This is PermitBase’s published record for Avon as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Avon building permits

Verified

Avon, Colorado — as published 2026-07-06.

Verified 2026-07-06 · Source

Codes adopted

2021 International Building Code (IBC) — Town of Avon Adopted Building Codes page2021 International Residential Code (IRC)2021 International Energy Conservation Code (IECC)2021 International Plumbing Code (IPC)2021 International Fuel Gas Code (IFGC)2021 International Mechanical Code (IMC)2021 International Fire Code (IFC), with additions and exceptions per the Eagle River Fire Protection District (ERFPD)2021 International Swimming Pool and Spa Code2021 International Property Maintenance Code2021 International Wildland-Urban Interface Code2023 National Electrical Code (NEC) — administered by the Colorado Department of Regulatory Agencies (DORA), not the Town, per the Town's own 'Common Building Permit Types' documentICC A117.1-2017 Standard for Accessible and Usable Buildings and FacilitiesNote on code currency: Avon's adopted-codes list (2021 I-Codes cycle) is one cycle behind Vail's currently posted 2024 I-Codes list within the same county — confirmed directly against the Town's own Adopted Building Codes page as of this review; do not assume parity with Vail's code edition.

Permit types & fees

Residential Building Permit (New Structure)

Verified

Required for new single-family homes and new residential structures in the Town of Avon, referred to on the Town's own permit-types guide as a 'New structure permit.' Reviewed under the 2021 IRC/IBC as locally adopted, plus the Town's published design criteria. Mechanical and plumbing are included in a New Structure Permit; electrical permits must be separately obtained through DORA (state), and a fire sprinkler permit is separately obtained through the Eagle River Fire Protection District.

Verified 2026-07-06 · Source

Requirements

  • Plans must comply with the 2021 IRC/IBC as adopted, and meet the Town's Design Criteria: 129 psf ground snow load (above 8,200 ft) / 107 psf (below), 115 mph wind speed, 48-inch minimum frost depth, -20F winter design temperature, Seismic Design Category B
  • One full-size paper plan set required for all new construction before plan review can begin, in addition to the Cloudpermit electronic submittal
  • Electrical permits are NOT issued by the Town — must be separately obtained through the Colorado Department of Regulatory Agencies (DORA)
  • Fire sprinkler permit (if applicable) obtained separately through the Eagle River Fire Protection District
  • Contractor Business License (Cloudpermit) required for the General Contractor/Project Manager before the building permit can be issued
  • Exterior design/site elements typically require Planning Division Development Plan review (Minor or Major) in addition to Building Division review
  • Applications submitted via the Town of Avon Cloudpermit portal

Required documents

  • RequiredBuilding Permit Application (Cloudpermit)Submitted electronically through us.cloudpermit.com/avon
  • RequiredFull-Size Paper Plan SetOne full-size paper set required for new construction before plan review begins
  • RequiredContractor Business LicenseRequired through Cloudpermit prior to permit issuance

Fee schedule

Fee typeAmountNotes
Building/Plumbing/Mechanical Permit Fee — valuation $1.00-$500$50.00Community Development Fee Schedule, approved March 26, 2024 (Exhibit A to Resolution 24-11)
Building Permit Fee — valuation $501-$2,000$50.00 for the first $500 plus $3.40 for each additional $100 or fraction thereof, to and including $2,000
Building Permit Fee — valuation $2,001-$25,000$76.25 for the first $2,000 plus $15.50 for each additional $1,000 or fraction thereof, to and including $25,000
Building Permit Fee — valuation $25,001-$50,000$391.75 for the first $25,000 plus $11.15 for each additional $1,000 or fraction thereof, to and including $50,000
Building Permit Fee — valuation $50,001-$100,000$710 for the first $50,000 plus $7.75 for each additional $1,000 or fraction thereof, to and including $100,000
Building Permit Fee — valuation $100,001-$500,000$1,095 for the first $100,000 plus $6.20 for each additional $1,000 or fraction thereof, to and including $500,000
Building Permit Fee — valuation $500,001-$1,000,000$3,560 for the first $500,000 plus $5.25 for each additional $1,000 or fraction thereof, to and including $1,000,000
Building Permit Fee — valuation $1,000,001 and up$6,170 for the first $1,000,000 plus $4.05 for each additional $1,000 or fraction thereof
Building Plan Review Fee65% of Building Permit FeeNon-refundable regardless of whether permit is issued or withdrawn
Plumbing Permit Fee (included with Building Permit)15% of Building Permit Fee
Mechanical Permit Fee (included with Building Permit)15% of Building Permit Fee
Plumbing or Mechanical Plan Review Fee (with Building Permit)65% of Plumbing or Mechanical Permit Fee
Use Tax (construction materials, projects $250,000+)4%Effective January 1, 2025, per Community Development Fee Schedule and Town sales/use tax rules

