This is PermitBase’s published record for Fort Collins as of 2026-07-20. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Fort Collins building permits

Verified

Fort Collins, Colorado — as published 2026-07-20.

Verified 2026-06-30 · Source

Codes adopted

2024 International Building Code (IBC) with 2024 Fort Collins IBC Amendments — current as of April 1, 2026 (permits submitted on/after April 1, 2026 use these; 2021 IBC available for reference until Oct. 1, 2026)2024 International Residential Code (IRC) with 2024 Fort Collins IRC Amendments — current as of April 1, 20262024 International Energy Code (IECC) with 2024 Fort Collins IECC Amendments — current as of April 1, 2026; Fort Collins amendments add all-electric building provisions, solar-ready zone requirements, heat-pump and demand-response requirements (see localAmendments)2024 International Mechanical Code (IMC) with 2024 Fort Collins IMC Amendments2024 International Fuel and Gas Code (IFGC) with 2024 Fort Collins IFGC Amendments2024 International Plumbing Code (IPC) with 2024 Fort Collins IPC Amendments (Fort Collins uses the IPC, not the UPC)2023 National Electrical Code (NEC), effective Aug. 1, 2023 — adopted directly, matching the State of Colorado's adopted electrical code2024 International Existing Building Code (IEBC) with 2024 Fort Collins IEBC Amendments2024 International Property Maintenance Code (IPMC) with 2024 Fort Collins IPMC Amendments2024 International Swimming Pool and Spa Code (ISPSC) with 2024 Fort Collins ISPSC Amendments2025 Colorado Wildfire Resiliency Code (adopted statewide, current as of April 1, 2026)2017 ICC A117.1 — Accessibility, plus Colorado Accessibility State Law (CRS 9-5)Poudre Fire Authority Fire Code — see PFA's Fire Code webpage for current adopted fire code (separate department, not administered by Building Services)

Permit types & fees

Residential Building Permit (New Construction)

Verified

Required for new single-family homes, townhomes, and duplex/ADU new construction in Fort Collins. Reviewed against the 2024 IRC with 2024 Fort Collins Amendments and the 2024 IECC with Fort Collins energy/green amendments. Fee is calculated from the Fee Schedules occupancy-based rate table (R-3 = $0.65/sq ft), split 35% Plan Check / 65% Building Permit.

Verified 2026-06-30 · Source

Requirements

  • Submit one permit per detached structure
  • Plans must comply with the 2024 IRC with Fort Collins Amendments and 2024 IECC with Fort Collins Amendments (current as of April 1, 2026)
  • Residential Energy Code Compliance Form required
  • Residential Mechanical Systems Design Submittal (Manual J/D/S load calcs) required for new mechanical systems
  • Grading Plan Requirements form required
  • Construction Waste and Recycling Management Declaration of Responsibility + Construction Waste Management Report required
  • Homeowner Affidavit required if a homeowner is doing the work (self-permitting allowed for owner's own single-family residence, per Contractor Licensing exemptions)
  • New Construction Building Permit Fee Form required
  • Fee calculated from occupancy category (R-3 Single Family Detached/Duplex = $0.65/sq ft) via the Fee Schedules page: 35% Plan Check Fee due at application, 65% Building Permit Fee due at issuance
  • Transportation Capital Expansion Fees (TCEF) apply for new buildings that create additional traffic

Required documents

  • RequiredResidential Building Permit Application (PDF, 558KB)Primary application form for new residential construction, emailed to buildingservices@fortcollins.gov
  • RequiredNew Construction Building Permit Fee FormUsed with the Fee Schedules occupancy-rate table to calculate Plan Check and Building Permit fees
  • RequiredResidential Energy Code Compliance FormDemonstrates compliance with the 2024 IECC and Fort Collins energy amendments
  • RequiredResidential Mechanical Systems Design SubmittalManual J/D/S load calculations for new mechanical heating/cooling systems
  • RequiredGrading Plan RequirementsSite drainage and grading plan per city drainage requirements for residential permits
  • RequiredConstruction Waste and Recycling Management Declaration of Responsibility + ReportWaste diversion documentation required for new construction

Fee schedule

Fee typeAmountNotes
Building Permit Fee — R-3 (Single Family Detached/Duplex)$0.65 per square foot of project areaCity of Fort Collins Fee Schedules page — Applicable Fee Rates Per Square Foot table; example given: 3,500 sq ft x $0.65 = $2,275 total
Plan Check Fee35% of total fee, due at applicationCity of Fort Collins Fee Schedules page — Fees for New Construction Projects
Building Permit Fee (remainder)65% of total fee, due at permit issuanceCity of Fort Collins Fee Schedules page
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page — current rates apply; billed via project cost reports at close-out
Transportation Capital Expansion Fee (TCEF)Varies — applies to new buildings/major changes that create additional trafficCity of Fort Collins Fee Schedules page; exact amount not itemized on the general fee page — confirm at application

Residential Addition / Remodel Permit

Verified

Required for residential additions (garage expansions, pop-the-tops, sunrooms, enclosing a covered patio) and remodels (kitchen/bath alterations, basement finishes, layout changes) in Fort Collins. Additions use the same occupancy-based Fee Schedules rate table as new construction; interior remodels use a valuation-based tiered fee table.

