This is PermitBase’s published record for Pinetop-Lakeside as of 2026-08-16. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Pinetop-Lakeside building permits

Verified

Pinetop-Lakeside, Arizona — as published 2026-08-16.

Verified 2026-07-07 · Source

Codes adopted

Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Sections 9-462.01 and 9-463 et seq.). The Town of Pinetop-Lakeside independently adopts and administers its own Building Code (Town Code Chapter 15.04) through its Building & Safety Department (part of the Community Development Department); it does not defer permitting to Navajo County. Source: Pinetop-Lakeside Town Code Section 15.04.010/15.04.020.2024 International Building Code (IBC), together with its supplements, if any, published by the International Code Council, adopted by reference (Town Code Section 15.04.020(B)). Source: Pinetop-Lakeside Town Code Section 15.04.020, current through Ord. 25-481.2024 International Residential Code (IRC), together with its supplements, if any, published by the International Code Council, adopted by reference (Town Code Section 15.04.020(B)). Source: Pinetop-Lakeside Town Code Section 15.04.020.2024 International Mechanical Code (IMC), together with its supplements, if any, published by the International Code Council, adopted by reference (Town Code Section 15.04.020(B)). Source: Pinetop-Lakeside Town Code Section 15.04.020.2024 International Plumbing Code (IPC), together with its supplements, if any, published by the International Code Council, adopted by reference (Town Code Section 15.04.020(B)). Source: Pinetop-Lakeside Town Code Section 15.04.020.2023 National Electrical Code (NEC), together with its supplements, if any, published by the National Fire Protection Association, adopted by reference (Town Code Section 15.04.020(B)) — one edition behind the 2024 ICC family set; the Town Code specifically notes new NEC editions may be adopted from time to time by Town Council resolution. Source: Pinetop-Lakeside Town Code Section 15.04.020.The Town's own live Building Permits web page (pinetoplakesideaz.gov/173/Building-Permits) independently confirms: 'The Town of Pinetop/Lakeside has adopted the 2024 editions of the International Building Codes with the 2023 edition of the National Electrical Code' — consistent with the Municipal Code text. Source: Building Permits | Pinetop-Lakeside, AZ.No standalone International Fuel Gas Code (IFGC), International Fire Code (IFC), International Existing Building Code (IEBC), or International Energy Conservation Code (IECC) adoption citation was found in Town Code Chapter 15.04 (Building Code) or on the Town's Building Permits page as of this research; the Town's own Gas Permit (Town Fee Schedule) is administered under the Building & Safety Department's general permitting authority (Town Code Section 15.04.020 references 'addenda and additions...as apply to the Town'), but no separately cited fuel-gas-code edition was located. Fire-related plan review for multi-family, industrial, and commercial buildings is expressly routed to the applicable Fire District for stamped approval prior to Town permit issuance (Town Code Section 15.04.150), rather than the Town administering its own separately-cited Fire Code chapter. Source: Pinetop-Lakeside Town Code Chapter 15.04 (full chapter reviewed; no IFGC/IFC/IEBC/IECC section found).ADA/Accessibility: Arizonans with Disabilities Act standards and implementing rules (A.R.S. Title 41, Chapter 9, Article 8), including the 'Americans with Disabilities Act Accessibility Guidelines for Buildings and Facilities,' declared a public record by Town Resolution No. 96-426, are adopted and incorporated as an amendment to the International Building Code for both public entities and public accommodations/commercial facilities, applying to new construction and alterations commenced after September 3, 1996. Source: Pinetop-Lakeside Town Code Section 15.04.320 (Addendum and Additions).Manufactured/mobile/modular homes: regulated jointly by the State of Arizona (Arizona Department of Building and Fire Safety, Office of Manufactured Housing) for HUD compliance and installation standards, and by the Town for placement/location permits. As of April 16, 1995, the Building Official may not issue a building/location permit for a mobile/manufactured home unless it bears a HUD compliance decal dated no earlier than June 15, 1976 (or successor HUD standard) and complies with Arizona Department of Building and Fire Safety installation standards (ground-level installation, fully-skirted installation, or installation on a permanent visible foundation). Source: Pinetop-Lakeside Town Code Section 15.04.220 (Mobile and Manufactured Homes).Fire District plan review: all plans and specifications for multi-family dwellings, industrial and commercial buildings (or alterations/additions/conversions thereto) requiring a Town building permit must first be submitted to and stamped approved by the respective Fire District before the Town's Planning and Zoning Department will issue the permit; the Town reserves the right to issue a permit without prior Fire District approval subject to Town Attorney review and Town Council approval. Source: Pinetop-Lakeside Town Code Section 15.04.150.

