EV Charger / Electric Vehicle Charging Station Permit in Glenwood Springs, Colorado
Installing a Level 2 (240V) EV charging circuit or EVSE unit in Glenwood Springs is electrical work, and per Municipal Code §105.2 (IBC)/§R105.2 (IRC) as amended by Ordinance 2022-06, ALL electrical permits and inspections within the City are handled exclusively by the State of Colorado DORA Electrical Board -- the City of Glenwood Springs does not itself issue or inspect electrical permits, mirroring how the City routes all other electrical work (identical mechanism already documented in this file's electrical-permit entry). Unlike solar PV, which requires a separate City structural/racking Building Permit (Table 1-A, up to $500 residential), a simple wall-mounted or pedestal EV charger with no new structure does not trigger a City building permit -- only the State electrical permit applies.
Verified 2026-07-20 · Source
When you need this permit
- Electrical work (the EV charger circuit itself) must be permitted and inspected directly through the State of Colorado DORA Division of Professions and Occupations, Electrical Board -- not the City of Glenwood Springs
- The installing electrical contractor must additionally hold a City of Glenwood Springs 'Electrician' contractor registration (no charge) before being listed as electrical contractor of record, per the City's Contractor Licensing requirements -- this registration is separate from, and does not replace, the state electrical permit Contractor
- A City of Glenwood Springs Building Permit is required IN ADDITION only if the EVSE installation includes new structural work (e.g., a new carport, canopy, or accessory structure to house the charger) -- not required for a simple charger mounted on an existing wall or a freestanding pedestal with no new structure
- No EV-charger-specific submittal checklist analogous to the City's Solar Panel Permits page was found published by the City; electrical permitting follows the State's standard residential/commercial electrical permit process
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State of Colorado Electrical Inspection
Scheduled directly with the State of Colorado Electrical Board, not the City's Inspection Line -- verifies the new circuit, breaker sizing, and disconnect per NEC Article 625
See the full Glenwood Springs inspection guide — scheduling & re-inspection fees →
Tips
- Do not call the City's Inspection Line (970-384-6432) to schedule an EV charger electrical inspection -- that line only covers City-permitted work (building, plumbing, mechanical, solar structural). Electrical inspections must be scheduled directly with the State of Colorado.
- Even though the City doesn't issue the electrical permit itself, your electrician still needs a (free) City of Glenwood Springs contractor registration before being listed as the electrical contractor on any related City permit. Contractor
- Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act, 2024) directs larger Colorado municipalities and counties to streamline LAND USE permitting for public/commercial EV charging stations via the Colorado Energy Office's EV Charging Model Land Use Code -- this affects site-plan/land-use review for public charging installations, not the electrical permit itself, which remains a State DORA matter regardless of a jurisdiction's HB24-1173 compliance path. Confirm with City Community Development whether a site plan or land-use review applies for a commercial/public charging installation.
- A simple residential Level 2 charger mounted on an existing garage wall does not need a City building permit at all -- only the State electrical permit and the (free) City contractor registration for your electrician. Contractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glenwood Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Glenwood Springs
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Glenwood Springs project checklist
Describe your project once and get every permit, document, and fee it triggers in Glenwood Springs — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.