This is PermitBase’s published record for Gypsum as of 2026-07-06. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Gypsum building permits
VerifiedGypsum, Colorado — as published 2026-07-06.
Verified 2026-07-06 · Source
Codes adopted
Permit types & fees
Residential Building Permit (New Construction)
VerifiedRequired for new construction of single-family homes, duplexes, and townhomes in the Town of Gypsum. Reviewed under the 2021 IRC/IBC as locally adopted plus the Town's published design criteria (40 psf ground snow load, 90 mph wind design exposure, 42-inch frost depth, Seismic Design Category C). Issued by the Community Development Department, Building Department, after Design Review Board/HOA approval where applicable.
Verified 2026-07-06 · Source
Requirements
- Design Review Board (DRB) or Homeowners Association (HOA) approval required before building permit submittal, unless the project is within Eagle River Estate or Bertroch (which do not require this step) — a letter or stamped approved plan set must be provided at submittal
- Plans must comply with the 2021 IRC/IBC as adopted, and must meet the Town's design criteria: 40 psf ground snow load, 90 mph wind design exposure, 42-inch minimum frost depth, Seismic Design Category C
- Soils testing required; if bearing values test below 1,500 PSF, an engineered, stamped foundation plan is required
- Full plan set required: title block with legal description/subdivision/lot-block/address/preparer/owner, site plan (preferred 1"=10' scale) showing easements/utilities/landscaping/drainage/existing structures, footing and foundation plans, framing plans with sections and opening locations, floor plans (room usage, windows/doors, drywall type, electrical outlets, smoke detectors, fire-rated walls, exit corridors), elevations, building/wall sections foundation-to-roof, and stair details with rise/run/headroom
- All contractors must hold a current Town of Gypsum Contractor's License ($152/year per the 2025 fee schedule) in addition to any required Colorado state trade license
- Improvement Location Survey (ILS) required before Certificate of Occupancy is issued
- Applications submitted via the Town's online Building Permit & Plan Submittal portal (Streamline); separate permits required for Electrical, Plumbing, and Mechanical work
- Permit becomes null and void if work is not commenced within 180 days of issuance
Required documents
- RequiredBuilding Permit ApplicationSubmitted through the Town of Gypsum online Building Permit & Plan Submittal portal; requires owner, contractor, architect/engineer details, use classification, class of work, valuation, and DRB/HOA approval status
- RequiredFull Digital Plan Set (PDF)Site plan, footing/foundation plans, framing plans, floor plans, elevations, building/wall sections, stair details, per the Plan Requirements page
- RequiredDRB/HOA Approval Letter or Stamped PlansRequired prior to Town submittal for all parcels outside Eagle River Estate and Bertroch
- RequiredSoils ReportRequired for new construction; triggers an engineered stamped foundation plan if bearing values are below 1,500 PSF
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Not published in any fetchable Town document as of this review | The Town's own 2025 Annual Fee Schedule PDF is explicitly labeled 'partial' by the Town and does not include a building-permit valuation table; the governing table is referenced as living in Title 15 of the Municode-hosted Municipal Code, which serves its text only through a JavaScript-rendered, access-controlled application — both a direct fetch and a dated Wayback snapshot returned no recoverable section text. Genuinely unresolved after exhausting the chase; not estimated or backfilled from a peer jurisdiction. |
| Contractor's License (annual) | $152 | 2025 Annual Fee Schedule, Town of Gypsum, effective 1/1/2025, adopted 12/10/2024 |
| Additional/Re-inspection Fee | $60.00 per inspection | Base permit fee includes a maximum of four inspections; each additional inspection or re-inspection is billed separately and due before the inspection |
| Permit Late Fee | 18% per year (1.5% per month) | 2025 Annual Fee Schedule, Community Development section |
Residential Addition / Remodel Permit
VerifiedRequired for additions and interior remodels/finishes to existing single-family, duplex, and townhome structures in Gypsum, including basement finishes, garages, patio covers, and uncovered decks, each covered by a dedicated 2021 Town building guide. Reviewed under the 2021 IRC as locally adopted.