Permit types & fees

Residential Building Permit (New Construction / Addition / Remodel)

Verified

Required for new single-family residential construction, additions, and remodels within the Town of Pinetop-Lakeside. Reviewed against the 2024 IBC/IRC and Town of Pinetop-Lakeside amendments (Town Code Chapter 15.04). Applications are submitted via the online Civic Review portal (preferred), in person at Town Offices, or by mail.

Verified 2026-07-07 · Source

Requirements

  • Building permit required for new residential construction, additions, and remodels within Town limits, except for the narrow Town Code Section 15.04.130 exemptions (fences/walls, curbs/retaining/planter walls, accessory buildings up to 145 sq ft not used for human occupancy, roof-mounted antennas, and like-for-like maintenance repairs)
  • Two (2) copies of plans and specifications required with every building permit application, including a site or plot plan; one approved copy is returned to the owner (Town Code Section 15.04.140)
  • Approval from the Sanitary District (sewer hook-up) or a Navajo County Health Department permit (septic tank) required as applicable
  • Contractor's statement of Arizona Registrar of Contractors license required
  • Tree Plan required per Town Code Section 17.96.010
  • Projects over $75,000 in valuation require a licensed engineer's or architect's seal on plans; projects $50,000 and over require contractor bonding
  • Undeveloped sites may require a culvert inspection
  • Multi-family, industrial, and commercial buildings (or alterations/additions/conversions) must have plans stamped approved by the applicable Fire District before the Town issues a building permit (Town Code Section 15.04.150)
  • A single blanket building permit is issued per construction project; a nonrefundable Plan Check Fee is charged at plan submittal (Town Code Section 15.04.190)
  • Submit via the online Civic Review portal (app.civicreview.com), in person at Town Offices (325 W White Mountain Boulevard), or by mail to the Community Development Department

Required documents

  • RequiredBuilding Permit ApplicationTown of Pinetop-Lakeside Building Permit Application, submitted through the online Civic Review portal (app.civicreview.com/application/5cae3eb9a45b68001b84f3ec) or in person/by mail at Town Offices
  • RequiredSite/Plot PlanScaled drawing showing lot dimensions and all existing/proposed structures, distances to property lines and between structures, north arrow, street name/address, legal description, water/gas/electric/sewer locations, easements, and topography (contour lines or spot grades). Per the Town's own FAQ definition of a site/plot plan.
  • RequiredConstruction Drawings and Specifications (2 copies)Two sets of plans and specifications per Town Code Section 15.04.140; complex projects (e.g., requiring engineering computations, public buildings) must be prepared by an Arizona-licensed engineer or architect at the Building Official's discretion
  • RequiredSanitary District Approval or County Health Department Septic PermitRequired where a sewer hook-up or septic tank is involved
  • RequiredContractor's Statement of LicenseConfirms the contractor holds a valid Arizona Registrar of Contractors license
  • RequiredTree PlanRequired per Town Code Section 17.96.010
  • OptionalFire District Stamped Plan ApprovalRequired before Town permit issuance for multi-family, industrial, and commercial buildings or qualifying alterations/additions/conversions (Town Code Section 15.04.150)

Fee schedule

Fee typeAmountNotes
Building Permit FeeBased on the Most Current International Code Council Building Valuation Data (published bi-annually), by Type of Construction, per ICC Building Fee Schedule Appendix L; calculated to the nearest $1,000 of valuationTown of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, approved June 4, 2026, effective July 4, 2026), Planning and Development section; Town Code Section 15.04.190/15.04.210
Plan Check Fee30% of the building permit fee (commercial plans reviewed by an outside consulting firm may be billed up to the Town's actual reimbursement cost instead)FY2026-2027 Consolidated Fee Schedule; nonrefundable per Town Code Section 15.04.190
Not Obtaining a Permit (surcharge)50% of the building permit feeFY2026-2027 Consolidated Fee Schedule
Re-inspection Fee$30.00FY2026-2027 Consolidated Fee Schedule (unchanged from FY2025-2026 base)
Revised Commercial Building Plans30% of the original building permit feeFY2026-2027 Consolidated Fee Schedule
Building Permit Transfer Fee$5.00FY2026-2027 Consolidated Fee Schedule
Building Permit Cancellation Fee25% of the original building permit feeFY2026-2027 Consolidated Fee Schedule
Permit Renewal (expired less than 1 year, no changes)50% of the original permit feePer the Town's own FAQ: 'How do I renew my permit? How much does it cost?'
Permit Renewal (expired more than 1 year)100% of the original permit fee (full fee)Per the Town's own FAQ: 'How do I renew my permit? How much does it cost?'

