Prescott building permits

Verified

Prescott, Arizona — as published 2026-07-06.

Verified 2026-07-06 · Source

Codes adopted

Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Prescott's Community Development Department (Building Division) independently adopts and administers its own construction codes and Permit Center program; it does not defer permitting to Yavapai County. Source: City of Prescott Permit Center / Building Permits page (prescott-az.gov/permit-center/permit-categories/building-permits/).2024 International Building Code (IBC), as published by the International Code Council, adopted by the City of Prescott with local amendments codified at Prescott City Code Chapter 3, Article 3-1, 3-2, and 3-5. Currently in effect for plan review. Source: City of Prescott Building Permits page, '2024 Codes-Design Criteria' handout (rev. 01/01/2026), and Prescott City Code (codepublishing.com/AZ/Prescott).2024 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with City of Prescott amendments (Prescott City Code Article 3-8). Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026).2024 International Mechanical Code (IMC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IMC Significant Changes handout.2024 International Plumbing Code (IPC), adopted with City of Prescott amendments (Prescott City Code Article 3-6). Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IPC Significant Changes handout.2023 National Electrical Code (NEC), adopted with City of Prescott amendments (Prescott City Code Article 3-7) — one edition behind the 2024 ICC set, matching the standard NFPA 3-year NEC cycle. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2023 NEC Significant Changes handout.2024 International Fuel Gas Code (IFGC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026).2024 International Existing Building Code (IEBC), adopted with City of Prescott amendments. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026); 2024 IEBC Significant Changes handout.2024 International Fire Code (IFC), adopted by reference (Prescott City Code Article 6-1) as the City's uniform fire code, with a dedicated Urban-Wildland Interface amendment (Article 6-2) administered by the Prescott Fire Department. Source: City of Prescott '2024 Codes-Design Criteria' handout; Prescott City Code Article 6-1/6-2.2012 International Energy Conservation Code (IECC), adopted with City of Prescott amendments (Prescott City Code Article 3-18) — the City has NOT moved to a newer IECC edition; energy compliance for the 2024 code cycle is still evaluated under the 2012 IECC Climate Zone 4B tables. Source: City of Prescott '2024 Codes-Design Criteria' handout (rev. 01/01/2026), which explicitly lists '2012 International Energy Conservation Code (IECC)' alongside the otherwise-2024 code set.City of Prescott Administrative Building Code (Prescott City Code Article 3-17) governs permit administration, application processing, plan review, and issuance procedures citywide, overriding the ICC model codes' own administrative chapters where they conflict. Source: Prescott City Code Article 3-17 (codepublishing.com/AZ/Prescott).

Permit types & fees

Residential Building Permit (New Single-Family Residence / Duplex)

Verified

Required for new single-family residence and duplex construction in the City of Prescott. Reviewed against the 2024 IRC and City of Prescott amendments, plus the City's residential design criteria (105 mph wind, Seismic Category C, 18-inch frost depth, 20°F winter design temperature). Applications are submitted through the PrescottPermits.com online portal.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for new single-family residence and duplex construction within Prescott city limits
  • Plans must comply with the 2024 IRC and City of Prescott amendments, and the City's Residential Design Criteria (105 mph wind Exposure C; Seismic Design Category C unless a soils report verifies otherwise; 18-inch frost depth; 20°F winter design temperature; site-specific snow load per ASCE Hazard Tool)
  • Energy compliance evaluated under the 2012 IECC Climate Zone 4B tables (Roof R-49; Wall R-20; Floor R-19; Slab R-10 for 24 in; Window U-factor 0.35, SHGC 0.40); ResCheck documentation required
  • Construction documents, structural calculations, and (where applicable) a soils report and truss calculations with Engineer of Record verification must be submitted
  • Submittal via the PrescottPermits.com online portal, per the New Single Family Residence Checklist (combined 24x36 Plans file plus 8.5x11 Supporting Documents file)
  • Additional Engineering, Right-of-Way, Fire, or property-specific (floodplain/WUI/Historic District/Airport District) requirements may apply and must be checked before submittal

