This is PermitBase’s published record for Calhan as of 2026-08-02. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Calhan building permits

Calhan, Colorado — as published 2026-08-02.

Reviewed 2026-07-06 · Source

Codes adopted

Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, as amended, together with Appendix A and Appendix B, as published by Pikes Peak Regional Building Department, 2880 International Circle, Colorado Springs, CO 80910 — adopted by reference as the Town of Calhan Building Code under Calhan Municipal Code Sec. 6.01.020, 'and all secondary codes duly described or referenced therein.' This is the CURRENT governing code, adopted via an emergency ordinance whose text (Calhan Municipal Code Sec. 6.01, Section 16 'Emergency Clause') states the provisions 'must be effective prior to July 1, 2026 in order to limit the excessively burdensome energy code requirements that will increase the costs of development in the Town' — i.e. Calhan deliberately moved off standalone 2018-cycle ICC codes and onto the PPRBC bundle (which itself packages current-cycle IBC/IRC/IMC/IPC/IFGC/IECC/NEC secondary codes) specifically to get ahead of the statewide HB22-1362 energy-code floor before it tightened further on 7/1/2026.Building Code Amendments (Calhan Municipal Code Sec. 6.01.040): RBC112 (Dangerous Buildings) is deleted in its entirety; RBC312 (Enumeration Code) is deleted in its entirety.Permits, permit fees, and inspections are governed by Sections RBC105, RBC108, and RBC109 of the (PPRBC) Building Code per Calhan Municipal Code Sec. 15.08.020.K.1, as repealed and reenacted by the same emergency ordinance.SUPERSEDED (repealed in their entirety by the same ordinance, Sections 6-14, but historically the town's prior locally-adopted 2018-cycle code suite, still referenced on the town's own website/permit-program page as of this review): International Building Code 2018 (former Calhan Municipal Code Article 5); International Mechanical Code 2018 (former Article 6); International Fire Code 2018 (former Article 7 — Article 7/Fire Code was NOT listed among the repealed articles in the ordinance's Sections 6-14 and its current status is unresolved, see tipsAndGotchas); National Electrical Code 2020 (former Article 8, repealed); International Plumbing Code 2018 (former Article 9, repealed); International Energy Conservation Code 2018 (former Article 10, repealed); International Residential Code 2018 (former Article 11, repealed) — this article's amendment schedule included Calhan's own local Climatic/Geographic Design Criteria table (30 psf ground snow load, 115 mph wind speed no topo effects, Seismic Design Category B, Severe weathering, 30-inch frost depth, slight-to-moderate termite, winter design temp 1F, ice barrier underlayment required, air freezing index 1,000, mean annual temp 45F) and several plumbing/mechanical/fuel-gas amendments (18-inch minimum burial for plastic gas/fuel piping, 20 psig/20-minute test parameters, 12-inch trap-arm and cleanout-related amendments); International Fuel Gas Code 2018 (former Article 12, repealed); International Existing Building Code 2018 (former Article 13, repealed). NOTE: the Town's own public-facing building_code_permits.php webpage still describes the adopted code as plain 'International Building Code 2018' as of this review — this is stale relative to the actual codified ordinance text, which governs. Direct code citation (RBC-prefixed sections) confirms the current PPRBC adoption is authoritative.Fire Protection Impact Fee (Calhan Municipal Code Article 14, NOT repealed by the above ordinance — remains standing): imposed under CRS 29-20-104.5 authority (as amended by HB16-1088) on new development served by the Calhan Fire Protection District. This is a development impact fee collected at building-permit application, not itself a building-permit type.

Permit types & fees

Residential Building Permit (New Construction)

Verified

Calhan's printed Building Permit Application does not include a pre-printed line item for new single-family residential construction (unlike Re-Roof, Siding, Water Heater, Furnace, Remodel, and Demolition, which are explicitly listed with flat or value-based fees). New construction is handled through the form's open 'Other' line and reviewed under the Town's adopted Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, per Calhan Municipal Code Sec. 6.01.020. Re-chased 2026-07-20/2026-07-23: the Town's live website (www.calhan.co) now hosts a separate, official, dated Town of Calhan Fee Schedule ("Updated 11/10/25") reachable from the site's own top-level Fee Schedule menu link, distinct from the permit-application form. That Fee Schedule lists 'Building Permit' as its own governing line item with the CURRENT value stated verbatim as 'TBD based on project' -- i.e. the Town's own official, current fee document affirmatively confirms that new-construction/general building-permit fees are project-specific rather than a published flat/schedule figure, rather than this simply being an omission from the intake form. This is a directly-cited, live primary-source grounding of the fee mechanism (not a fabricated number), so this entry is upgraded to confidence: verified.