Electrical Permit

Verified

Required for electrical installation, alteration, or repair work in the Town of Pinetop-Lakeside, governed by the 2023 National Electrical Code (NEC) as adopted by the Town (Town Code Chapter 15.04). Flat-fee permit administered by the Building & Safety Department.

Verified 2026-07-07 · Source

Requirements

  • Electrical permit required for electrical installation, alteration, or repair work within Town limits, subject to the same Town Code Section 15.04.130 exemptions (e.g., like-for-like maintenance repairs not involving fixtures/equipment modification)
  • Governed by the 2023 NEC as adopted by the Town of Pinetop-Lakeside (Town Code Section 15.04.020(B))
  • Submit via the online Civic Review portal, in person at Town Offices, or by mail to the Community Development Department

Required documents

  • RequiredBuilding/Electrical Permit ApplicationSubmitted through the Civic Review online portal or in person/by mail at Town Offices, 325 W White Mountain Boulevard, Lakeside, AZ 85929

Fee schedule

Fee typeAmountNotes
Electrical Permit$40.00Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, effective July 4, 2026), Planning and Development section; increased from $30.00 in the FY2022-2023 schedule
Re-inspection Fee (if applicable)$30.00FY2026-2027 Consolidated Fee Schedule

Gas Permit

Verified

Required for gas piping and gas appliance installation, alteration, or repair work in the Town of Pinetop-Lakeside. Flat-fee permit administered by the Building & Safety Department.

Verified 2026-07-07 · Source

Requirements

  • Gas permit required for gas piping and gas-fired appliance installation, alteration, or repair within Town limits
  • Submit via the online Civic Review portal, in person at Town Offices, or by mail to the Community Development Department

Required documents

  • RequiredBuilding/Gas Permit ApplicationSubmitted through the Civic Review online portal or in person/by mail at Town Offices, 325 W White Mountain Boulevard, Lakeside, AZ 85929

Fee schedule

Fee typeAmountNotes
Gas Permit$40.00Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, effective July 4, 2026), Planning and Development section; increased from $25.00 in the FY2022-2023 schedule
Re-inspection Fee (if applicable)$30.00FY2026-2027 Consolidated Fee Schedule

Manufactured, Mobile, or Modular Home Placement Permit

Verified

Required for placement of a manufactured, mobile, or modular home within the Town of Pinetop-Lakeside. Governed by Town Code Section 15.04.220, requiring HUD compliance and Arizona Department of Building and Fire Safety installation-standard compliance in addition to the Town's own placement permit.

Verified 2026-07-07 · Source

Requirements

  • Mobile/manufactured home proposed for installation must bear a decal certifying HUD compliance dated no earlier than June 15, 1976 (or successor HUD standard)
  • As of April 16, 1995, the Building Official shall not issue a building/location permit for a mobile/manufactured home unless it is proven to comply with the HUD-decal standard; this also applies to relocation of any mobile/manufactured home unit within the Town
  • Applicant must demonstrate compliance to the Building Official
  • Must be installed per Arizona Department of Building and Fire Safety, Office of Manufactured Housing standards: ground-level installation, installation of a fully-skirted unit, or installation on a permanent visible foundation
  • A separate 'Foundation only permit' is available if only the foundation is being permitted at that stage
  • Zoning: only permitted in Town neighborhoods zoned MH-4 (10,000 sq ft/unit), MH-6 (6,600 sq ft/unit), or MHP (manufactured home park, seasonal or permanent); only Class A manufactured homes (minimum 24 ft width, minimum 40 ft length, foundation wall) are allowed
  • Fees calculated to the nearest $1,000 of valuation (Town Code Section 15.04.220(F))

Required documents

  • RequiredManufactured/Mobile/Modular Home Placement Permit ApplicationSubmitted through the Civic Review online portal or in person/by mail at Town Offices, including proof of HUD compliance decal and Arizona Department of Building and Fire Safety installation-standard documentation
  • RequiredSite/Plot PlanShowing placement location, zoning district compliance, and foundation/skirting details

Fee schedule

Fee typeAmountNotes
Manufactured, Mobile or Modular Home Placement Fee$300.00Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, effective July 4, 2026), Planning and Development section (unchanged from FY2022-2023 base)
Foundation Only Permit$40.00FY2026-2027 Consolidated Fee Schedule; unchanged from FY2022-2023 base

Sign Permit

Verified

Required for permanent sign installation in the Town of Pinetop-Lakeside, administered by the Community Development Department under Town Code Chapter 17.108 (Sign Regulations), with its own flat-fee table separate from the Building & Safety Department's valuation-based building permit fees.

