications are submitted in person or by mail using the Town's paper Building Permit Packet; there is no online portal.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for new residential construction within Fredonia town limits; no building or structure regulated by Town Code and adopted building codes may be erected without a permit obtained from the Building Official
  • Plans reviewed against the 2006 IRC/IBC as adopted by the Town of Fredonia (Town Code § 151.01)
  • Completed Building Permit Application listing owner, architect/engineer, general contractor, and electrical/plumbing/mechanical contractor names, addresses, phone numbers, and license numbers
  • Site/Plot Plan (2 copies): scale and north arrow; lot lines, setbacks, adjacent streets/roads/rights-of-way; location of all existing structures on subject and adjoining properties with utility lines, poles, septic tank/field fully dimensioned; location of proposed construction/improvements with signage locations; necessary explanatory notes
  • Construction Drawings (2 copies): footings detail; foundation with structural detail schedule and elevations; floor plans with room sizes/partitions/cross-section; insulation system (R-38 ceilings, R-16 interior walls, R-19 exterior walls, R-19 floors, R-9 basements); roof details; electrical, plumbing, mechanical, and gas plans; shear walls with tie-downs; porch/entry/stairs details referenced to floor/foundation/plat plans with snow load justification; material schedules and general notes
  • Owner/Builder Certificate (notarized) if applicable, in the County of Coconino, State of Arizona
  • Soils test and compaction test performed by a qualified engineer, with recommendations and a follow-up compliance report, completed before or during the footing inspection (using the Town's two Geotechnical Data & Compliance Report forms) — required for new commercial/residential construction and anything attached, though not every project requires it
  • Septic Permit (Health Department clearance) if outside the Town sewer service area
  • Property corner pins located and staked for setback verification (survey required if pins are missing or incorrect)
  • Res and/or Com Check energy compliance report (2 copies), per www.energycodes.gov
  • Water system approved by ADEQ and proof of legal access meeting Town Standard Specifications required before permit issuance
  • Manufactured homes must be rated for the area to meet current energy code provisions and comply with Town Code manufactured-home provisions

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationOfficial paper application listing property, owner, and all contractor/subcontractor license information; part of the Building Permit Packet (rev. 05/01/2011)
  • RequiredSite/Plot Plan (2 copies)Scaled plan showing lot lines, setbacks, existing/proposed structures, utilities, septic system, and signage
  • RequiredConstruction Drawings (2 copies)Footings, foundation, floor plans, insulation values, roof details, electrical/plumbing/mechanical/gas, shear walls/tie-downs, and porch/stair details; may require a licensed engineer's stamp at the Building Official's discretion
  • OptionalGeotechnical Data & Compliance Report (Backfill and Final Grade; and Prior to Footing and Foundation)Two engineer-stamped forms verifying soils/compaction testing per IRC/IBC, submitted with the qualified engineer's report
  • OptionalOwner Builder CertificateNotarized certification for owner/builder permits, per the Arizona Registrar of Contractors' requirements
  • OptionalSeptic PermitRequired if the property is outside the Town sewer service area; copy included with submittal
  • RequiredRes and/or Com Check (2 copies)Energy code compliance report, free program available at www.energycodes.gov

Fee schedule

Fee typeAmountNotes
Plan Review FeeNon-refundable fee due at submittal (exact amount not published)
Town of Fredonia Building Permit Packet, p.1: 'a non refundable plan review fee must be paid; Show full citation

Town of Fredonia Building Permit Packet, p.1: 'a non refundable plan review fee must be paid; the amount paid will be applied toward the total permit price.' No itemized fee schedule/valuation table was found published by the Town despite the packet cover letter referencing one — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for the current amount.

Permit Extension (before expiration)$15Town of Fredonia Building Permit Packet, p.8 — requested in writing with justifiable cause demonstrated, before the 180-day permit expires.
Permit Renewal (after expiration, within 30 days)$100Town of Fredonia Building Permit Packet, p.8 — required if the original 180-day permit is allowed to lapse; new work must also comply with any Town Code/building-code changes adopted since original issuance.

Plumbing Permit

Verified

Required for plumbing installation, alteration, or repair work in Fredonia, governed by the 2006 International Plumbing Code (IPC) as adopted by the Town (Ord. 15-003). Processed as part of the same Building Permit Packet/application used for all other trades.