Required documents

  • RequiredNew Single Family Residence ChecklistCity of Prescott submittal checklist requiring a combined 'PLANS' file (cover sheet, site plan, floor/foundation/framing plans, cross-sections, elevations, energy compliance, electrical/mechanical/plumbing plans) and a combined 'SUPPORT DOCS' file (structural calculations, truss calculations/layout, soils report, ResCheck, Manual J/S/D, manufacturer installation instructions, ESRs, special inspection forms)
  • RequiredSite/Plot PlanParcel lot lines and address, parcel square footage, setbacks (front/rear/side), existing structures/fences/retaining walls/utilities/easements, and location/size of proposed structure with distances from lot lines and other structures
  • RequiredStructural Plan and CalculationsSealed structural design; truss calculations and layout must include verification of Engineer of Record review
  • RequiredResCheck / Manual J, S, DEnergy code compliance documentation and HVAC design calculations

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on ValuationTotal Building Value (per 2026 IBC Valuation Table, by Occupancy Group/Construction Type, e.g., R-3 Type VB = $171/sq ft) × 0.00461 multiplierCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025, effective Jan. 2026); figures are approximate as the table revises twice yearly
Plan Review/Submittal FeeMinimum $43 if total building value is under $14,000; otherwise calculated as part of the Building Fee worksheetCity of Prescott Building Valuation and Fee Estimator, 1-2 Unit Residential worksheet
Electrical / Mechanical / Fuel Gas Fee (each), 1-2 Unit ResidentialTotal building square footage × $0.0396 per tradeCity of Prescott Building Valuation and Fee Estimator; fuel gas line optional if not used
MPF&E Plan Review FeeCombined M/P/FG/E fee total × 65%City of Prescott Building Valuation and Fee Estimator, 1-2 Unit Residential worksheet
Building Residential Plan Review Deposit Amount, New Single Family$788.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
C of O Walk-thru, Residential Building only$198.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Residential Addition / Remodel Permit (Addition, Remodel, Casita, Guesthouse, Decks, Patio Cover, Pergola)

Verified

Required for additions, remodels, casitas, guesthouses, decks, patio covers, and pergolas on existing residential structures in Prescott. Reviewed against the 2024 IRC as adopted and amended by the City of Prescott.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for additions, remodels, casitas, guesthouses, decks (over 200 sq ft, over 30 inches high, part of required egress, or attached to the house — and even smaller detached decks per the City's permit-required matrix), patio covers, and pergolas
  • Residential Addition or Remodel Checklist applies, requiring a combined 'PLANS' file (cover sheet, site plan, applicable construction plans) and 'SUPPORT DOCS' file (structural calculations, truss layout, soils report, ResCheck, Manual J/S/D, as applicable to project scope)
  • Plans must comply with City of Prescott Design Criteria (105 mph wind, Exposure C; Seismic Design Category C)
  • Properties in Historic Preservation Districts may face additional exterior-appearance review standards

Required documents

  • RequiredResidential Addition or Remodel ChecklistCity of Prescott submittal checklist for additions, remodels, casitas, guesthouses, decks, patio covers, and pergolas
  • RequiredSite/Plot PlanParcel lot lines and address, parcel square footage, setbacks, existing structures/utilities/easements, and location/size of proposed addition with distances from lot lines and other structures

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on ValuationTotal Building Value (2026 valuation table by occupancy/construction type; e.g. covered patio $67/sf, covered deck $67/sf, uncovered deck $65/sf per the City's residential worksheet) × 0.00461 multiplierCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
Plan Review/Submittal FeeMinimum $43 if total building value is under $14,000City of Prescott Building Valuation and Fee Estimator, 1-2 Unit Residential worksheet
Building Plan Check — Additions or Revisions to Approved Plans (per hour)$106.00/hourCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Electrical Only Permit

Verified

Required for electrical repair, replacement, addition, and new service work in Prescott, governed by the 2023 National Electrical Code (NEC) as adopted and amended by the City of Prescott. Like-for-like panel upgrades up to 200 amps and simple panel replacements qualify for the Fast Track expedited program.

Verified 2026-07-06 · Source

Requirements

  • Electrical permit required for panel work, adding circuits/outlets, new generator placement, new service entrances/upgrades, and new electric meters
  • Governed by the 2023 NEC as adopted by the City of Prescott
  • Like-for-like panel upgrades up to 200 amps require no supporting documents beyond the application itself; adding circuits or outlets requires an electrical schematic/floor plan showing new and existing circuits, amperage, and GFCI/AFCI requirements
  • New service entrances/upgrades under 600 amps and under 4,000 sq ft require a one-line diagram, panel schedule, and load calculations if 4,000 sq ft or greater; service entrances 600 amps or greater require full engineered, stamped documents
  • Electrical Panel Replacement up to 200 amps qualifies for the Fast Track Permit (FTP) program (no construction plans required, on-site verification)
  • Submit via the PrescottPermits.com online portal