Verified 2026-06-30 · Source

Requirements

  • Additions: enlarging/expanding enclosed area (pop-the-top, lean-to, garage expansion, sunroom, enclosing a covered patio) — fee calculated via Fee Schedules occupancy rate table
  • Remodels: kitchen/bath alterations, interior layout changes, garage/attic/accessory-building-to-living-space conversions, converting living space to bedroom, digging out a crawlspace for a basement, finishing a large attic — fee calculated via the tiered valuation-based Permit Fee table
  • Residential Mechanical Systems Design Submittal required if a mechanical system is completely new or the type of heating/cooling is changing
  • Residential Energy Code Compliance Form required when a non-heated space becomes heated
  • Construction Waste and Recycling Management Declaration of Responsibility required for additions larger than 2,500 sq ft
  • Homeowner Affidavit required if homeowner is doing the work
  • Basement Finish is processed as its own Fast-Track permit type with a flat $155 Building Permit Fee (see notes)

Required documents

  • RequiredBuilding Permit Application (PDF, 619KB)Standard application for residential additions/remodels
  • OptionalNew Residential Addition Submittal GuideCity guidance for pop-the-top, garage expansion, sunroom and similar addition scopes
  • OptionalResidential Mechanical Systems Design SubmittalManual J/D/S load calcs, required when a new/second primary heating or cooling system is proposed
  • OptionalResidential Energy Code Compliance FormRequired when converting unheated to heated space
  • OptionalBasement Finish Permit Application (PDF, 501KB)Fast-Track permit application for full/partial residential basement finish; requires an engineer's evaluation letter for structural work including new/larger basement windows

Fee schedule

Fee typeAmountNotes
Residential Addition — occupancy-based (Fee Schedules Table)$0.65 per square foot (R-3) of added enclosed areaCity of Fort Collins Fee Schedules page; same occupancy rate table as new residential construction
Residential Remodel (Single Family or Multifamily) — valuation-basedUp to $2,000: flat $105.00. $2,000–$25,000: $105 + $15.50 per additional $1,000. $25,000–$50,000: $461.50 + $10.50 per additional $1,000. $50,000–$100,000: $724.00 + $6.50 per additional $1,000. $100,000–$500,000: $1,049.00 + $60 per additional $10,000 ($6/$1,000 equivalent). Above $500,000: $3,449.00 + $55 per additional $10,000 ($5.50/$1,000 equivalent).City of Fort Collins Building Permits page — Remodel and Alteration Permits fee table (Residential Remodels, Single Family)
Basement Finish (Fast-Track flat fee)$155.00City of Fort Collins Building Permits page — Fast-Track Permits, Basement Finish
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Electrical Permit

Verified

Required for outlets, panels, wiring, repairs, lighting, EV chargers, and other electrical work in Fort Collins. The CITY of Fort Collins Building Services issues and reviews electrical permits (not a Colorado state board directly) — but individuals performing electrical work must hold a State of Colorado electrical license, and Master Electricians must additionally register with the City of Fort Collins Contractor Licensing office to work under permits in city limits. Governed by the 2023 NEC (effective Aug. 1, 2023), matching the state-adopted electrical code.

Verified 2026-06-30 · Source

Requirements

  • Work included: outlets, panels, wiring, repairs, lighting, electric for ground-mounted pre-fabricated hot tubs, residential EV chargers for single-family detached/duplex/townhomes (Fast-Track eligible)
  • If more than one trade is involved, or an unheated space becomes heated, or for commercial EV chargers, submit a Remodel/Alteration permit instead of the Fast-Track Electric permit
  • Master Electricians must be licensed by the State of Colorado (Supervisor relationship) AND separately register with the City of Fort Collins (no additional City exam required for the registration)
  • General/Trade Contractors performing electrical work as part of broader scope need the applicable City of Fort Collins contractor license
  • Commercial EV charging stations require accessible parking/EV charging compliance documentation

Required documents

  • RequiredElectric Permit Application (PDF, 432KB)Fast-Track application for residential/light-commercial electrical work
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if a homeowner is doing the electrical work themselves
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial electrical permits
  • RequiredMaster License Registration Packet (PDF, 620KB)Required for Master Electricians to register with the City, in addition to their State of Colorado license