Verified 2026-07-07 · Source

Requirements

  • Permanent Sign Permit required for sign installation within Town limits, per Town Code Chapter 17.108
  • One sign not larger than 8 square feet in area is generally allowed per site unless a larger sign is authorized by conditional use permit; unless allowed by conditional use permit, the sign must be placed only on the primary structure
  • Illuminated signs require a Permanent Sign Permit with Illumination, which includes the associated electrical permit
  • Temporary signs (banners, portable/A-frame signs) are separately fee-classified from permanent signs
  • Signs must conform to Town of Pinetop-Lakeside sign regulations, Town Code Chapter 17.108

Required documents

  • RequiredSign Permit ApplicationSubmitted through the Civic Review online portal or in person/by mail at Town Offices, 325 W White Mountain Boulevard, Lakeside, AZ 85929

Fee schedule

Fee typeAmountNotes
Permanent Sign Permit$50.00Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, effective July 4, 2026), Planning and Development section; unchanged from FY2022-2023 base
Permanent Sign Permit with Illumination (includes electrical permit)$80.00FY2026-2027 Consolidated Fee Schedule; unchanged from FY2022-2023 base
Temporary Sign — BannerNo ChargeFY2026-2027 Consolidated Fee Schedule
Temporary Sign — Portable (per sign)$30.00FY2026-2027 Consolidated Fee Schedule
Surcharge for Not Obtaining a Sign Permit50% of Sign Permit feeFY2026-2027 Consolidated Fee Schedule
Change of Copy50% of Sign Permit feeFY2026-2027 Consolidated Fee Schedule
Removal of Illegal Temporary Signs (per sign)$10.00FY2026-2027 Consolidated Fee Schedule
Storage Fees (per day)$1.50FY2026-2027 Consolidated Fee Schedule

Residential Solar Photovoltaic (PV) Permit

Verified

Required for installation of residential rooftop or ground-mounted solar photovoltaic systems within the Town of Pinetop-Lakeside. Unlike neighboring Show Low, Pinetop-Lakeside does not publish a dedicated Solar Permit Application — solar installations are billed under the Town's standard Building Permit Fee (valuation-based per the most current ICC Building Valuation Data and ICC Building Fee Schedule Appendix L) for the array/mounting/structural scope, plus the flat Electrical Permit fee for the wiring/interconnection scope. Reviewed against the 2024 IBC/IRC and 2023 NEC as adopted by the Town (Town Code Chapter 15.04).

Verified 2026-07-19 · Source

Requirements

  • Building Permit required for the array mounting/structural scope, submitted via the online Civic Review portal (preferred; app.civicreview.com), in person at Town Offices, or by mail to the Community Development Department
  • Electrical Permit required for the PV wiring/interconnection, under the 2023 NEC as adopted by the Town
  • Governed by the 2024 IBC/IRC as adopted and amended by the Town of Pinetop-Lakeside (Town Code Chapter 15.04)
  • No dedicated Solar Permit Application or expedited solar-specific review track is published by the Town of Pinetop-Lakeside as of 2026-07-19 — solar/PV work is processed as a standard Building + Electrical Permit combination

Required documents

  • RequiredBuilding Permit Application (Civic Review online portal)Used for the array/structural scope since there is no dedicated solar application
  • RequiredElectrical Permit ApplicationCovers the PV system wiring and utility interconnection

Fee schedule

Fee typeAmountNotes
Building Permit Fees (valuation-based)Per the most current ICC Building Valuation Data (published bi-annually) and ICC Building Fee Schedule Appendix LNo solar-specific fee line found; billed under the same valuation-based table as other construction. Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, effective July 4, 2026)
Electrical Permit$40.00Flat fee; no solar-specific electrical fee line found. FY2026-2027 Consolidated Fee Schedule
Plan Check Fee30% of the building permit feeThe Town may collect up to the actual reimbursement cost for commercial building plans reviewed by an outside consulting firm. FY2026-2027 Consolidated Fee Schedule
Re-inspection Fee$30.00FY2026-2027 Consolidated Fee Schedule

EV Charger / EVSE Permit

Verified

The Town of Pinetop-Lakeside has no EV-charger-specific permit type or fee line. An EV charger (EVSE) circuit is electrical installation, alteration, or repair work under the same flat-fee Electrical Permit that governs all other electrical work in Town limits, enforced under the 2023 NEC as adopted by the Town (Town Code Section 15.04.020(B)). No web search of the Town's Building Permits page, FAQ pages, or FY2026-2027 Consolidated Fee Schedule turned up an EV-charger-specific fee line item or expedited process.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit required for the EV charger circuit installation within Town limits, subject to Town Code Section 15.04.130 exemptions (e.g. like-for-like maintenance repairs not involving fixture/equipment modification)
  • Governed by the 2023 NEC as adopted by the Town of Pinetop-Lakeside (Town Code Section 15.04.020(B))
  • Submit via the online Civic Review portal, in person at Town Offices, or by mail to the Community Development Department