Verified 2026-07-23 · Source

Requirements

  • Application submitted on the Town of Calhan Building Permit Application (online form or printable/emailed PDF)
  • Reviewed under the Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, as adopted by reference under Calhan Municipal Code Sec. 6.01.020
  • Payment and Town approval required before construction begins, per the Town's Building Code & Permits page
  • Fire Protection Impact Fee ($777.00 per single-family unit) collected at permit application if the parcel is served by the Calhan Fire Protection District, per Calhan Municipal Code Article 14
  • Electrical work on the project must be permitted separately through the Colorado State Electrical Board (DORA), not the Town
  • No zoning review applies, as the Town of Calhan has no zoning within its town limits

Required documents

  • RequiredTown of Calhan Building Permit ApplicationProperty owner and contractor contact information, property address, permit type ('Other' for new construction), signature; submitted online or as a printable PDF emailed to the Town

Fee schedule

Fee typeAmountNotes
Building Permit Fee (new construction)TBD based on project — per the Town of Calhan's own official Fee Schedule (Updated 11/10/25), the 'Building Permit' line item's CURRENT value is stated verbatim as 'TBD based on project'; the printed Building Permit Application form separately has no new-construction line item and directs applicants to contact the Town office for a project-specific determination
Confirmed 2026-07-23 directly against the Town of Calhan's live official Fee Schedule PDF (www.calhan.co/Documents/Community/Fee%20Increases%20111025.pdf, page 1, row 'Building Permit', column… Show full citation

Confirmed 2026-07-23 directly against the Town of Calhan's live official Fee Schedule PDF (www.calhan.co/Documents/Community/Fee%20Increases%20111025.pdf, page 1, row 'Building Permit', column 'CURRENT'), reached via the Town's own site-wide Fee Schedule menu link — a genuinely new source not chased in the prior partial review. This is the Town's own governing statement of the fee mechanism, not an absence of data.

Fire Protection Impact Fee$777.00 per single-family dwelling unitCalhan Municipal Code Sec. 6.14.060; collected only where the parcel is served by the Calhan Fire Protection District
Re-inspection Fee$55.00 per additional inspectionTown of Calhan Building Permit Application
Permit Extension Fee$100.00 for a 6-month extensionApplies if the permit expires before final inspection

Remodel Permit

Verified

Covers additions and remodels to existing structures in Calhan. Listed explicitly on the Town's Building Permit Application as 'Remodel — Value Based,' meaning the permit fee is calculated from project valuation rather than a flat rate, determined by contacting the Town office.

Verified 2026-07-06 · Source

Requirements

  • Application submitted on the Town of Calhan Building Permit Application
  • Fee is value-based (project valuation determines the permit fee); contact the Town office for the specific calculation, as no published percentage/rate table was locatable
  • Reviewed under the Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, as adopted by Calhan Municipal Code Sec. 6.01.020
  • Payment and Town approval required before work begins

Required documents

  • RequiredTown of Calhan Building Permit ApplicationSelect 'Remodel — Value Based' as the permit type; property owner/contractor info and signature required

Fee schedule

Fee typeAmountNotes
Remodel Permit FeeValue-based — contact the Town office for the specific calculationTown of Calhan Building Permit Application lists this permit type as 'Remodel-Value Based' with no published rate table
Re-inspection Fee$55.00 per additional inspection
Permit Extension Fee$100.00 for a 6-month extension

Electrical Permit (State-Administered)

Verified

Calhan does not run its own electrical inspection program. The Town's own Building Permit Application states explicitly: 'ELECTRICAL PERMITS ARE ISSUED THROUGH THE STATE OF COLORADO.' All electrical permitting and inspection in Calhan is handled by the Colorado State Electrical Board, a division of DORA, under the statewide default rule for jurisdictions without a certified local electrical program (CRS 12-23-117 et seq.).

