Skip to main content
PermitBase

EV Charger / EVSE Permit in Poncha Springs, Colorado

Poncha Springs has no EV-charger-specific permit type or fee line. An EV charger (EVSE) circuit is electrical work, issued and inspected by the Chaffee County Building Safety Department under CRS 12-23-117, using the same county-wide Electrical Permit Application and fee schedule verified elsewhere in this corpus — a standalone EVSE circuit at an existing home is billed under the 'All other installations' valuation-based tier, since it is not new residential wiring by square footage. A Town of Poncha Springs zoning sign-off (Building Permit Coversheet) is required first only when the EV charger work is part of a broader project that independently triggers Town review (e.g., new construction, addition). Colorado's HB24-1173 (EV charger permit checklists, 3-business-day decisions) applies only to counties with 20,000+ residents and municipalities with 10,000+ residents; Chaffee County's 2020 Census population (19,476) is below that threshold, and Poncha Springs itself is far smaller, so the statewide mandate does not currently bind either permitting agency.

Verified 2026-07-20 · Source

When you need this permit

  • Confirm with the Town of Poncha Springs (mail@ponchasprings.us) whether a standalone EV charger installation needs a Town Coversheet sign-off, or whether it can go directly to the County as a standalone trade permit — the electrical-permit entry's guidance (Town sign-off only required when bundled with a broader project) is treated as applicable here
  • Submit the Chaffee County Electrical Permit Application; a standalone EVSE circuit is priced from the 'All other installations' valuation-based tier since it is not new residential wiring by square footage
  • Colorado's homeowner clause allows an owner-occupant to self-perform electrical work on their sole residence if not for sale/resale/rental Owner-builder

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

All other installations — valuation up to $2,000.00 (applies to a standalone EV charger circuit; no EV-specific line item found)Chaffee County Electrical Permit Application, CRS 12-23-117 fee schedule (county-wide, applies identically in Poncha Springs). No EV-charger or electric-vehicle line item was found on the Application; a standalone EVSE circuit is billed under this general installation-valuation tier.
$135.00
All other installations — valuation $2,001.00 and above (if the EVSE installation requires a panel upgrade or larger-scope electrical work)
$135.00 + $13.50 per $1,000 (or fraction thereof)
Re-inspection Fee
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Poncha Springs?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    EVSE circuit wiring prior to insulation and drywall

  2. 2

    Final

    Charger installed and energized prior to occupancy sign-off

See the full Poncha Springs inspection guide — scheduling & re-inspection fees →

Tips

  • If a permit is not filed in advance of the installation's commencement, the inspection fee is DOUBLED per CRS 12-23-117(3), per the County's own application — this applies to EV charger work the same as any other electrical installation.
  • Chaffee County's population (19,476 per the 2020 Census) sits just under Colorado HB24-1173's 20,000-resident county threshold, so the state's EV-charger-specific permitting mandate (checklists, 3-business-day decisions) does not currently apply here — worth re-checking if a newer population figure crosses the line.

Frequently asked questions

Poncha Springs requires an ev charger / evse permit for: Confirm with the Town of Poncha Springs (mail@ponchasprings.us) whether a standalone EV charger installation needs a Town Coversheet sign-off, or whether it can go directly to the County as a standalone trade permit — the electrical-permit entry's guidance (Town sign-off only required when bundled with a broader project) is treated as applicable here; Submit the Chaffee County Electrical Permit Application; a standalone EVSE circuit is priced from the 'All other installations' valuation-based tier since it is not new residential wiring by square footage; Colorado's homeowner clause allows an owner-occupant to self-perform electrical work on their sole residence if not for sale/resale/rental. If your project isn't listed, confirm with Two-agency split: Town of Poncha Springs (Town Zoning Criteria review, Town Building Permit Coversheet, Town Building/Utility fees, and 2% Building Construction Materials Use Tax, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at Town of Poncha Springs: 719-539-6882 (after-hours/on-call: 719-207-2293; fax 719-539-6898). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208 before starting work.

No. Electrical permits for EV chargers in Poncha Springs are issued by the Chaffee County Building Safety Department under the same county-wide fee schedule used for any other electrical work — a standalone EVSE circuit falls under the 'All other installations' valuation tier ($135.00 up to $2,000 of valuation). A Town Coversheet sign-off is only required if the charger work is bundled with a larger project that independently triggers Town review.