Fee schedule

Fee typeAmountNotes
Electric (Fast-Track Building Permit Fee)$65.00City of Fort Collins Building Permits page — Fast-Track Permits, Electric
EV Charger (Commercial and Multifamily) — valuation-basedUp to $2,000: flat $105.00. $2,000–$25,000: $105 + $15.50 per additional $1,000. $25,000–$50,000: $461.50 + $10.50/$1,000. $50,000–$100,000: $724.00 + $6.50/$1,000. $100,000–$500,000: $1,049.00 + $6/$1,000. Above $500,000: $3,449.00 + $5.50/$1,000.City of Fort Collins Building Permits page — Remodel and Alteration Permits, EV Charger (Commercial and Multifamily)
Master Electrician Registration (new/reinstatement)$300.00 (License and Supervisor's Certificate, new or reinstatement)City of Fort Collins Contractor Licensing page — Fees table; renewal is $225.00
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Plumbing Permit

Verified

Required for water, sewer, gas piping and valve work in Fort Collins. The CITY of Fort Collins Building Services issues and reviews plumbing permits directly — individuals performing plumbing work must hold a State of Colorado plumbing license, and Master Plumbers must additionally register with the City of Fort Collins. Governed by the 2024 International Plumbing Code (IPC) with Fort Collins Amendments (Fort Collins uses the IPC, unlike Reno's UPC).

Verified 2026-06-30 · Source

Requirements

  • Work included: water, sewer, gas piping and valves
  • If more than one trade is involved (HVAC, electric, plumbing), submit a Remodel/Alteration permit instead of the Fast-Track Plumbing permit
  • If a gas line is installed for a heater, submit a Mechanical permit instead
  • Master Plumbers must be licensed by the State of Colorado (Supervisor relationship) AND separately register with the City of Fort Collins (no additional City exam required)
  • Governed by the 2024 IPC with Fort Collins Amendments (current as of April 1, 2026); Colorado Plumbing Code also referenced on the Building Code page

Required documents

  • RequiredPlumbing Permit Application (PDF, 432KB)Fast-Track application for plumbing work
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if a homeowner is doing the plumbing work themselves
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial plumbing permits
  • RequiredMaster License Registration Packet (PDF, 620KB)Required for Master Plumbers to register with the City

Fee schedule

Fee typeAmountNotes
Plumbing (Fast-Track Building Permit Fee)$65.00City of Fort Collins Building Permits page — Fast-Track Permits, Plumbing
Master Plumber Registration (new, renewal or reinstatement)$200.00City of Fort Collins Contractor Licensing page — Fees table
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Mechanical / HVAC Permit

Verified

Required for heating, cooling, ductwork, exhaust, mini-splits, heat pumps, air handlers, rooftop unit replacement, A/C, furnaces, and water heaters in Fort Collins. Governed by the 2024 International Mechanical Code (IMC) and 2024 International Fuel and Gas Code (IFGC) with Fort Collins Amendments.

Verified 2026-06-30 · Source

Requirements

  • Work included: heating, cooling, ductwork, exhaust, mini-splits, heat pump, air handler, rooftop unit (RTU) replacement, A/C and furnace
  • If more than one trade is involved, or an unheated space becomes heated, submit a Remodel/Alteration permit instead
  • If an RTU is a new size, weight or location, submit a structural evaluation from a Colorado-licensed structural engineer
  • Water heater replacement is its own Fast-Track line item under the Heating/Cooling permit application, billed per water heater
  • For a water heater replacement in a commercial food service establishment, also contact the Larimer County Health Department

Required documents

  • RequiredHeating or Cooling Permit Application (PDF, 483KB)Fast-Track application covering furnace, A/C, heat pump, mini-split, and water heater work
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if a homeowner is doing the work
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial mechanical permits
  • OptionalResidential Mechanical Systems Design Submittal (PDF, 314KB)Manual J/D/S calcs, required for new mechanical systems submitted as part of additions/remodels/new construction

Fee schedule

Fee typeAmountNotes
Mechanical (Fast-Track Building Permit Fee)$65.00 per heating applianceCity of Fort Collins Building Permits page — Fast-Track Permits, Mechanical
Water Heater (Fast-Track Building Permit Fee)$65.00 per water heaterCity of Fort Collins Building Permits page — Fast-Track Permits, Water Heater
Fireplace, Wood Stove or Fire Pit (Fast-Track Building Permit Fee)$65.00City of Fort Collins Building Permits page — Fast-Track Permits, Fireplace/Wood Stove/Fire Pit
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Roofing Permit (Reroof)

Verified

Required for roof replacement/repair beyond a minor threshold on residential and commercial buildings in Fort Collins. Flat-fee Fast-Track permit; residential and commercial rates differ. Fort Collins requires Class 4 impact-resistant asphalt shingles when replacing 50% or more of a roof and mandates ice barrier at all eaves.