Verified 2026-07-06 · Source
Requirements
- DRB/HOA approval required before submittal if the project includes exterior changes and the parcel is outside Eagle River Estate or Bertroch
- Basement Finish, Residential Ramp, Residential Garage, Patio Cover, and Uncovered Deck projects are each governed by a Town-published 2021 guide document listing scope-specific requirements
- Soils testing and engineered foundation plans required if the addition includes new footings and bearing values test below 1,500 PSF
- All contractors must hold a current Town of Gypsum Contractor's License
Required documents
- RequiredBuilding Permit ApplicationSubmitted via the Town's online Building Permit & Plan Submittal portal
- OptionalScope-Specific Building GuideBasement Finish Guide, Residential Garage Guide, Patio Cover Guide, or Uncovered Decks Guide (all 2021 editions), matched to project scope
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (valuation-based) | Not published in any fetchable Town document as of this review | Same gap as new construction — the governing valuation table lives in Title 15 of the Municode-hosted Municipal Code, which returned no recoverable text via direct fetch or Wayback snapshot |
| Additional/Re-inspection Fee | $60.00 per inspection | Base permit fee includes a maximum of four inspections |
Electrical Permit
VerifiedRequired for installation, alteration, or repair of electrical systems in Gypsum, issued as a separate permit from the general Building Permit per the Town's own application form. Governed by the 2023 NEC as adopted.
Verified 2026-07-06 · Source
Requirements
- Issued as a standalone permit, separate from the Building Permit, per the Building Permit Application's own notice that 'separate permits are required for Electrical, Plumbing, Mechanical'
- Governed by the 2023 NEC as adopted by the Town of Gypsum
- Contractors must hold a current Town of Gypsum Contractor's License; applicable Colorado state electrical licensure also required
- For smaller scope work not requiring plans (e.g., electrical panel upgrades), one-time permit applications are available per the Building Permit Application page
Required documents
- RequiredElectrical Permit ApplicationSubmitted via the Town of Gypsum online Building Permit & Plan Submittal portal, or as a one-time permit application for smaller scopes
- RequiredTown of Gypsum Contractor's LicenseRequired for all contractors performing electrical work in Town
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit Fee | Not published in any fetchable Town document as of this review | No trade-specific electrical fee table was recoverable via the Town's site, its 2025 fee schedule PDF (labeled 'partial' by the Town, containing no permit valuation tables), or Title 15 of the Municipal Code (Municode SPA, no text recoverable via direct fetch or Wayback) |
| Additional/Re-inspection Fee | $60.00 per inspection | General Town of Gypsum inspection fee, applies across trade permits per the Inspections page |
Plumbing Permit
VerifiedRequired for installation, alteration, or repair of plumbing systems in Gypsum, issued as a separate permit from the general Building Permit. Governed by the 2021 International Plumbing Code (IPC) as adopted.
Verified 2026-07-06 · Source
Requirements
- Issued as a standalone permit, separate from the Building Permit, per the Town's own application form
- Governed by the 2021 IPC as adopted by the Town of Gypsum
- Contractors must hold a current Town of Gypsum Contractor's License; applicable Colorado state plumbing licensure also required
- One-time permit applications available for smaller scopes not requiring plans, such as plumbing fixture replacement
Required documents
- RequiredPlumbing Permit ApplicationSubmitted via the Town's online Building Permit & Plan Submittal portal, or as a one-time permit application for smaller scopes
- RequiredTown of Gypsum Contractor's LicenseRequired in addition to Colorado state plumbing licensure
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plumbing Permit Fee | Not published in any fetchable Town document as of this review | No trade-specific plumbing fee table was recoverable via the Town's site, its 2025 partial fee schedule, or Title 15 (Municode SPA, no text recoverable) |
| Additional/Re-inspection Fee | $60.00 per inspection | General Town of Gypsum inspection fee |
Mechanical / HVAC Permit
VerifiedRequired for heating, cooling, and ventilation equipment installation or replacement in Gypsum, issued as a separate permit from the general Building Permit. Governed by the 2021 International Mechanical Code (IMC) and 2021 International Fuel Gas Code (IFGC) as adopted.
