Inspection sequence, scheduling, and re-inspection fees for building permits in Poncha Springs, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
Town of Poncha Springs Town Hall: 333 Burnett Avenue, PO Box 190, Poncha Springs, CO 81242. Chaffee County Building Safety Department: 104 Crestone Ave., Room 125 (2nd Floor), Salida, CO 81201 (mailing: P.O. Box 699, Salida, CO 81201)
Phone
Town of Poncha Springs: 719-539-6882 (after-hours/on-call: 719-207-2293; fax 719-539-6898). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208
Office hours
Town of Poncha Springs Town Hall: Monday-Thursday 8:00 a.m.-5:00 p.m., Fridays 8:00 a.m.-12:00 p.m., closed weekends and major holidays, per the Town's own site footer. Chaffee County Building Safety Department: operates on a 4-day work week (Monday-Thursday), inspections performed Monday-Thursday excluding federal holidays; inspection requests must arrive by 4:00 p.m. the business day before the desired inspection date.

Inspection sequence

Applies to: Residential Building Permit (New Construction, Single-Family, ADU, Additions)

  1. 1

    Foundation / Footing

    Performed by Chaffee County Building Safety Department before concrete pour

  2. 2

    Framing

    Performed by Chaffee County

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed; each trade requires its own separate County permit

  4. 4

    Final Inspection (County) + Town Staff Pre-CO Site Review

    County final inspection plus a distinct Town Staff review confirming road cuts patched, sidewalk/infrastructure damage repaired, exterior finishes complete, driveway surfaced, final grading/drainage established, exterior lighting compliant (Sec. 5.15 municipal code), and one street-side tree planted, per the Town's own Building Permit Coversheet

Applies to: Electrical Permit

  1. 1

    Service Underground System

    Per the County's own required-inspections list

  2. 2

    Rough-In

    Prior to insulation and drywall

  3. 3

    Final

    Prior to occupancy

Applies to: Plumbing Permit

  1. 1

    Underground / Under-slab

    Before concrete pour

  2. 2

    Rough-In

    Before walls closed

  3. 3

    Final

    Fixtures connected, no leaks, proper venting

Applies to: Residential Addition / Remodel Building Permit

  1. 1

    Foundation (if new footings)

    Performed by Chaffee County

  2. 2

    Framing / Rough Trades

    Framing and MEP rough-in before concealment

  3. 3

    Final Inspection (County) + Town Staff Pre-CO Site Review

    Both required before Certificate of Occupancy, per the Town's own Building Permit Coversheet

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Service Underground System

    Per Chaffee County's required-inspections list

  2. 2

    Rough-In

    Prior to insulation and drywall; roof-mount racking/attachment verified before module installation

  3. 3

    Final

    Prior to occupancy/energizing the system

Applies to: Accessory Dwelling Unit (ADU) Building Permit

  1. 1

    Foundation / Framing

    Performed by Chaffee County per standard residential construction sequence

  2. 2

    Final Inspection (County) + Town Staff Pre-CO Site Review

    Both required before Certificate of Occupancy

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    EVSE circuit wiring prior to insulation and drywall

  2. 2

    Final

    Charger installed and energized prior to occupancy sign-off

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment installation and ductwork before walls closed

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Roofing Permit

  1. 1

    Mid-Roof / In-Progress

    Required for all re-roof permits; verifies ice/water barrier, underlayment, drip edge, and flashing installation

  2. 2

    Final

    Confirms completed roof assembly per approved plans and manufacturer instructions

Re-inspection fees

Electrical PermitRe-inspection Fee
$100.00
Plumbing PermitRe-inspection Fee
$100.00
Mechanical / HVAC PermitRe-inspection Fee
$50.00
EV Charger / EVSE PermitRe-inspection Fee
$100.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Poncha Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Poncha Springs building permits

Get alerts for Poncha Springs

We'll email you when Poncha Springs's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.