Required documents

  • RequiredElectrical Only ChecklistCity of Prescott submittal checklist covering electrical repair/replacement, circuit additions, generator placement, and service entrance/meter work
  • OptionalFast Track Permit ChecklistUsed in place of the standard checklist for 'Electrical Panel Replacement up to 200 amps' — requires only a site plan (properties in Historic Districts or FEMA floodplains are not eligible)

Fee schedule

Fee typeAmountNotes
Electrical Fee (new construction context), 1-2 Unit ResidentialTotal building square footage × $0.0396City of Prescott Building Valuation and Fee Estimator, 1-2 Unit Residential worksheet
Electrical Fee (new construction context), 3+ Unit/CommercialTotal building square footage × $0.0792City of Prescott Building Valuation and Fee Estimator, 3+ Unit/Commercial worksheet
Fast Track Permit (FTP) Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); applies to Electrical Panel Replacement up to 200 amps and other qualifying Fast Track scopes
Fast Track Permit (FTP) Issue Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Plumbing Only Permit

Verified

Required for plumbing installation, alteration, or repair work in Prescott, governed by the 2024 International Plumbing Code (IPC) as adopted and amended by the City of Prescott. Interior plumbing repair/replacement and water heater like-for-like replacement both qualify for the Fast Track expedited program.

Verified 2026-07-06 · Source

Requirements

  • Plumbing permit required for interior plumbing repair/replacement, new/repaired/replaced gas yardlines, and water heater changes (including change of fuel type)
  • Governed by the 2024 IPC as adopted by the City of Prescott
  • Interior Plumbing Repair or Replace requires an Interior Plumbing Plan showing water/sewer/gas line locations, piping length/material/size, and (for gas repairs) BTUs and total developed piping length
  • New Gas Yardline or Gas Yardline Repair/Replace requires a full site plan showing meter location, connection point, dielectric union and shut-off, existing yardlines, and piping material/length/size
  • Water Heater Change of Fuel Type requires a sealed structural plan/calculations (if applicable) plus a site plan with water and sewer service details per City Standard Details 316P and 440P-3
  • Interior plumbing repair/replace and like-for-like water heater replacement qualify for the Fast Track Permit (FTP) program
  • Submit via the PrescottPermits.com online portal

Required documents

  • RequiredPlumbing Only ChecklistCity of Prescott submittal checklist covering interior plumbing repair/replace, gas yardlines, and water heater fuel-type changes
  • OptionalFast Track Permit ChecklistUsed for 'Water Heater, like for like' and 'Interior plumbing repair or replace' — requires only a site plan (properties in Historic Districts or FEMA floodplains are not eligible)

Fee schedule

Fee typeAmountNotes
Plumbing Fee (new construction context), 3+ Unit/CommercialTotal building square footage × $0.0792City of Prescott Building Valuation and Fee Estimator, 3+ Unit/Commercial worksheet (the 1-2 Unit Residential worksheet groups Plumbing into the combined M,P,FG&E $0.0396/sf rate)
Fast Track Permit (FTP) Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); applies to Water Heater like-for-like and Interior Plumbing Repair or Replace
Fast Track Permit (FTP) Issue Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Mechanical Only Permit (HVAC)

Verified

Required for new heating/AC units, new equipment locations, new ductwork, or new curbing in Prescott, governed by the 2024 International Mechanical Code (IMC) as adopted and amended by the City of Prescott. Like-for-like HVAC replacement qualifies for the Fast Track expedited program.

Verified 2026-07-06 · Source

Requirements

  • Mechanical permit required for new heating and air conditioning units, new equipment locations, new ductwork, and new roof curbing
  • Governed by the 2024 IMC as adopted by the City of Prescott
  • HVAC like-for-like replacement qualifies for the Fast Track Permit (FTP) program, requiring only a site plan and manufacturer installation instructions
  • Furnace/HVAC replacement always requires a permit per the City's 'What Needs a Permit' matrix, even for simple replacements
  • Submit via the PrescottPermits.com online portal

Required documents

  • RequiredMechanical Only ChecklistCity of Prescott submittal checklist for new heating/AC units, equipment relocation, ductwork, and curbing
  • OptionalFast Track Permit ChecklistUsed for 'HVAC Like for like' replacement — requires a site plan and manufacturer installation instructions (properties in Historic Districts or FEMA floodplains are not eligible)