Addition / Remodel Permit

Verified

Required anytime a project affects the existing structure or exterior of a property in Avon, including new windows, doors, siding, decks, and similar work, per the Town's own 'Common Building Permit Types' guide. Reviewed under the 2021 IRC as locally adopted; projects with exterior changes may additionally require Planning Division review.

Verified 2026-07-06 · Source

Requirements

  • Required anytime a project affects the existing structure or exterior of a property (new windows, doors, siding, decks, etc.)
  • Depending on scope, the project may need to go through Planning Division review initially (Minor or Major Development Plan)
  • Cosmetic-only interior work (cabinets, countertops, flooring, interior paint) does NOT require a building permit
  • Electrical work included in an addition/remodel scope must still be separately permitted through DORA, not the Town
  • Contractor Business License required through Cloudpermit

Required documents

  • RequiredBuilding Permit Application (Cloudpermit)Submitted through us.cloudpermit.com/avon
  • RequiredFull-Size Paper Plan SetRequired for architect/engineer-stamped remodel projects before review begins

Fee schedule

Fee typeAmountNotes
Building Permit Fee (same valuation-based schedule as new construction)$50.00 minimum, scaling per the valuation tiers in the Community Development Fee Schedule (Exhibit A to Resolution 24-11)
Building Plan Review Fee65% of Building Permit FeeNon-refundable regardless of outcome
Plumbing/Mechanical Permit Fee (if applicable, included with Building Permit)15% of Building Permit Fee each

Electrical Permit

Verified

Electrical permits are NOT issued or administered by the Town of Avon. Per the Town's own 'Common Building Permit Types' guide: 'The Town of Avon does not manage electrical permits, these go through the Colorado Department of Regulatory Agencies' (DORA). This is confirmed independently by the Town's own Building Permit Fee Schedule footnote: 'Electrical Permits and Fees are administered by the Colorado Department of Regulatory Agencies.' This is a materially different model from Vail (same county), which issues its own electrical permits locally.

Verified 2026-07-06 · Source

Requirements

  • Electrical work in Avon requires a permit issued directly through the Colorado Department of Regulatory Agencies (DORA), Division of Professions and Occupations, State Electrical Board — NOT through the Town of Avon
  • Governed by the 2023 NEC as adopted by the Town for code-compliance purposes, but permitting/inspection authority itself sits with the state, not the Town
  • Signs that are illuminated also require a DORA electrical permit, per the Town's guide
  • New Structure and PV (solar) permits still require a separate DORA electrical permit and DORA final electrical inspection even though the Town issues the building/mechanical/plumbing portions

Required documents

  • RequiredColorado DORA Electrical Permit ApplicationSubmitted directly to the Colorado Department of Regulatory Agencies, Division of Professions and Occupations — not to the Town of Avon

Fee schedule

Fee typeAmountNotes

Plumbing Permit

Verified

Required for new plumbing installation or changes to existing plumbing in the Town of Avon. Issued by the Building Division as part of, or alongside, the Building Permit; governed by the 2021 International Plumbing Code (IPC) as adopted. Cosmetic fixture swaps (e.g., replacing an existing toilet or sink) typically do not require a permit.

Verified 2026-07-06 · Source

Requirements

  • Required anytime new plumbing is added to a structure, or changes are made to existing plumbing
  • Cosmetic-only fixture replacement (e.g., swapping an existing toilet or sink with no other changes) typically does NOT require a permit — confirm with staff if unsure
  • Governed by the 2021 IPC as adopted by the Town of Avon
  • When bundled with a Building Permit (new construction or addition/remodel), billed as a percentage add-on rather than a standalone valuation-based fee

Required documents

  • RequiredBuilding/Plumbing Permit Application (Cloudpermit)Submitted through us.cloudpermit.com/avon

Fee schedule

Fee typeAmountNotes
Plumbing Permit Fee (with Building Permit)15% of Building Permit FeeCommunity Development Fee Schedule, Exhibit A to Resolution 24-11
Plumbing Plan Review Fee (with Building Permit)65% of Plumbing Permit FeeNon-refundable regardless of outcome

Mechanical / Gas Permit

Verified

Required for work on mechanical systems in the Town of Avon, per the Town's own guide (HVAC system replacement, gas line repair, etc.). Governed by the 2021 International Mechanical Code (IMC) and 2021 International Fuel Gas Code (IFGC) as adopted. Billed as a percentage add-on to the Building Permit fee.