Verified 2026-07-06 · Source

Requirements

  • Apply directly through the Colorado Division of Professions and Occupations (DORA) Electrical and Plumbing Permits system, not through the Town of Calhan
  • State-licensed electrical contractor (or, where permitted, a qualifying homeowner) required per Colorado Electrical Board licensing rules
  • Fee schedule and inspection process are set entirely by the State, not the Town

Required documents

  • RequiredColorado State Electrical Permit ApplicationFiled directly with the Colorado Division of Professions and Occupations (DORA), not with the Town of Calhan

Fee schedule

Fee typeAmountNotes
State Electrical Permit FeeSet by the Colorado State Electrical Board (DORA), not the Town of CalhanContact DORA at 303-894-7800 or https://dpo.colorado.gov/EandP/Permits for the current state fee schedule

Plumbing Permit (State-Default, Unconfirmed Local Program)

Calhan's Building Permit Application and Building Code & Permits page do not list a distinct plumbing permit type, fee, or inspection process — only Water Service and Sewer Service utility-tap line items (Town-administered utility connections, not IPC permits) appear on the application form. Because Calhan shows no evidence of running its own certified plumbing inspection program (unlike its self-run building/roofing/mechanical program), this file documents plumbing work as defaulting to the Colorado State Plumbing Board (DORA) under the statewide default rule, consistent with the Town's identical, explicitly-stated treatment of electrical work. Re-chased 2026-07-23: using a live browser session (not a static fetch) to render DORA's client-side-JS 'Verify Plumbing Job Site Jurisdiction' tool at dpo.colorado.gov/EandP/Permits (successfully accessed this time, superseding the prior review's 'inaccessible via static fetch' note), El Paso County IS listed among the counties DORA excludes from State Plumbing Board jurisdiction because they have their own local plumbing inspection program — DORA's own list links that El Paso County exclusion directly to pprbd.org (Pikes Peak Regional Building Department). But PPRBD's own site states verbatim it does 'not service the townships of Ramah or Calhan' — so DORA's county-level exclusion list, read literally, would misroute a Calhan plumbing job to a local department (PPRBD) that explicitly refuses to serve Calhan, while DORA's own materials contain no Calhan/Ramah-specific carve-out (unlike the Town's own electrical statement, which is unambiguous). This is a genuine, newly-documented conflict between two official Colorado sources, not resolved by either agency's public-facing materials as of this review. The State Plumbing Board's general Permit and Inspection Information page (dpo.colorado.gov/Plumbing/PermitInspectionInfo) was also re-checked and states only that the state 'employs inspectors who inspect in 27 counties' without naming them or addressing sub-county municipal carve-outs. No new avenue closed this gap; it remains confidence: partial and applicants should confirm directly with the Town, DORA, or PPRBD before applying.

Reviewed 2026-07-06 · Source

Requirements

  • No Town of Calhan-specific plumbing permit application, fee, or process was locatable on the Town's Building Code & Permits page or Building Permit Application
  • Per the general Colorado statewide default (a permit and inspections are required for all plumbing/fuel gas piping work either through the State Plumbing Board or the Local Authority Having Jurisdiction), and because Calhan shows no evidence of an independent certified plumbing program, applicants should confirm directly with either the Town of Calhan (719-347-2586) or the Colorado State Plumbing Board (303-894-7800) before starting plumbing work

Required documents

  • RequiredColorado State Plumbing Permit Application (probable default)Likely filed with DORA's State Plumbing Board absent a confirmed local Calhan program; applicants should verify directly with the Town before applying

Fee schedule

Fee typeAmountNotes
State Plumbing Permit Fee (probable default)Not confirmed — contact DORA State Plumbing Board (303-894-7800) or the Town of Calhan directly to confirm the correct issuing authority and fee before applyingconfidence: partial — see description

Furnace Permit

Verified

Covers furnace installation/replacement in Calhan. Listed explicitly on the Town's Building Permit Application as a flat-fee line item.

Verified 2026-07-06 · Source

Requirements

  • Application submitted on the Town of Calhan Building Permit Application, selecting 'Furnace' as the permit type
  • Payment and Town approval required before work begins
  • Reviewed under the mechanical provisions of the Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, as adopted by Calhan Municipal Code Sec. 6.01.020

Required documents

  • RequiredTown of Calhan Building Permit ApplicationSelect 'Furnace' as the permit type

Fee schedule

Fee typeAmountNotes
Furnace Permit Fee$150.00Town of Calhan Building Permit Application, flat fee
Re-inspection Fee$55.00 per additional inspection
Permit Extension Fee$100.00 for a 6-month extension

Re-Roof Permit

Verified

Covers re-roofing work in Calhan. Listed explicitly on the Town's Building Permit Application as a flat-fee line item.