Fee schedule

Fee typeAmountNotes
Mechanical Fee (new construction context), 3+ Unit/CommercialTotal building square footage × $0.0792City of Prescott Building Valuation and Fee Estimator, 3+ Unit/Commercial worksheet (the 1-2 Unit Residential worksheet groups Mechanical into the combined M,P,FG&E $0.0396/sf rate)
Fast Track Permit (FTP) Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); applies to HVAC like-for-like replacement
Fast Track Permit (FTP) Issue Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Re-Roof Only Permit

Verified

Required for complete roof tear-off and re-sheathing in Prescott; a non-structural re-roof (no second layer of different material, no structural repairs) may qualify for the Fast Track expedited program. Governed by 2024 IRC/IBC roofing provisions and the City's Re-Roof Only Checklist.

Verified 2026-07-06 · Source

Requirements

  • Building permit required for a complete roof tear-off/replacement of sheathing; adding a second layer of shingles of the SAME type requires no permit outside a Historic District, but any other re-roof scope requires one
  • Roofing Plan required combining site plan (showing re-roof location, roof pitch, dimensions, materials) with structural calculations where the project requires meeting 30 lb snow load or adds a second layer of different roofing material or a second layer of structural decking
  • Material cut sheets required for Historic District properties (physical samples may also be requested)
  • Non-structural re-roofs qualify for the Fast Track Permit (FTP) program; properties in Historic Districts or FEMA floodplains are not eligible for Fast Track

Required documents

  • RequiredRe-Roof Only ChecklistCity of Prescott submittal checklist requiring a combined 'ROOFING PLAN' file (site plan plus structural calculations where applicable) and, for Historic District properties, material cut sheets
  • OptionalFast Track Permit ChecklistUsed for 'Re-Roof Non-Structural' — requires only a site plan (properties in Historic Districts or FEMA floodplains are not eligible)

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on ValuationTotal roof value (per applicable valuation table) × 0.00461 multiplierCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); standard (non-Fast-Track) re-roof projects follow the general Building Permit valuation worksheet
Fast Track Permit (FTP) Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); applies to Re-Roof Non-Structural
Fast Track Permit (FTP) Issue Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Photovoltaic Solar System Permit

Verified

Required for installation of rooftop or ground-mount photovoltaic solar systems in Prescott. Governed by the City's dedicated Photovoltaic Solar System Checklist and the 2023 NEC as adopted and amended by the City of Prescott. Solar panels always require a permit per the City's 'What Needs a Permit' matrix.

Verified 2026-07-06 · Source

Requirements

  • Solar panels or hydronic heat systems always require a building permit per the City's 'What Needs a Permit' matrix
  • Combined 24x36 'PLANS' file required: cover sheet (applicable codes, design criteria, sheet index, PV system kW size and quantity/size/type of modules, combiner, inverters, racking, batteries), site plan (parcel lines, existing structures/fences/gates, main/sub-panel and equipment locations, ground-mount panel locations and distances), and solar plans (roof layout with fire pathways, roof support/racking detail, placard/label locations, one-line diagram)
  • Supporting documents (8.5x11 'SUPPORT DOCS' file) required if applicable: manufacturer equipment/hardware specs with UL compliance, structural design analysis (residential required if built prior to 1994; commercial always required, sealed by an Arizona-registered engineer), and a roof structure sign-off letter sealed by an Arizona-registered structural engineer
  • Submit via the PrescottPermits.com online portal

Required documents

  • RequiredPhotovoltaic Solar System ChecklistCity of Prescott submittal checklist detailing required Plans and Supporting Documents file contents for rooftop and ground-mount PV systems
  • OptionalStructural Design Analysis / Roof Structure Sign-offRequired for residential structures built prior to 1994, and always required (Arizona-engineer sealed) for commercial installations

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on ValuationValuation-based per the City's Building Valuation and Fee Estimator, applying the applicable occupancy/construction-type multiplierCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); no separate flat PV fee line was published — PV systems are billed through the general valuation-based Building Permit Fee worksheet
Building Plan Check (Per Hour, if additional review needed)$106.00/hourCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Demolition Permit

Verified

Required for demolition of residential, commercial, and multi-family structures in Prescott. Accessory structure demolition qualifies for the Fast Track expedited program; commercial demolition requires a NESHAP report.

