Longmont building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Longmont, Colorado.

Verified 2026-06-30 · Source

How to schedule

Inspections are requested through the building department below.

Address
385 Kimbark St., Longmont, CO 80501
Phone
(303) 651-8332
Office hours
Mon–Fri, 8 a.m.–5 p.m. (closed Federal holidays, Veterans Day, and the day after Thanksgiving; Building Inspection closed 10–11 a.m. on the 2nd and 4th Thursday for staff training)

Published scheduling rules

  • Notify LPC at least 48 hours in advance to schedule any required Disconnect; LPC must receive an approved inspection release from Building Services before a Reconnect can occur; LPC staff perform ALL electric meter sets/removals and service disconnects/reconnects (no exceptions) (EV Charger / Electric Vehicle Charging Station Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend below the 30-inch frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed

  4. 4

    Insulation / Energy

    Insulation and energy compliance verification before drywall

  5. 5

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings and foundation before concrete pour — 30-inch frost depth minimum

  2. 2

    Framing

    Structural framing per engineered/stamped plans

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    After framing complete, before walls covered

  2. 2

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  3. 3

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Deck / Covered Patio Permit

  1. 1

    Footing

    Before concrete pour for structural post footings — must extend below 30-inch frost line

  2. 2

    Framing

    Structural framing before decking/cover installed

  3. 3

    Final

    Structure complete per approved plans

Applies to: Plumbing Permit

  1. 1

    Underground / Under-slab

    Before concrete pour — pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final — Building

    Panel mounting, racking attachment, roof penetration sealing, all electrical connections verified

  3. 3

    LPC Meter Set / Anti-Islanding Test

    After final building inspection passes, LPC sets the bi-directional net meter and performs anti-islanding and pre-parallel testing before issuing Permission to Operate (PTO)

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed

  2. 2

    Final

    All devices installed, panel labeled, system energized; LPC sets/verifies meter

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment installation and ductwork before walls closed

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Roofing Permit (Reroof)

  1. 1

    Mid-Roof (commercial built-up roofs only)

    Required before dry-in and when above-deck insulation or roof sheathing is installed

  2. 2

    Final

    Completed roof — verify flashing, drip edge, underlayment, installation quality

Longmont building permits

Get alerts for Longmont

We'll email you when Longmont's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.