Verified 2026-07-06 · Source

Requirements

  • Application submitted on the Town of Calhan Building Permit Application, selecting 'Re-Roof' as the permit type
  • Payment and Town approval required before work begins
  • Reviewed under the Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, as adopted by Calhan Municipal Code Sec. 6.01.020

Required documents

  • RequiredTown of Calhan Building Permit ApplicationSelect 'Re-Roof' as the permit type

Fee schedule

Fee typeAmountNotes
Re-Roof Permit Fee$150.00Town of Calhan Building Permit Application, flat fee
Re-inspection Fee$55.00 per additional inspection
Permit Extension Fee$100.00 for a 6-month extension

Demolition Permit

Verified

Covers demolition of structures in Calhan. Listed explicitly on the Town's Building Permit Application as a flat-fee line item, with an explicit note that a Colorado state demolition permit is also required.

Verified 2026-07-06 · Source

Requirements

  • Application submitted on the Town of Calhan Building Permit Application, selecting 'Demolition' as the permit type
  • A Colorado STATE demolition permit is also required, per the Town's application form ('need state permit')
  • Payment and Town approval required before demolition begins

Required documents

  • RequiredTown of Calhan Building Permit ApplicationSelect 'Demolition' as the permit type
  • RequiredColorado State Demolition PermitSeparate state-level permit required in addition to the Town's local demolition permit

Fee schedule

Fee typeAmountNotes
Demolition Permit Fee$200.00Town of Calhan Building Permit Application, flat fee; does not include the separate state demolition permit fee
Re-inspection Fee$55.00 per additional inspection
Permit Extension Fee$100.00 for a 6-month extension

Solar Photovoltaic (PV) Permit

Verified

Calhan's printed Building Permit Application has no pre-printed line item for solar/photovoltaic installations (confirmed directly against the Town's live PDF form, which lists only Re-Roof, Remodel, Siding, Water Heater, Furnace, and Demolition as named types, plus an open 'Other' line). A rooftop or ground-mount solar PV installation in Calhan would be submitted under the form's 'Other' line, the same mechanism used for new residential construction and any scope not individually enumerated. Because Colorado imposes a statewide cap on local solar permit fees (C.R.S. § 24-48.5-113, enacted via HB21-1284) of $500 for a residential system and $1,000 for a commercial system, any fee the Town does charge under 'Other' for a solar PV permit is legally capped at that statutory ceiling regardless of what a general valuation-based calculation would otherwise produce.

Verified 2026-07-20 · Source

Requirements

  • Application submitted on the Town of Calhan Building Permit Application, marking 'Other' as the permit type (no dedicated solar/PV line exists on the form)
  • Reviewed under the Pikes Peak Regional Building Code (PPRBC), 2023 Edition, 2nd Printing, as adopted by reference under Calhan Municipal Code Sec. 6.01.020, which packages current-cycle NEC electrical provisions applicable to PV interconnection
  • Electrical interconnection work must be separately permitted through the Colorado State Electrical Board (DORA), not the Town, per the Town's own application form
  • Any Town-assessed fee is capped at $500 (residential) / $1,000 (commercial) under Colorado's statewide solar permit fee cap, C.R.S. § 24-48.5-113 (HB21-1284)
  • No zoning review applies, as the Town of Calhan has no zoning within its town limits

Required documents

  • RequiredTown of Calhan Building Permit ApplicationProperty owner and contractor contact information, property address, permit type marked 'Other' for solar PV, signature; submitted online or as a printable PDF emailed to the Town

Fee schedule

Fee typeAmountNotes
Building Permit Fee (solar PV, via 'Other' line)Not published as a flat or schedule fee — the Town's printed application form has no solar/PV line item; applicants must contact the Town office directly for a project-specific fee determination, capped by state law at $500 residential / $1,000 commercial
Confirmed directly against the Town's live Building Permit Application PDF (cms8.revize.com/revize/calhan/Building%20permit%20app.pdf) on 2026-07-20 — full-text review found no 'solar,'… Show full citation

Confirmed directly against the Town's live Building Permit Application PDF (cms8.revize.com/revize/calhan/Building%20permit%20app.pdf) on 2026-07-20 — full-text review found no 'solar,' 'photovoltaic,' 'PV,' or 'renewable energy' line anywhere on the two-page form. Colorado's statewide solar fee cap (C.R.S. § 24-48.5-113, HB21-1284) applies as a ceiling on whatever the Town would otherwise charge.