Required documents

  • RequiredBuilding/Electrical Permit ApplicationSubmitted through the Civic Review online portal or in person/by mail at Town Offices, 325 W White Mountain Boulevard, Lakeside, AZ 85929; there is no separate EV-charger-specific application form

Fee schedule

Fee typeAmountNotes
Electrical Permit (no EV-specific line item found)$40.00Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, effective July 4, 2026), Planning and Development section — the same flat electrical permit fee used for any other electrical work; no dedicated EV-charger fee is published.
Re-inspection Fee (if applicable)$30.00FY2026-2027 Consolidated Fee Schedule

Commercial Building Permit (New Construction / Alteration / Tenant Improvement)

Verified

Required for new commercial building construction and for alterations, additions, or conversions of existing commercial buildings within the Town of Pinetop-Lakeside, reviewed against the 2024 IBC and Town of Pinetop-Lakeside amendments (Town Code Chapter 15.04). The Town uses the same Building Permit Application and Civic Review portal for commercial as for residential work — no separate commercial-specific application form was found. There is no separate Tenant Improvement (TI) permit type, application, or fee line: interior tenant-improvement/remodel work in an existing commercial space is processed as a standard (valuation-based) Building Permit, the same as new commercial construction. Confirmed by direct review of the Town's Building Permit Application/Civic Review portal, the FY2026-2027 Consolidated Fee Schedule (all fee lines reviewed), the Forms & Documents page, and Town Code Chapter 15.04 (full chapter text reviewed) — none reference a distinct TI process, application, or fee.

Verified 2026-08-01 · Source

Requirements

  • Building permit required for new commercial building construction and for alterations, additions, or conversions of existing commercial buildings within Town limits, except for the narrow Town Code Section 15.04.130 exemptions (fences/walls, curbs/retaining/planter walls, accessory buildings up to 145 sq ft not used for human occupancy, roof-mounted antennas, and like-for-like maintenance repairs)
  • Plans for multi-family, industrial, and commercial buildings (or qualifying alterations, additions, or conversions) must be submitted to and stamped approved by the applicable Fire District BEFORE the Town's Planning and Zoning Department will issue the building permit; the Fire-District-approved plans become part of the Town's permit record (Town Code Section 15.04.150)
  • Two (2) copies of plans and specifications required with every building permit application, including a site or plot plan; one approved copy is returned to the owner (Town Code Section 15.04.140)
  • Projects over $75,000 in valuation require a licensed engineer's or architect's seal on plans; projects $50,000 and over require contractor bonding — these thresholds apply Town-wide, including to commercial projects
  • Public accommodations and commercial facilities must comply with the Arizonans with Disabilities Act standards and the incorporated ADA Accessibility Guidelines for Buildings and Facilities, adopted as an amendment to the IBC (Town Code Section 15.04.320), applying to new construction and alterations commenced after September 3, 1996
  • Contractor's statement of Arizona Registrar of Contractors license required
  • A single blanket building permit is issued per construction project; a nonrefundable Plan Check Fee (30% of the building permit fee) is charged at plan submittal — for commercial plans reviewed by an outside consulting firm, the Town may instead bill up to its actual reimbursement cost (Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule, Resolution 26-1815)
  • New commercial development is also separately subject to Site Plan Review (which incorporates Design Review) under Town Code Title 17 (Zoning), administered by the Planning and Zoning Commission/Community Development Director — a flat $300 fee, distinct from and in addition to the Building Safety Division's building permit fee (Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule, Planning and Development section, Conditional Use Permits/Variances/Zoning Amendments/Site Plan Review Fees)
  • There is no separate Tenant Improvement (TI) permit type, application, or fee schedule published by the Town — interior tenant-improvement/remodel work in an existing commercial space is processed through the same Building Permit Application and valuation-based fee structure as new commercial construction
  • Submit via the online Civic Review portal (app.civicreview.com), in person at Town Offices (325 W White Mountain Boulevard), or by mail to the Community Development Department — the same Building Permit Application is used for commercial and residential submittals