Verified 2026-07-06 · Source
Requirements
- Issued as a standalone permit, separate from the Building Permit, per the Town's own application form
- Governed by the 2021 IMC and 2021 IFGC as adopted by the Town of Gypsum
- All contractors must hold a current Town of Gypsum Contractor's License; applicable Colorado state trade licensure where required
Required documents
- RequiredMechanical Permit ApplicationSubmitted via the Town's online Building Permit & Plan Submittal portal
- RequiredTown of Gypsum Contractor's LicenseRequired for all contractors performing mechanical work
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mechanical Permit Fee | Not published in any fetchable Town document as of this review | No trade-specific mechanical fee table was recoverable via the Town's site, its 2025 partial fee schedule, or Title 15 (Municode SPA, no text recoverable) |
| Additional/Re-inspection Fee | $60.00 per inspection | General Town of Gypsum inspection fee |
Roofing Permit (Re-Roof)
VerifiedRequired for re-roofing work in the Town of Gypsum. Smaller re-roof projects that do not require plans are eligible for the Town's one-time permit application process rather than the full plan-submittal portal. Governed by the 2021 IRC/IBC as adopted.
Verified 2026-07-06 · Source
Requirements
- A new roof is explicitly listed by the Town as an example of a smaller project eligible for a one-time permit application (i.e., not requiring a full plan set), per the Building Permit Application page
- DRB/HOA approval may still be required for parcels outside Eagle River Estate/Bertroch since re-roofing can be considered exterior work — confirm with the applicable DRB/HOA
- All contractors must hold a current Town of Gypsum Contractor's License
Required documents
- RequiredOne-Time Permit Application (Re-Roof)Used for re-roof projects not requiring a full plan set, per the Building Permit Application page
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roofing Permit Fee | Not published in any fetchable Town document as of this review | No re-roof-specific or valuation-based fee table was recoverable via the Town's site, its 2025 partial fee schedule, or Title 15 (Municode SPA, no text recoverable) |
Accessory Dwelling Unit (ADU) Permit
VerifiedRequired for construction of a new Accessory Dwelling Unit, or to bring an existing non-approved ADU into compliance, on a single-family lot in Gypsum. Processed alongside a standard Building Permit for the structure itself, plus a dedicated ADU application, deed restriction, and utility documentation.
Verified 2026-07-06 · Source
Requirements
- Maximum size: 800 sq ft or 50% of the primary dwelling's floor area, whichever is smaller
- Only one ADU permitted per lot; not permitted in multi-family or mobile home park settings
- Allowed forms: detached, attached, interior (upper or lower unit), above-garage, or garage conversion; mobile homes, travel trailers, and RVs are prohibited as an ADU
- Property owner must reside on-site; the ADU cannot be subdivided or sold separately from the primary home
- Maximum two parking spaces per ADU, in a garage or driveway (limited on-street exception)
- Separate trash service subscription required for the ADU
- Water/sewer: monthly service fee applies; septic/well documentation required if Town water/sewer service is unavailable
- Upon sale of the property, the new owner must complete a transfer of the ADU's deed restriction and records (typically handled by the realtor)
Required documents
- RequiredADU Application / Summary LetterDescribes the proposed ADU scope and configuration
- RequiredSite PlanShows the ADU's location relative to the primary dwelling and lot lines
- RequiredBuilding PermitCan be processed simultaneously with the ADU-specific application
- RequiredADU Deed Restriction FormRecorded against the property; required for all ADUs
- RequiredADU Water, Sewer & Trash FormDocuments utility arrangements for the ADU
- OptionalADU Deed Restriction Transfer FormRequired upon sale of a property with an existing approved ADU
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| New ADU Construction Fee | $250 | Town of Gypsum Accessory Dwelling Units page |
| Existing Non-Approved ADU (bring into compliance) | $500 | — |
| Transfer of Existing Approved ADU (new owner) | $50 re-inspection fee | — |
| Deed Restriction Recording | $43 | — |
| Trash Service Setup | $110 (container plus monthly fee) | — |
| Building Permit Fee (for the ADU structure itself) | Not published in any fetchable Town document as of this review | Same valuation-table gap as the general Residential Building Permit |
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gypsum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.