Menifee building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Menifee, California.
Verified 2026-09-20 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 29844 Haun Road, Menifee, CA 92586
- Phone
- (951) 723-3729 (Building & Safety); 951-672-6777 (City Hall and inspection cancellations); (951) 723-3736 (to speak to an inspector, 7:00-8:00 am only); fax 951-679-2567
- Office hours
- City Hall hours are published as "Monday - Friday 8:00 a.m. - 5:00 p.m." No separate counter hours for the Building & Safety Division appear on the pages read, so this record does not assert any. Two narrower windows are published and are the ones that actually govern: inspections run 8:00 am to 4:00 pm, and an inspector can be reached directly only between 7:00 am and 8:00 am.
- Website
- Official site
Published scheduling rules
- GET INSPECTION REQUESTS IN BEFORE 2:00 PM for the next business day. (Building Permit)
- EVERYTHING GOES THROUGH THE PORTAL AND THE MONEY COMES WITH IT: "All submittals including Fast-Track permits must be made through the Menifee Permit Portal, with fees - including plan review fees - due at the time of submittal." Registration is required both to apply and to schedule inspections. (Building Permit)
Inspection sequence
Applies to: Building Permit
- 1
Portal only, with inspectors working assigned areas
"All building inspections must be scheduled via the Menifee Permit Portal. You must be registered to apply for permits and schedule inspections." Behind it: "field inspectors are assigned an area of the City and perform daily inspections in that area."
- 2
Monday to Friday, 8:00 am to 4:00 pm, with a 2:00 pm cut-off
"Inspections are conducted Monday through Friday, from 8:00 am - 4:00 pm", and "Building Inspections requested before 2:00 pm can be performed the next business day."
- 3
One hour a day to reach an inspector by phone
"To speak with an inspector directly, please call (951) 723-3736 between 7:00 am and 8:00 am, Monday through Friday." Outside that hour the route is the portal or the main line; the window sits before inspections begin at 8:00 am.
- 4
Two solar inspections per company per day
"Two inspections per solar company can be accommodated per day." The cap is on the COMPANY, not the project - so a solar contractor with three jobs finishing on the same day cannot have all three inspected that day however they are booked.
- 5
The solar contractor signs the checklist first
"For the SolarAPP+ permits field, the solar representative shall verify the Inspection Checklist and sign the document confirming completion prior to inspection." The signature is a precondition of the inspection, not a record of it.
- 6
Cancellations go to the main line
"For cancellations, call the Building & Safety Department at (951) 672-6777." Booking is in the portal; cancelling is a telephone call.
Sources & verification
Verified against official sources. Last reviewed 2026-09-20.
Fee schedules
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Menifee building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Menifee building permits
Get alerts for Menifee
We'll email you when Menifee's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.