Glenwood Springs building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Glenwood Springs, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
101 W. 8th Street, Second Floor, Glenwood Springs, CO 81601
Phone
970-384-6450
Office hours
Glenwood Springs City Hall Hours: 7:30 AM to 5:30 PM, Mondays-Thursdays (closed Fridays), per the City's Contact Us footer. Building Department direct line 970-384-6450; Fax 970-945-8582; Inspection Line (24-hour automated request system) 970-384-6432; Building Official Victor Meraz, 970-384-6410.

Published scheduling rules

  • Do not call the City's Inspection Line (970-384-6432) to schedule an electrical inspection — that line only covers City-permitted work (building, plumbing, mechanical, solar). Electrical inspections must be scheduled directly with the State of Colorado. (Electrical Permit (Issued by the State of Colorado, Not the City))
  • To schedule an inspection, call the City's Inspection Hot Line (970-384-6432) at least 24 hours in advance with: project address, permit number, date requested, morning/afternoon preference, and contractor contact information (Solar PV Permit)
  • Do not call the City's Inspection Line (970-384-6432) to schedule an EV charger electrical inspection -- that line only covers City-permitted work (building, plumbing, mechanical, solar structural). Electrical inspections must be scheduled directly with the State of Colorado. (EV Charger / Electric Vehicle Charging Station Permit)
  • Electrical work on your commercial project is permitted and inspected by the State of Colorado, not the City — schedule state electrical inspections independently, and don't call the City's inspection line (970-384-6432) for them. (Commercial Building Permit (Including Tenant Improvement / Commercial Remodel))

Inspection sequence

Applies to: Commercial Building Permit (Including Tenant Improvement / Commercial Remodel)

  1. 1

    Foundation

    Before concrete pour, for new construction or structural additions; the City does not inspect drilling/reinforcement/placement of piers, piles, shafts, or caissons — a qualified engineer must perform and certify that inspection separately

  2. 2

    Rough Framing

    Structural framing and (for tenant improvements) new partition-wall framing complete before cover

  3. 3

    Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; electrical rough-in is inspected separately by the State of Colorado, not the City

  4. 4

    Lath and Gypsum Board Inspection

    After gypsum board is in place but before joint taping/finishing, per the adopted IBC inspection sequence

  5. 5

    Final Inspection / Certificate of Occupancy

    All City-permitted work complete per approved plans; a separate final electrical sign-off from the State of Colorado is required before occupancy; certificate of occupancy withheld until all monies owed to the City are paid in full. A Temporary Certificate of Occupancy process is available (listed among Building Department documents)

Applies to: Residential Building Permit (New Construction, 4 or Fewer Units)

  1. 1

    Foundation

    Before concrete pour; City does not inspect drilling/reinforcement/placement of piers, piles, shafts, or caissons — a qualified engineer must perform and certify that inspection separately

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Rough Mechanical

    Trade rough-ins before concealment; electrical rough-in is inspected separately by the State of Colorado, not the City

  4. 4

    Lath and Gypsum Board Inspection

    After lathing/gypsum board (interior and exterior) is in place but before plastering or joint taping/finishing

  5. 5

    Final Inspection

    All City-permitted work (building, plumbing, mechanical) complete per approved plans; a separate final electrical inspection/sign-off from the State of Colorado is required before occupancy; certificate of occupancy withheld until all monies owed to the City are paid in full

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour, if new footings are part of the ADU construction

  2. 2

    Rough Framing

    Framing complete, four-sided design features verified against approved plans

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment; electrical rough-in inspected separately by the State of Colorado

  4. 4

    Final Inspection and Certificate of Occupancy

    All work complete per approved plans; a Certificate of Occupancy specifically stating the unit is an ADU is required before it may legally be rented

Applies to: Residential Addition / Remodel Permit (Including New Accessory Structures)

  1. 1

    Foundation (if new footings)