Poncha Springs does not publish a plan-review timeline for this permit. Contact Two-agency split: Town of Poncha Springs (Town Zoning Criteria review, Town Building Permit Coversheet, Town Building/Utility fees, and 2% Building Construction Materials Use Tax, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at Town of Poncha Springs: 719-539-6882 (after-hours/on-call: 719-207-2293; fax 719-539-6898). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208 for current turnaround.

You'll need: Chaffee County Electrical Permit Application. See the required-documents checklist on this page for details on each.

Poncha Springs requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Two-agency split: Town of Poncha Springs (Town Zoning Criteria review, Town Building Permit Coversheet, Town Building/Utility fees, and 2% Building Construction Materials Use Tax, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) (Town of Poncha Springs: 719-539-6882 (after-hours/on-call: 719-207-2293; fax 719-539-6898). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208).

Apply through Two-agency split: Town of Poncha Springs (Town Zoning Criteria review, Town Building Permit Coversheet, Town Building/Utility fees, and 2% Building Construction Materials Use Tax, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at Town of Poncha Springs Town Hall: 333 Burnett Avenue, PO Box 190, Poncha Springs, CO 81242. Chaffee County Building Safety Department: 104 Crestone Ave., Room 125 (2nd Floor), Salida, CO 81201 (mailing: P.O. Box 699, Salida, CO 81201). Phone: Town of Poncha Springs: 719-539-6882 (after-hours/on-call: 719-207-2293; fax 719-539-6898). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208, email: Town of Poncha Springs: mail@ponchasprings.us. Chaffee County Building Safety Department: bdepartment@chaffeecounty.org (electronic plan submittals: eplans@chaffeecounty.org). Office hours: Town of Poncha Springs Town Hall: Monday-Thursday 8:00 a.m.-5:00 p.m., Fridays 8:00 a.m.-12:00 p.m., closed weekends and major holidays, per the Town's own site footer. Chaffee County Building Safety Department: operates on a 4-day work week (Monday-Thursday), inspections performed Monday-Thursday excluding federal holidays; inspection requests must arrive by 4:00 p.m. the business day before the desired inspection date.. Official information: https://www.ponchasprings.us/planning-zoning and https://www.chaffeecounty.org/departments/building_department/index.php.

Poncha Springs, Colorado has adopted: 2021 International Building Code (IBC) — enforced county-wide by the Chaffee County Building Safety Department per the County's own Adopted Codes & Design Criteria page; the Town of Poncha Springs' own Land Use Code (Section 6.13.5.9) explicitly confirms IBC compliance is 'administered by the Chaffee County Building Department' for construction within Town limits; 2021 International Residential Code (IRC); 2021 International Fire Code (IFC); 2021 International Existing Building Code (IEBC); 2021 International Plumbing Code (IPC); 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2021 International Energy Conservation Code (IECC); 2023 National Electrical Code (NFPA 70 / NEC) — per Chaffee County Building Safety Department's Adopted Codes & Design Criteria page, the agency that actually issues and enforces electrical permits county-wide including Poncha Springs; 2017 ICC A117.1 Accessible and Usable Buildings and Facilities — Chaffee County Adopted Codes & Design Criteria page; Colorado Wildfire Resiliency Code (effective July 1, 2026) — Chaffee County Adopted Codes & Design Criteria page, BOCC Ordinance 2026-02 with local amendments; Colorado Model Electric Ready & Solar Ready Code — Chaffee County Adopted Codes & Design Criteria page; Town of Poncha Springs Land Use Code (adopted December 9, 2013, amended on an ongoing basis, most recently by Ordinance No. 2025-04) — governs zoning districts, setbacks, dimensional standards, ADU eligibility/design standards (Section 6.13), home occupations (Section 6.12), lighting standards (Section 5.15), and site work required before Certificate of Occupancy; reviewed by Town Staff (John Armstrong, Town Planner, per the Town's own Building Permit Coversheet) as the mandatory first step before the County's building-permit review begins; Town of Poncha Springs Ordinance #2008-11 (Building Construction Materials Use Tax) and CRS 29-2-105 — imposes a 2% Town use tax on building materials for any building-permit project, collected as part of the Town's own permit intake process, verified verbatim on the Town's own Exemption Certificate / Use Tax acknowledgment form. Local amendments apply — see the Poncha Springs overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Poncha Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.