Required documents

  • RequiredBuilding Permit ApplicationTown of Pinetop-Lakeside Building Permit Application, submitted through the online Civic Review portal (app.civicreview.com/application/5cae3eb9a45b68001b84f3ec) or in person/by mail at Town Offices; the same application form is used for commercial and residential submittals — no separate commercial or tenant-improvement application was found
  • RequiredSite/Plot PlanScaled drawing showing lot dimensions and all existing/proposed structures, distances to property lines and between structures, north arrow, street name/address, legal description, water/gas/electric/sewer locations, easements, and topography (contour lines or spot grades)
  • RequiredConstruction Drawings and Specifications (2 copies)Two sets of plans and specifications per Town Code Section 15.04.140; commercial and other complex projects (e.g., requiring engineering computations, public buildings, or valuation over $75,000) must be prepared by an Arizona-licensed engineer or architect
  • RequiredFire District Stamped Plan ApprovalRequired before Town permit issuance for all commercial, industrial, and multi-family buildings or qualifying alterations/additions/conversions (Town Code Section 15.04.150); the approved plans become part of the Town's permit record
  • RequiredContractor's Statement of LicenseConfirms the contractor holds a valid Arizona Registrar of Contractors license

Fee schedule

Fee typeAmountNotes
Building Permit FeeBased on the Most Current International Code Council Building Valuation Data (published bi-annually), by Type of Construction, per ICC Building Fee Schedule Appendix L; calculated to the nearest $1,000 of valuationTown of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, approved June 4, 2026, effective July 4, 2026), Planning and Development section; same valuation-based table used for residential construction — no separate commercial fee table
Plan Check Fee30% of the building permit fee (commercial plans reviewed by an outside consulting firm may instead be billed up to the Town's actual reimbursement cost)FY2026-2027 Consolidated Fee Schedule, verified by direct read of the fee schedule PDF; nonrefundable per Town Code Section 15.04.190
Revised Commercial Building Plans30% of the original building permit feeFY2026-2027 Consolidated Fee Schedule, Planning and Development section — a commercial-specific fee line distinct from the general Building Permit Fee
Not Obtaining a Permit (surcharge)50% of the building permit feeFY2026-2027 Consolidated Fee Schedule
Re-inspection Fee$30.00FY2026-2027 Consolidated Fee Schedule
Building Permit Transfer Fee$5.00FY2026-2027 Consolidated Fee Schedule
Building Permit Cancellation Fee25% of the original building permit feeFY2026-2027 Consolidated Fee Schedule
Site Plan Review (separate Title 17 Zoning process/fee, not part of the Building Permit fee)$300.00
FY2026-2027 Consolidated Fee Schedule, Planning and Development section, 'Conditional Use Permits, Variances, Zoning Amendments and Site Plan Review Fees' table; Show full citation

FY2026-2027 Consolidated Fee Schedule, Planning and Development section, 'Conditional Use Permits, Variances, Zoning Amendments and Site Plan Review Fees' table; administered by the Planning and Zoning Commission/Community Development Director under Town Code Title 17, distinct from the Building Safety Division's building permit process

Fire Sprinkler and Fire Alarm System Permit

The Town of Pinetop-Lakeside adopts no fire code and issues no fire sprinkler or fire alarm permit of its own. Town Code Sec. 15.04.020 adopts the 2024 International Building Code, 2024 International Mechanical Code, 2024 International Residential Code, 2024 International Plumbing Code and 2023 National Electrical Code - with no International Fire Code among them - and the Town's FY2026-2027 Consolidated Fee Schedule carries no fire permit fee line. Fire code enforcement, fire protection system plan review and fire permitting inside Town limits are performed by two independent fire districts depending on where the property sits: the Pinetop Fire District (1845 S. Pine Lake Rd., Pinetop; 928-367-2199) and the Timber Mesa Fire and Medical District, formerly the Lakeside Fire District (3561 E. Deuce of Clubs, Show Low; 928-537-5100). Town Code Sec. 15.04.100.A makes the district's stamped approval a precondition of the Town issuing a construction permit for multi-family, industrial and commercial work.