Verified 2026-07-06 · Source

Requirements

  • Building permit required before demolishing a residential, commercial, or multi-family structure within Prescott city limits
  • Site plan required showing parcel lot lines and address, existing structures/fences/retaining walls, and existing utilities/easements
  • Commercial demolition requires a National Emission Standard for Hazardous Air Pollutants (NESHAP) Report
  • Accessory Structure Demolition qualifies for the Fast Track Permit (FTP) program
  • Additional Engineering/FEMA Floodplain (928-777-1405 option 3) or Fire Sprinkler/WUI (928-777-1445 option 3) coordination may be required depending on the site

Required documents

  • RequiredDemolition ChecklistCity of Prescott submittal checklist for residential, commercial, and multi-family demolition permits
  • OptionalNESHAP ReportRequired for commercial demolition only
  • OptionalFast Track Permit ChecklistUsed for 'Accessory Structure Demolition' — requires only a site plan (properties in Historic Districts or FEMA floodplains are not eligible)

Fee schedule

Fee typeAmountNotes
Fast Track Permit (FTP) Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); applies to Accessory Structure Demolition
Fast Track Permit (FTP) Issue Fee$66.00City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
Building Permit Fee (non-Fast-Track demolition, e.g., primary structure)Per the general Building Valuation and Fee Estimator worksheet, or a flat administrative fee determined by the Permit Center depending on structure size/typeNo separately itemized flat demolition fee line (beyond the Fast Track accessory-structure rate) was published in the City's Building Valuation and Fee Estimator as of this review; primary-structure demolition should be confirmed directly with the Permit Center at 928-777-1371

Fences and Walls Permit

Verified

Fences and retaining/masonry walls in Prescott always require a building permit (any height) per the City's 'What Needs a Permit' matrix — unlike some Arizona jurisdictions with a permit-exempt fence-height threshold. A Right-of-Way permit is additionally required if the fence or wall is located in the public right-of-way.

Verified 2026-07-06 · Source

Requirements

  • Fences of ANY height (6 feet and under, or over 6 feet) require a building permit in Prescott — there is no permit-exempt fence-height threshold, unlike Buckeye or many other Arizona cities
  • A Right-of-Way (ROW) permit is additionally required if the fence or wall is located within the public right-of-way
  • Residential fences/non-retaining masonry walls 6 feet and under require only a site plan (lot lines, existing structures/fences/retaining walls, utilities/easements/setbacks, proposed wall size/location/height/materials)
  • Residential retaining walls 32 inches and under require the same site plan documentation
  • Residential retaining walls over 32 inches, and ANY commercial/multi-family fence/wall or residential fence over 6 feet, require a structural plan and calculations sealed by an Arizona-registered structural engineer

Required documents

  • RequiredFences and Walls ChecklistCity of Prescott submittal checklist covering residential fences/walls under 6 ft, retaining walls under/over 32 inches, and commercial/multi-family or over-height fences/walls
  • OptionalStructural Plan and CalculationsSealed by an Arizona-registered structural engineer; required for retaining walls over 32 inches and any commercial/multi-family or over-6-ft residential fence/wall

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on ValuationValuation-based per the City's Building Valuation and Fee Estimator worksheetCity of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025); no separate flat fence/wall fee line was published — fences and walls are billed through the general valuation-based Building Permit Fee worksheet
Plan Review/Submittal FeeMinimum $43 (1-2 unit residential) or $49 (3+ unit/commercial) if total value is under $14,000City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

Accessory Structures Permit (Sheds, Carports)

Verified

Required for sheds over 200 sq ft (or any size with mechanical/plumbing/electrical), sheds under 200 sq ft, and carports of any size in Prescott. Governed by the 2024 IRC/IBC as adopted and amended by the City of Prescott.

Verified 2026-07-06 · Source

Requirements

  • Sheds over 200 sq ft, or any size shed with mechanical/plumbing/electrical service, require a building permit
  • Sheds under 200 sq ft with no mechanical/plumbing/electrical STILL require a building permit in Prescott per the City's 'What Needs a Permit' matrix — there is no size-based exemption as in some other Arizona cities
  • Carports under 200 sq ft and carports over 200 sq ft BOTH require a building permit
  • Accessory Structures Checklist applies for submittal requirements

Required documents

  • RequiredAccessory Structures ChecklistCity of Prescott submittal checklist for sheds, carports, and other detached accessory structures
  • RequiredSite/Plot PlanParcel lot lines and address, existing structures/fences/retaining walls, existing utilities and easements, and location/size of proposed structure