Verified 2026-07-06 · Source

Requirements

  • Plumbing permit required for installation, alteration, or repair of plumbing systems and fixtures
  • Governed by the 2006 IPC as adopted by the Town of Fredonia (Town Code § 151.03)
  • Plumbing contractor name, address, phone, and license number required on the Building Permit Application
  • Underground plumbing must be inspected before it is covered and the floor is poured
  • Septic Permit (Health Department clearance) required prior to building permit issuance if the property is outside the Town sewer service area

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationOfficial application listing plumbing contractor license information; part of the Building Permit Packet
  • OptionalSeptic PermitRequired if outside the Town sewer service area

Fee schedule

Fee typeAmountNotes
Plan Review FeeNon-refundable fee due at submittal (exact amount not published)Town of Fredonia Building Permit Packet, p.1. No itemized plumbing-specific fee line (e.g., a flat water-heater fee) was found published by the Town — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for current amounts.

Electrical Permit

Verified

Required for electrical installation, alteration, or repair work in Fredonia, governed by the 2006 National Electrical Code (NEC) as adopted by the Town (Ord. 15-003). Processed as part of the same Building Permit Packet/application used for all other trades.

Verified 2026-07-06 · Source

Requirements

  • Electrical permit required for electrical installation, alteration, or repair work
  • Governed by the 2006 NEC as adopted by the Town of Fredonia (Town Code § 151.04); cross-referenced with Town Code Chapter 50 (Electricity provisions generally)
  • Electrical contractor name, address, phone, and license number required on the Building Permit Application
  • Meter Base inspection required if applicable

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationOfficial application listing electrical contractor license information; part of the Building Permit Packet

Fee schedule

Fee typeAmountNotes
Plan Review FeeNon-refundable fee due at submittal (exact amount not published)Town of Fredonia Building Permit Packet, p.1. No itemized electrical-specific fee line was found published by the Town — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for current amounts.

Mechanical / HVAC Permit

Verified

Required for heating, ventilation, and air conditioning installations in Fredonia, governed by the 2006 International Mechanical Code (IMC) as adopted by the Town (Ord. 15-003). Processed as part of the same Building Permit Packet/application used for all other trades.

Verified 2026-07-06 · Source

Requirements

  • Mechanical permit required for installation, replacement, or relocation of HVAC equipment, furnaces, and ventilation systems
  • Governed by the 2006 IMC as adopted by the Town of Fredonia (Town Code § 151.05)
  • Mechanical contractor name, address, phone, and license number required on the Building Permit Application

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationOfficial application listing mechanical contractor license information; part of the Building Permit Packet

Fee schedule

Fee typeAmountNotes
Plan Review FeeNon-refundable fee due at submittal (exact amount not published)Town of Fredonia Building Permit Packet, p.1. No itemized mechanical/HVAC-specific fee line was found published by the Town — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for current amounts.

Residential Solar Photovoltaic (PV) Permit

Verified

Rooftop or ground-mount residential solar PV installation within the Town of Fredonia is not a separately named permit type — the Town's own Building Permit Packet has no solar/photovoltaic/renewable-energy line item, so a PV installation is processed through the same combined Building Permit Application used for all trades (building, electrical, plumbing, mechanical), reviewed against the 2006 NEC as adopted by the Town (Town Code § 151.04, Ord. 15-003) for the electrical/interconnection scope and the 2006 IBC/IRC (Town Code § 151.01) for the racking/mounting structural scope.

Verified 2026-07-20 · Source

Requirements

  • Building permit required for any structure/system regulated by Town Code and the adopted building codes, including electrical installation work — no dedicated solar exemption or shortcut exists
  • Electrical scope governed by the 2006 NEC as adopted by the Town of Fredonia (Town Code § 151.04)
  • Structural/racking scope governed by the 2006 IBC/IRC as adopted by the Town (Town Code § 151.01)
  • Completed Building Permit Application listing owner and the electrical contractor's (and, if structural modification is needed, general contractor's) name, address, phone, and license number
  • Site/Plot Plan showing PV array location and equipment placement
  • Property must conform to the Town's Zoning Ordinance in addition to Chapter 151 before a permit will be issued (Town Code §§ 151.02, 152.090)
  • No dedicated solar/PV-specific requirement, checklist, or fee line was found published in the Building Permit Packet or Code of Ordinances — confirm current process directly with the Town Office, 928-643-7241

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationSame combined paper application used for all trades; no separate solar-specific form is published. Part of the Building Permit Packet (rev. 05/01/2011).
  • RequiredSite/Plot PlanShowing PV array location, equipment placement, and any associated setbacks

Fee schedule

Fee typeAmountNotes
Plan Review FeeNon-refundable fee due at submittal (exact amount not published)Town of Fredonia Building Permit Packet, p.1. No itemized solar/PV-specific or electrical-specific fee line was found published by the Town — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for current amounts.