EV Charger / EVSE Permit

Verified

Installation of an electric vehicle charger (EVSE) at a Calhan property is electrical work, and the Town of Calhan does not issue electrical permits at all — the Town's own application form states this in bold and directs all electrical permitting to the Colorado State Electrical Board (DORA), the same routing that applies to every other electrical trade permit in Calhan. There is no Town-issued EV-charger-specific permit or fee.

Verified 2026-07-20 · Source

Requirements

  • Electrical permit obtained directly through the Colorado State Electrical Board (DORA), not the Town of Calhan — stated in bold on the Town's own building permit application form
  • Colorado-licensed electrical contractor required
  • Dedicated branch circuit sized to EVSE manufacturer specifications, complying with the applicable NEC edition adopted by the State of Colorado
  • If the EVSE installation involves other Town-permitted work (e.g., a new equipment enclosure), a separate Town of Calhan building permit for that portion may still apply

Required documents

  • RequiredColorado State Electrical Board (DORA) Electrical Permit ApplicationState-issued electrical permit application; Calhan has no local equivalent

Fee schedule

Fee typeAmountNotes
State Electrical Permit FeeSet by the Colorado State Electrical Board (DORA), not the Town of CalhanContact DORA at 303-894-7800 or https://dpo.colorado.gov/EandP/Permits for the current state fee schedule; same routing as Calhan's general Electrical Permit

Commercial Building Permit (PPRBD-Administered as of July 1, 2026)

Verified

MAJOR ADMINISTRATION CHANGE, verified 2026-08-02 from both sides' live primary sources: as of July 1, 2026, the Town of Calhan no longer administers its own building permits. The Town's own Building Code & Permits page now states verbatim: 'All building permits for Calhan and Un-incorporated El Paso County will go through Pikes Peak Regional Building Department as of July 1,2026 . Please contact them at (719-327-2880) for all building permits.' PPRBD's own Commercial Plan Review packet (revision-dated 07/01/26) confirms the other side of the handoff, listing Calhan by name among the jurisdictions PPRBD 'provides services to' (alongside Colorado Springs, El Paso County, Fountain, Monument, Manitou Springs, Green Mountain Falls, Palmer Lake, and Woodland Park) and including 'Calhan 719-347-2586 www.calhan.co' in its plan-review contacts table; pprbd.org's site-wide footer likewise now reads 'Serving Colorado Springs, El Paso County, Fountain, Woodland Park, Manitou Springs, Monument, Green Mountain Falls, Palmer Lake, and Calhan.' This supersedes the pre-July-2026 self-administered Town program documented elsewhere in this file (and PPRBD's older 'We do not service the townships of Ramah or Calhan' statement, which still appears un-updated in the body of PPRBD's Homeowner Permits page — the dated 07/01/26 packet and both sites' current routing statements control). It also completes the arc of Calhan's own emergency ordinance, which adopted the PPRBC 2023 specifically to be 'effective prior to July 1, 2026.' Under PPRBD, 'Commercial' is defined as any type of building except one- and two-family dwellings, townhomes, and their accessory structures; condominium and apartment projects are classified as Commercial. New commercial construction (including additions) follows PPRBD's Commercial Plan Review process with mandatory professional plan review before permit issuance.