    Before concrete pour, for additions/accessory structures with new foundation elements

  2. 2

    Rough Framing

    Framing complete and tied into existing structure before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment; electrical rough-in inspected separately by the State of Colorado

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment; license verification performed on-site by the City inspector

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar PV Permit

  1. 1

    Pre-Installation Inspection of Bracketing

    Verifies mounting bracket installation prior to panel placement

  2. 2

    Final Inspection

    Completed installation verified

Re-inspection fees

Residential Building Permit (New Construction, 4 or Fewer Units)
Re-inspection Fee · Table 1-A 'Other Inspections and Fees'. Show full citationRe-inspection Fee · Table 1-A 'Other Inspections and Fees'. The same row sets a second re-inspection at $250.00 per hour and a third or any subsequent re-inspection at $500.00 per hour, with a one-hour minimum — an escalation not previously recorded here. Or the hourly cost to the jurisdiction, whichever is greatest.
$100.00 per hour (minimum charge: 1 hour)
Plumbing Permit
Re-inspection Fee · Per Table 1-A, assessed via §109.8 IBC as cross-referenced by the plumbing code. Show full citationRe-inspection Fee · Per Table 1-A, assessed via §109.8 IBC as cross-referenced by the plumbing code. The same row sets a second re-inspection at $250.00 per hour and a third or any subsequent re-inspection at $500.00 per hour, with a one-hour minimum — an escalation not previously recorded here. Or the hourly cost to the jurisdiction, whichever is greatest.
$100.00 per hour (minimum charge: 1 hour)
Mechanical / HVAC Permit
Re-inspection Fee · Per Table 1-A, assessed via §109.8 IBC as cross-referenced by the mechanical code. Show full citationRe-inspection Fee · Per Table 1-A, assessed via §109.8 IBC as cross-referenced by the mechanical code. The same row sets a second re-inspection at $250.00 per hour and a third or any subsequent re-inspection at $500.00 per hour, with a one-hour minimum — an escalation not previously recorded here. Or the hourly cost to the jurisdiction, whichever is greatest.
$100.00 per hour (minimum charge: 1 hour)
Roofing Permit (Re-Roofing)
Re-inspection Fee · Table 1-A 'Other Inspections and Fees' item 3, Municipal Code §060.020.020. Show full citationRe-inspection Fee · Table 1-A 'Other Inspections and Fees' item 3, Municipal Code §060.020.020. The same row sets a second re-inspection at $250.00 per hour and a third or any subsequent re-inspection at $500.00 per hour, with a one-hour minimum — an escalation not previously recorded here. Or the hourly cost to the jurisdiction, whichever is greatest.
$100.00 per hour (minimum charge: 1 hour)
Demolition Permit
Re-inspection Fee · Table 1-A 'Other Inspections and Fees' item 3, Municipal Code §060.020.020. Show full citationRe-inspection Fee · Table 1-A 'Other Inspections and Fees' item 3, Municipal Code §060.020.020. The same row sets a second re-inspection at $250.00 per hour and a third or any subsequent re-inspection at $500.00 per hour, with a one-hour minimum — an escalation not previously recorded here. Or the hourly cost to the jurisdiction, whichever is greatest.
$100.00 per hour (minimum charge: 1 hour)
Commercial Building Permit (Including Tenant Improvement / Commercial Remodel)
Re-inspection Fee · Table 1-A 'Other Inspections and Fees'. Show full citationRe-inspection Fee · Table 1-A 'Other Inspections and Fees'. The same row sets a second re-inspection at $250.00 per hour and a third or any subsequent re-inspection at $500.00 per hour, with a one-hour minimum — an escalation not previously recorded here. Or the hourly cost to the jurisdiction, whichever is greatest.
$100.00 per hour (minimum charge: 1 hour)

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glenwood Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Glenwood Springs building permits

Get alerts for Glenwood Springs

We'll email you when Glenwood Springs's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.