Verified 2026-07-06 · Source

Requirements

  • Required if work is being performed on mechanical systems, e.g. HVAC system replacement, gas line repair
  • Governed by the 2021 IMC and 2021 IFGC as adopted by the Town of Avon
  • Gas fireplace installation/repair may require a Fireplace Permit (a related but distinct category on the Town's own permit-types guide) which may also require a plumbing permit depending on scope

Required documents

  • RequiredBuilding/Mechanical Permit Application (Cloudpermit)Submitted through us.cloudpermit.com/avon

Fee schedule

Fee typeAmountNotes
Mechanical Permit Fee (with Building Permit)15% of Building Permit FeeCommunity Development Fee Schedule, Exhibit A to Resolution 24-11
Mechanical Plan Review Fee (with Building Permit)65% of Mechanical Permit FeeNon-refundable regardless of outcome

Replacement / New Roof Permit

Verified

Required anytime a roof is repaired or replaced in the Town of Avon, per the Town's own permit-types guide. May require Planning Division review depending on the extent of work. Reviewed under the 2021 IRC/IBC as adopted, with the Town's snow-load design criteria applicable to structural roof work.

Verified 2026-07-06 · Source

Requirements

  • Required anytime you are repairing or replacing your roof
  • May need to go through Planning Division review depending on the extent of work being done
  • Structural roof work should account for the Town's Minimum Roof Snow Load design criteria: 90 psf above 8,200 ft elevation, 75 psf below

Required documents

  • RequiredBuilding/Roofing Permit Application (Cloudpermit)Submitted through us.cloudpermit.com/avon

Fee schedule

Fee typeAmountNotes
Building Permit Fee (valuation-based, same schedule as new construction)$50.00 minimum, scaling per the valuation tiers in the Community Development Fee Schedule (Exhibit A to Resolution 24-11)No separate flat re-roof fee is published; billed under the general valuation-based Building Permit Fee schedule
Building Plan Review Fee65% of Permit FeeNon-refundable regardless of outcome

Solar Photovoltaic (PV) Permit

Verified

Required for installing a photovoltaic system on a home's roof in the Town of Avon, per the Town's own permit-types guide. Requires a Town building permit AND a fire department permit/final inspection (Eagle River Fire Protection District) AND a separate electrical permit/final inspection through DORA (state) — three distinct authorities for one project.

Verified 2026-07-06 · Source

Requirements

  • Requires a Town of Avon building permit for the PV installation itself
  • Requires a separate permit and final inspection through the fire department (Eagle River Fire Protection District)
  • Requires a separate electrical permit and final inspection through the Colorado Department of Regulatory Agencies (DORA) — NOT the Town
  • Flat Solar PV Fee applies at the Town level (distinct from the general valuation-based Building Permit Fee table used for other permit types)

Required documents

  • RequiredBuilding Permit Application — Solar PV scope (Cloudpermit)Submitted through us.cloudpermit.com/avon for the Town's building-permit portion
  • RequiredFire Department Permit (ERFPD)Required for the solar electrical PV scope per the Eagle River Fire Protection District
  • RequiredDORA Electrical PermitRequired separately through the Colorado Department of Regulatory Agencies; not issued by the Town

Fee schedule

Fee typeAmountNotes
Solar PV Fee — ResidentialFlat fee of $500Community Development Fee Schedule, Exhibit A to Resolution 24-11
Solar PV Fee — CommercialFlat fee of $1,000Community Development Fee Schedule, Exhibit A to Resolution 24-11

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Avon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Later version (2026-07-07) →View current record →All versions →

Permalink: /colorado/eagle-county/avon-co/as-of/2026-07-06/

Snapshot date: 2026-07-06

Commit: 8e52a49

Reproducible from PermitBase’s version-controlled dataset, commit 8e52a49.