Fee schedule

Fee typeAmountNotes
Building Permit Fee — Based on ValuationValuation-based per the City's Building Valuation and Fee Estimator worksheet (Group U, Utility/Miscellaneous/Garage valuation rates, e.g., $73-$123/sf depending on construction type per the 2026 IBC Valuation Table)City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)
Plan Review/Submittal FeeMinimum $43 (1-2 unit residential) if total value is under $14,000City of Prescott Building Valuation and Fee Estimator (rev. 12/26/2025)

EV Charger / EVSE Permit

Verified

The City of Prescott has no EV-charger-specific permit type or fee. Per the City's 'What Needs a Permit' matrix, 'ELECTRICAL ADDITION/MOVE/DEMO' requires a permit, and an EV charger circuit is filed under the standard 'Electrical Only' permit's 'Adding Circuits or Outlets' scope (Electrical Only Checklist), governed by the 2023 NEC as adopted by the City. Direct review of the City's Fast Track Permit Checklist confirms the program covers exactly seven scopes — HVAC like-for-like, Water Heater like-for-like, Accessory Structure Demolition, Re-Roof Non-Structural, Window and Door like-for-like, Interior plumbing repair/replace, and Electrical Panel Replacement up to 200 amps — and an EV charger circuit addition is NOT among them, so it does not qualify for the Fast Track program's flat $66 issue fee and must go through standard Electrical Only review. The City's Building Valuation and Fee Estimator publishes electrical fees primarily in a new-construction context, but the City's own Council-adopted FY2026 Citywide Fee Schedule confirms the governing rate: an 'E/M/P Permit Residential - Electrical' line of $0.0396 per square foot, with the parallel Commercial E/M/P Electrical line explicitly labeled 'Valuation/min $66.00' -- establishing a $66.00 practical minimum permit fee that applies across the E/M/P schedule. A typical EV charger circuit retrofit (small scope, valuation far below the City's $14,000 building-permit-fee threshold) is billed at this $66.00 minimum.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit required for an EV charger circuit — filed under the Electrical Only permit's 'Adding Circuits or Outlets' scope
  • Governed by the 2023 NEC as adopted by the City of Prescott
  • Electrical Schematic / Floor Plan required, showing locations of new and existing circuits or outlets, circuit amperage, GFCI/AFCI requirements, and appliance requirements for specialized equipment
  • NOT eligible for the Fast Track Permit (FTP) program — the FTP's seven eligible scopes do not include EV chargers or general circuit additions (only 'Electrical Panel Replacement up to 200 amps' is FTP-eligible among electrical work)
  • If the installation requires a new service entrance/upgrade, additional documentation (one-line diagram, panel schedule, load calculations, or full engineered stamped documents for 600+ amp services) is required per the Electrical Only Checklist
  • Submit via the PrescottPermits.com online portal

Required documents

  • RequiredElectrical Only ChecklistCity of Prescott submittal checklist; the EV charger circuit falls under the 'Adding Circuits or Outlets' section, requiring an electrical schematic/floor plan showing new and existing circuits, amperage, and GFCI/AFCI requirements

Fee schedule

Fee typeAmountNotes
Electrical Only Permit -- E/M/P Permit Residential Electrical (minimum/issue fee)$66.00 minimum (FY26), plus $0.0396 per square foot of affected floor area for larger scopesCity of Prescott FY2026 Citywide Fee Schedule (Council Adopted 5/27/2025, Amended 9/9/2025), Community Development - Building Safety section: 'E/M/P Permit Residential - Electrical (Sq. Foot)' = $0.0396/sq ft; 'Issue Building' = $66.00 Each; 'Residential Building Permit Under $14,000' = $66.00 Each. The parallel Commercial E/M/P Electrical line is explicitly listed as 'Valuation/min $66.00', confirming a $66.00 practical floor applies across the E/M/P fee lines. A typical EV charger circuit retrofit (small scope, valuation well under $14,000) is billed at this $66.00 minimum. Re-verified directly against the adopted fee schedule as of 2026-07-20.
Issue Fee$66.00City of Prescott FY2026 Citywide Fee Schedule, Community Development - Building Safety section (confirms the $66.00 figure previously sourced only from the Building Valuation and Fee Estimator calculator tool)

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Prescott building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

View current record →All versions →

Permalink: /arizona/yavapai-county/prescott/as-of/2026-07-06/

Snapshot date: 2026-07-06

Commit: cfd4e2c

Reproducible from PermitBase’s version-controlled dataset, commit cfd4e2c.