Louisville building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Louisville, Colorado.

Verified 2026-07-05 · Source

How to schedule

Inspections are requested through the building department below.

Address
City Hall, 749 Main St, Louisville, CO 80027
Phone
(303) 335-4584
Office hours
Monday-Thursday 8AM-4PM (in-person; remote 4PM-5PM); Friday 8AM-5PM remote/by appointment only; Tuesday 11AM-12PM limited staff availability (staff meeting). Inspection hours Monday-Friday 6:30AM-5PM.

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footing

    Before concrete pour

  2. 2

    Rough Frame

    Framing, sub-flooring, and stairs complete before cover

  3. 3

    Rough Plumbing / Rough Electrical / Rough Mechanical

    Trade rough-ins requested via the CSS portal before concealment

  4. 4

    Building Final

    All work complete per approved plans; Certificate of Occupancy/Completion reviewed by staff within 3 business days of a passed Building Final

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour (new detached ADU)

  2. 2

    Rough Frame / Rough Plumbing / Rough Electrical / Rough Mechanical

    Trade rough-ins before concealment

  3. 3

    Building Final

    All work complete; occupancy and utility-connection compliance confirmed

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour

  2. 2

    Rough Frame / Rough Plumbing / Rough Electrical / Rough Mechanical

    Trade rough-ins before concealment

  3. 3

    Building Final

    All work complete per approved plans

Applies to: Solar PV Permit (Roof Top Unit/Solar/Telecommunication)

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, requested via the CSS portal

  2. 2

    Building Final (racking/structural)

    Racking, roof penetrations, and structural attachment verified against approved plans

  3. 3

    Final Electrical

    System energized and verified; devices installed and labeled per the 2023 NEC

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Requested via the CSS portal once wiring and panel are installed, before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment installed but not yet concealed

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Requested via the CSS portal after pipes are installed, before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Louisville building permits

Get alerts for Louisville

We'll email you when Louisville's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.