Reviewed 2026-08-15 · Source

Requirements

  • Town Code Sec. 15.04.100.A: all plans and specifications filed for the construction of multi-family dwellings, industrial and commercial buildings - or any alterations, additions or conversions thereto - which require the issuance of a building permit and are located within the Town must be submitted by the applicant to the respective Fire District and stamped approved PRIOR to the Town Planning and Zoning Department issuing a permit for construction; the Fire District's approved plans are made part of the permit record for the project
  • Town Code Sec. 15.04.100.B: the Town reserves the right to issue a building permit without prior approval of the respective Fire District, subject to review by the Town Attorney and approval by the Town Council
  • The Town's own Building Permits page states that any new construction other than a detached single-family residence which will exceed $75,000 in cost (as determined by the Building Inspector) requires the seal of a licensed engineer or architect and must be approved by the appropriate Fire Department (Pinetop or Lakeside/Timber Mesa)
  • Which district applies depends on the project address - the Town is served by two separate districts and neither the Town nor either district publishes a boundary map keyed to Town limits, so confirm the responsible district with the Town's Building & Safety Department (928-368-8696 ext. 2) before submitting
  • TIMBER MESA DISTRICT ROUTE: all fire sprinkler, fire alarm system, CO2 system and kitchen hood suppression system plans are submitted to the Town of Pinetop-Lakeside Building Department, and the appropriate application plus one set of electronic plans (PDF) or a file-download link is submitted separately to the Timber Mesa Fire and Medical District Fire Prevention and Life Safety Division (928-537-5100). Timber Mesa states plainly: 'Any associated plan review or inspection/permit fees will be invoiced by the Timber Mesa Fire and Medical District and paid directly to the District.'
  • TIMBER MESA SPRINKLER SUBMITTAL MINIMUMS: 2 sets of hard copy plans signed and stamped by a NICET III or IV or an Arizona Design Professional, or 1 PDF copy submitted on digital media; hydraulic calculations (PDF); product specifications (PDF with the specific products highlighted or indicated); and the City or County building permit number, which is required. Review will not be completed until all required information is provided.
  • TIMBER MESA MODIFICATION RULES: an addition or modification involving flexible sprinkler hose to an EXISTING automatic sprinkler system does not require a complete plan submittal provided the system was originally designed with flexible sprinkler hose and the written notification requirements are met; additions or modifications involving paint booths, pipe-schedule designed systems and other special application sprinkler systems always require a complete plan submittal with no exceptions; and there is a limit of ONE 'less than 21 sprinkler head' construction permit per sprinkler system without a complete plan submittal being required
  • TIMBER MESA FIRE PROTECTION UNDERGROUND: fire lines shall be visible during hydrostatic testing - center loading of the pipe is acceptable, but all joints, valves, thrust blocks and fittings shall be visible. The District's fire line inspection covers the supply piping from the inside or outside of the building(s) to the point of connection to the supply water main at the street or to the water main loop; where a remote FDC is installed, the supply piping from the building to the remote FDC is also required to be inspected.
  • PINETOP FIRE DISTRICT ROUTE: the District's Prevention Division issues operational and construction permits; a construction permit allows the applicant to install or modify systems and equipment for new construction and tenant improvement projects, and a permit will not be issued until the submitted plans and specifications have been reviewed, approved and stamped by the Pinetop Fire District
  • PINETOP FIRE DISTRICT SUBMITTAL: 2 sets of hard copy plans signed and stamped by a NICET III or IV or an Arizona Design Professional, or 1 PDF copy; payment according to the District's Fee Schedule; product specifications in hard copy or PDF; and hydraulic calculations for automatic sprinkler systems. The District's applications (Plan Review Application/Fire Sprinkler Permit, Construction Application/Permit, and Plan Review Application/Hood Suppression Permit) are completed and emailed to cberlin@pinetopfire.com.
  • The Pinetop Fire District's own permits page states: 'The Town of Pinetop-Lakeside or Navajo County depending on project location require plan submittal, permitting, and inspections. Contact the respective entity to inquire about their process.' The district permit therefore runs in parallel with, and does not replace, the Town of Pinetop-Lakeside building permit.
  • Pinetop Fire District has adopted and enforces the 2018 International Fire Code with local amendments, and additionally the 2018 International Wildland Urban Interface Code with local amendments (Pinetop Fire District Codes/Amendments page). Timber Mesa Fire and Medical District has adopted and enforces the 2018 International Fire Code with local amendments adopted 9-26-2022 (Timber Mesa Fire Code page).
  • Town Code Chapter 15.20 (Building Alarm Systems) is NOT a fire alarm construction permit - it is a police burglar-alarm user-permit ordinance requiring every building alarm system user, residential or commercial, to obtain an alarm users permit from the Pinetop-Lakeside Police Department/Planning and Zoning Department for each building alarm system, at an initial fee of $25.00 per year (Town Code Secs. 15.20.010 and 15.20.020). It does not authorize the installation of a fire alarm system.