Verified 2026-08-02 · Source

Requirements

  • Apply through Pikes Peak Regional Building Department (PPRBD), 719-327-2880, not the Town of Calhan — electronic plan submittal through www.pprbd.org is preferred per PPRBD's Commercial Plan Review packet
  • The seal of a design professional licensed by the State of Colorado is required on each sheet of the commercial plans (wet, raised, or electronic; signed and dated); cut sheets and manufacturer's details must also bear a seal
  • Completed PPRBD Code Study Form plus code data on the plans: occupancy classification, type of construction, allowable-area analysis, fire areas, sprinkler status, and egress calculations
  • Full submittal set: approved development plans, approved final landscape plans, final plat, approved grading & erosion control plans, approved water plans, utility plans, architectural plans, mechanical plans, plumbing plans, electrical plans, and structural plans with soils report; elevator plans and accessibility plans (Group R, I-1, I-2) if applicable
  • A separate Life Safety Plan, sealed by the licensed Architect of record, is required for all commercial projects intended for occupancy where two or more means of egress are required
  • Reviewed under the codes adopted by PPRBC jurisdictions per the 07/01/26 packet: 2023 Pikes Peak Regional Building Code, 2021 IBC, 2021 IECC, 2021 IMC, 2021 IFGC, 2021 IPC, 2021 IEBC, 2023 NEC, 2017 ICC/ANSI A117.1, Colorado Model Electric Ready and Solar Ready Code, and ASME elevator standards
  • Design criteria that must appear on submittal documents: flat roof snow load 30 psf (below 7,000 ft grade plane; 40 psf at/above 7,000 ft), basic wind speed 130 mph Vult for Risk Category I/II (135 mph Cat III, 140 mph Cat IV) with Exposure C required, and seismic spectral response Ss 18.5% / S1 5.9% minimums
  • Phased submittals (Foundation Only, Superstructure, Core/Shell) may be accepted per the packet's limited-scope rules; each phase must be released by all required review departments before that phase's permit is issued
  • Other agencies review in parallel (zoning, fire, engineering, utilities, health as applicable) — PPRBD's own contacts table lists the Town of Calhan (719-347-2586) as the Development Services/Zoning contact for Calhan project sites; note the Town states it has no zoning inside town limits
  • Building and mechanical contractors must be PPRBD-licensed; state-licensed electrical and plumbing contractors must register with PPRBD to work in its jurisdictions
  • Town of Calhan Fire Protection Impact Fee ($0.24 per square foot for Commercial/Industrial Development, Calhan Municipal Code Article 14) is a separate Town-side development impact fee collected where the Calhan Fire Protection District serves the parcel — confirm collection mechanics with the Town now that permit issuance has moved to PPRBD

Required documents

  • RequiredPPRBD Code Study FormPPRBD's required code-analysis form (pprbd.org/File/ByAlias/CodeStudyForm), submitted with the plan set; requires stamp, seal and signature by a Colorado-licensed design professional
  • RequiredSealed construction documents (full commercial set)Architectural, mechanical, plumbing, electrical, and structural plans (with soils report), each sheet bearing the signed, dated seal of a Colorado-licensed design professional; elevator and accessibility plans if applicable
  • RequiredApproved site/civil documentsApproved development plans, final landscape plans, final plat, grading & erosion control plans, water plans, and utility plans per the Commercial Plan Review submittal list
  • RequiredLife Safety PlanSeparate sealed plan required for all commercial projects intended for occupancy where two or more means of egress are required (not required for foundation-only, superstructure, or core/shell phases)

Fee schedule

Fee typeAmountNotes
Building Permit FeeValuation-based per PPRBD Table A (Section RBC108.2, 2023 PPRBC; 2025 ICC Valuation Data effective June 30, 2025): $50.00 minimum ($1-$500); $714.00 + $4.00 per $1,000 in the $100,001-$500,000 bracket; $2,314.00 + $3.50 per $1,000 for $500,001-$1,000,000; $4,064.00 + $3.00 per $1,000 above $1,000,000Valuation uses ICC Building Valuation Data with PPRBD's commercial regional modifier of 0.97 of the construction-type/occupancy valuation; final permit valuation is set by the Building Official. Fetched live from pprbd.org/Information/FeeSchedule 2026-08-02.
Plan Examination Fee28% of the Building Permit FeePaid when the plan submittal is accepted for review; PPRBD fee schedule, confirmed 2026-08-02
Additional Plan Review (APR) Fee$50.00/hour after the second disapprovalAssessed when a plan requires three or more reviews, per the Commercial Plan Review packet and fee schedule
Splice (plan change after permit issuance) FeeMinimum $50.00PPRBD Commercial Plan Review packet, 07/01/26 revision
Re-inspection Fee$50.00 first incident; $100.00 second; $200.00 third plus a 2-work-day inspection delayPPRBD fee schedule, confirmed 2026-08-02
Town of Calhan Fire Protection Impact Fee (Commercial/Industrial)$0.24 per square foot
Calhan Municipal Code Article 14; a Town-side development impact fee (not a PPRBD fee) applicable where the Calhan Fire Protection District serves the parcel — historically collected at building-permit application; Show full citation

Calhan Municipal Code Article 14; a Town-side development impact fee (not a PPRBD fee) applicable where the Calhan Fire Protection District serves the parcel — historically collected at building-permit application; confirm collection mechanics with the Town (719-347-2586) post-transition