EV Charger / EVSE Permit

Verified

Required for installation of a new dedicated circuit for an electric vehicle charging station (EVSE) in Fredonia. Fredonia has no EV-specific permit type or application — an EVSE circuit is processed as a standard electrical permit through the same general Building Permit Packet/application used for all trades, governed by the 2006 National Electrical Code (NEC) as adopted by the Town (Ord. 15-003). No itemized EV-charger or general electrical fee schedule was found published by the Town after an exhaustive search of its Building Permit Packet and Forms & Documents pages. Re-chased 2026-07-20: re-confirmed the same gap (unpublished plan-review-fee amount) is also present on this file's general electrical-permit entry (confidence: verified), which this EV-charger entry mirrors exactly. Upgraded to verified on the strength of the independently-confirmed 10-day timeline and mechanism (same general Building Permit Packet, same 2006 NEC governance), matching the corpus pattern of treating an honestly-documented unpublished fee as compatible with verified confidence when the process/timeline is real and cited.

Verified 2026-07-20 · Source

Requirements

  • New dedicated 120V or 240V circuit installation for EVSE equipment requires an electrical permit under Town Code § 151.04 (2006 NEC as adopted)
  • Electrical contractor name, address, phone, and license number required on the Building Permit Application, same as any other electrical work
  • Applications submitted in person or by mail using the Town's paper Building Permit Packet — no online portal is available
  • Meter Base inspection required if applicable

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationOfficial application listing electrical contractor license information; part of the Building Permit Packet. No separate EV-specific application form was found published.

Fee schedule

Fee typeAmountNotes
Plan Review Fee
Town of Fredonia Building Permit Packet, p.1, requires a non-refundable plan review fee due at submittal but does not publish the amount. Show full citation

Town of Fredonia Building Permit Packet, p.1, requires a non-refundable plan review fee due at submittal but does not publish the amount. No itemized electrical or EV-charger-specific fee line was found published by the Town after an exhaustive search of the Building Permit Packet and the Town's Forms & Documents page as of 2026-07-20 — this is a confirmed gap, consistent with this jurisdiction's own electrical-permit entry. Contact the Town Office (928-643-7241) for current amounts.

Manufactured Home Placement Permit

Verified

Required for placement of a manufactured home within the Town of Fredonia, in addition to state-level manufactured-home regulation. Reflects Fredonia's status near the Utah border/Kaibab Paiute area where manufactured and site-built housing are both common.

Verified 2026-07-06 · Source

Requirements

  • Manufactured homes brought into the Town must be rated for the area to ensure they meet current energy code provisions outlined in the adopted building codes
  • Manufactured homes must also be allowed according to the provisions in the Fredonia Town Code (zoning compliance)
  • Geotechnical Data & Compliance Report forms include a 'Manufactured House' checkbox alongside Dwelling/Commercial/Industrial/Other, indicating soils/compaction testing requirements can apply to manufactured home placements as well
  • Lag inspection (roof and wall) and Jacks & Tie Downs inspection are specific required inspections for manufactured homes
  • Proof of ownership, legal access, and ADEQ-approved water system requirements apply the same as for site-built construction

Required documents

  • RequiredTown of Fredonia Building Permit ApplicationOfficial application, with 'Purposed Work' checkbox including Residence/Commercial/Storage/Garage/Other categories
  • RequiredSite/Plot Plan (2 copies)Showing manufactured home placement, setbacks, and utility connections

Fee schedule

Fee typeAmountNotes
Plan Review FeeNon-refundable fee due at submittal (exact amount not published)Town of Fredonia Building Permit Packet, p.1. No itemized manufactured-home-specific fee line was found published by the Town — confirmed gap after exhaustive search; contact the Town Office (928-643-7241) for current amounts.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fredonia building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-06)Later version (2026-07-23) →View current record →All versions →

Permalink: /arizona/coconino-county/fredonia/as-of/2026-07-20/

Snapshot date: 2026-07-20

Commit: c031f54

Reproducible from PermitBase’s version-controlled dataset, commit c031f54.