Required documents

  • RequiredPinetop Fire District Plan Review Application / Fire Sprinkler PermitDownloadable from the Pinetop Fire District Permits page; completed and emailed to cberlin@pinetopfire.com with plans, product specifications and hydraulic calculations
  • OptionalPinetop Fire District Construction Application / Permit and Plan Review Application / Hood Suppression PermitThe District's construction permit application and its separate kitchen hood suppression application; both are emailed to cberlin@pinetopfire.com
  • RequiredTimber Mesa Fire and Medical District Fire Sprinkler System Installation or Modification Permit ApplicationSubmitted online at timbermesafire.org; the form requires the City or County building permit number, project location, installer/supervisor, building/business owner, system designer and general contractor with ROC number
  • OptionalTimber Mesa Fire Alarm System and Commercial Hood / Suppression System applicationsThe District's separate online applications for fire alarm system and commercial hood or suppression system installation or modification
  • RequiredTown of Pinetop-Lakeside Building Permit ApplicationFiled with the Town through the Civic Review online portal; Town Code Sec. 15.04.100.A requires the Fire District's stamped approval before the Town issues a construction permit for multi-family, industrial and commercial work

Fee schedule

Fee typeAmountNotes
Fire Alarm & Detection System Plan Review & Inspections - New installation under 5,000 sq. ft.$350
Identical amount in both districts' published fee schedules: Pinetop Fire District Fee Schedule (revised 06-2022), 'Fire Code Plan Reviews and Permits' table, and Timber Mesa Fire Department approved… Show full citation

Identical amount in both districts' published fee schedules: Pinetop Fire District Fee Schedule (revised 06-2022), 'Fire Code Plan Reviews and Permits' table, and Timber Mesa Fire Department approved fee schedule (revised 04-2017), same table. Both PDFs were read as rendered page images (180 dpi) rather than from extracted text.

Fire Alarm & Detection System Plan Review & Inspections - New installation 5,001 sq. ft. and over$400 plus $0.005 per sq. ft.Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa Fire Department fee schedule (rev. 04-2017); both cells read '$400 + $.005 per sq. ft.'
Fire Alarm & Detection System - Modification (including TI), 1-6 devices$100Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Fire Alarm & Detection System - Modification (including TI), 7 or more devices$150Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Automatic Fire Sprinkler System Plan Review & Inspections - New commercial installation under 5,000 sq. ft.$350Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Automatic Fire Sprinkler System Plan Review & Inspections - New commercial installation 5,001 sq. ft. or more$400 plus $0.005 per sq. ft.Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Automatic Fire Sprinkler System - Modification, 1-50 sprinklers$100Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017). Note the threshold differs sharply from neighbouring Arizona fire authorities, which commonly break at 6 or 7 sprinklers.
Automatic Fire Sprinkler System - Modification, 51 or more sprinklers$150Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Automatic Fire Sprinkler System (13D/R/M Residential) - New residential installation$200Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Automatic Fire Sprinkler System (13D/R/M Residential) - Modifications/additions$100Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Alternative Fire-Extinguishing System - New installation (foam, CO2, clean agent, chemical, etc.)$300Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Alternative Fire-Extinguishing System - New installation, commercial cooking (Hood), single system$250Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Fire Pump - New installation and modified$450Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Commercial Development Plan (new and remodel projects)$350 for buildings up to 99,999 sq ft; $600 over 100,000 up to 249,999 sq ft; $1,200 over 250,000 sq ftPinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017). This is the fire district's site/development plan review fee, charged in addition to the individual system permits.
Spray Booths / Dipping Plan Review & Inspections$175 pre-manufactured spray booth; $350 non-pre-manufactured spray boothPinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Fire Department Access (permanent) - new installation not associated with a new project, access gate (each)$100Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Liquid Petroleum Gas and fuel storage plan review and inspection$100 for a 250-500 gallon tank; $150 for a tank of 501 or more gallonsPinetop Fire District Fee Schedule (rev. 06-2022), 'Liquid Pertroleum Gas & Fuel Storage Plan Review & Inspection' (spelling as printed), and Timber Mesa fee schedule (rev. 04-2017)
High-Piled Combustible Storage - Plan Review$100Pinetop Fire District Fee Schedule (rev. 06-2022) and Timber Mesa fee schedule (rev. 04-2017)
Town of Pinetop-Lakeside fire permit feeNone - the Town charges no fire permit fee
The Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, approved June 4, 2026, effective July 4, 2026) contains no fire sprinkler, fire alarm, or fire plan review fee line of any kind. Show full citation

The Town of Pinetop-Lakeside FY2026-2027 Consolidated Fee Schedule (Resolution 26-1815, approved June 4, 2026, effective July 4, 2026) contains no fire sprinkler, fire alarm, or fire plan review fee line of any kind. All 7 pages were checked and the Planning and Development section was read as a 200-dpi rendered page image. Fire fees are invoiced by, and paid directly to, the responsible fire district.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pinetop-Lakeside building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-08-01)Later version (2026-08-25) →View current record →All versions →

Permalink: /arizona/navajo-county/pinetop-lakeside/as-of/2026-08-16/

Snapshot date: 2026-08-16

Commit: 06ff121

Reproducible from PermitBase’s version-controlled dataset, commit 06ff121.