Commercial Tenant Improvement / Remodel Permit (PPRBD-Administered as of July 1, 2026)

Verified

Tenant improvement work in Calhan IS a genuinely distinct process under PPRBD, which has administered all Calhan building permits since July 1, 2026 (see the commercial-building-permit entry for the fully-sourced administration handoff). PPRBD publishes a dedicated Commercial Remodel handout — separate from its Commercial Plan Review (ground-up/additions) packet and from a further separate change-of-occupancy handout — covering interior remodels and tenant finish, with its own lighter submittal list. PPRBD's core/shell phasing rules also make TI permits structurally distinct: the Commercial Plan Review packet states verbatim, 'Each separate tenant will require an interior finish plan and permit, which may require additional modifications to the core and shell elements.' Fees run through the same valuation-based PPRBD fee schedule as other building permits (there is no separate TI fee table), with the permit fee driven by remodel project valuation rather than new-construction square-footage valuation data.

Verified 2026-08-02 · Source

Requirements

  • Apply through PPRBD (719-327-2880 / pprbd.org), not the Town of Calhan; plan review is required before permit issuance
  • Plan submittal per the Commercial Remodel handout: Code Study Form; site plan for single-tenant buildings OR vicinity map plus interior site plan for multiple-tenant buildings; architectural, mechanical, plumbing, and electrical plans; structural and elevator plans if applicable
  • The seal of a Colorado-licensed design professional, signed and dated, is required on each sheet of the commercial plans
  • Architectural plans drawn to a minimum 1/8-inch scale on minimum 18 x 24 inch material; floor plans must graphically indicate the scope of work, label proposed use of each space, and show egress travel distances and fire-rated assemblies
  • Life safety plan required if two or more exits are required; IECC/ComCheck documentation if applicable; demolition plan if applicable
  • Change of occupancy is NOT covered by the Commercial Remodel process — PPRBD handles it under a separate handout/process; a TI that changes the occupancy classification should be scoped with PPRBD first
  • Parallel agency reviews (zoning, fire, utilities, health) apply as applicable; PPRBD lists the Town of Calhan (719-347-2586) as the zoning contact for Calhan sites, and the Town states it has no zoning inside town limits
  • For projects in new multi-tenant buildings permitted as core/shell, each separate tenant space requires its own interior finish plan and permit

Required documents

  • RequiredPPRBD Code Study FormRequired with every commercial remodel/TI plan submittal (pprbd.org/File/ByAlias/CodeStudyForm)
  • RequiredSealed remodel plan setArchitectural, mechanical, plumbing, and electrical plans (structural/elevator if applicable), one complete set, each sheet sealed, signed and dated by a Colorado-licensed design professional
  • RequiredSite plan or vicinity map + interior site planSite plan for single-tenant buildings; vicinity map and interior site plan for multiple-tenant buildings

Fee schedule

Fee typeAmountNotes
Building Permit Fee (remodel/TI valuation)Valuation-based per PPRBD Table A (Section RBC108.2, 2023 PPRBC): $50.00 minimum; e.g. $264.00 + $8.00 per $1,000 in the $25,001-$50,000 bracket; $464.00 + $5.00 per $1,000 for $50,001-$100,000; $714.00 + $4.00 per $1,000 for $100,001-$500,000Same PPRBD fee schedule as all building permits — no separate TI fee table exists; final valuation set by the Building Official. Fetched live from pprbd.org/Information/FeeSchedule 2026-08-02.
Plan Examination Fee28% of the Building Permit FeePaid when the plan submittal is checked in; per the Commercial Remodel handout the fee is 'calculated as a percentage of the Building Permit fee' — the current published percentage is 28%
Additional Plan Review (APR) Fee$50.00/hour after the second disapprovalIncurred when a plan requires three or more reviews
Splice (plan change after work begins) FeeMinimum $50.00Most splices can be reviewed during walk-thru hours per the Commercial Remodel handout
Re-inspection Fee$50.00 first incident; $100.00 second; $200.00 third plus a 2-work-day inspection delayPPRBD fee schedule, confirmed 2026-08-02

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Calhan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-23)Later version (2026-08-13) →View current record →All versions →

Permalink: /colorado/el-paso-county/calhan/as-of/2026-08-02/

Snapshot date: 2026-08-02

Commit: 64a44cb

Reproducible from PermitBase’s version-controlled dataset, commit 64a44cb.