Verified 2026-07-01 · Source

Requirements

  • Roofing repairs up to 100 sq ft (one roofing square) per building are permit-exempt; larger repairs and full reroofs require a permit
  • Historic-designated buildings must be checked before submitting
  • If an existing solar PV system must be removed and reinstalled for the reroof, submit a separate Solar PV Reinstallation permit
  • Class 4 impact-resistant asphalt shingles required when replacing 50% or more of a roof (on the portion being replaced)
  • Roof overlays allowed only as a second layer (max), weighing under 3 lb/sq ft (else a structural evaluation is required), manufacturer-permitted, and installed for high-wind per manufacturer instructions/code
  • Ice barrier required at all roof eaves — minimum 24 in. upslope from the low eave edge (36 in. for slopes 8:12 or steeper)
  • Drip edge required at eaves and gables of asphalt shingle roofs; continuous or step flashing at vertical sidewalls (except masonry/stucco)

Required documents

  • RequiredRoofing Permit Application (PDF, 2MB)Application for reroof/roof repair work
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if a homeowner is doing the work
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial/multifamily roofing permits

Fee schedule

Fee typeAmountNotes
Roofing — Residential (flat Building Permit Fee)$85.00
City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Roofing accordion, "Fees and Taxes": "Building Permit Fee: $85 residential; Show full citation

City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Roofing accordion, "Fees and Taxes": "Building Permit Fee: $85 residential; $210 commercial." (verified 2026-07-01 by expanding the Roofing accordion; this content is client-side rendered and not visible to plain HTTP fetch/curl)

Roofing — Commercial (flat Building Permit Fee)$210.00
City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Roofing accordion, "Fees and Taxes": "Building Permit Fee: $85 residential; Show full citation

City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Roofing accordion, "Fees and Taxes": "Building Permit Fee: $85 residential; $210 commercial." (verified 2026-07-01 by expanding the Roofing accordion; this content is client-side rendered and not visible to plain HTTP fetch/curl)

Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Solar PV Permit

Verified

Required for rooftop or ground-mounted solar PV installation, reinstallation, and energy storage systems (ESS) in Fort Collins. Because Fort Collins Utilities is the city's own municipal electric utility, solar/battery projects require a SEPARATE Utilities Interconnect and Rebate Application in addition to the Building Services permit. A separate Poudre Fire Authority permit is also required for new installations and larger ESS.

Verified 2026-06-30 · Source

Requirements

  • New installation: site plan, roof plan (if roof-mounted), panel layout, structural engineering for wind/snow loads and attachment (stamped by Colorado-licensed engineer), engineered electrical one-line diagram (stamped)
  • A separate permit from Poudre Fire Authority is required for new solar PV installations, including fire access/clearances per the International Fire Code
  • Reinstallation (same location/identical panels, no system changes): before-photo of existing system required; roof plan with panel layout only if the system changes
  • Energy Storage System (ESS): location/spacing must comply with 2021 IRC R328 and the city's interpretation; requires a Master Electrician or Homeowner Affidavit; separate PFA permit required above 20 kWh (individual units), 40 kWh aggregate (utility closets/basements/storage), or 80 kWh aggregate (garages/exterior/outdoor)
  • Utilities Interconnect and Rebate Application (separate from the building permit) must be submitted to Fort Collins Utilities — see Residential Solar and Battery Storage program

Required documents

  • RequiredSolar PV Permit Application (PDF, 401KB)Application for new solar PV installation or ESS
  • OptionalResidential Solar PV Guide (PDF, 546KB)City guidance on submittal requirements for residential solar PV
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if homeowner is doing the work, including for ESS installs without a Master Electrician
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial/multifamily solar permits
  • RequiredUtilities Interconnect and Rebate ApplicationSeparate submittal to Fort Collins Utilities (Solar-Rebates@fortcollins.gov), required in addition to the Building Services permit for interconnection and any applicable rebate

Fee schedule

Fee typeAmountNotes
Solar PV New Installation — Residential$85.00 total application fee ($29.75 Plan Check due at application + $55.25 Building Permit Fee due at issuance)City of Fort Collins Building Permits page — Solar PV (New Installation), Residential
Solar PV New Installation — Commercial$155.00 total application fee ($54.25 Plan Check due at application + $100.75 Building Permit Fee due at issuance)City of Fort Collins Building Permits page — Solar PV (New Installation), Commercial
Solar PV Reinstallation (flat fee)$65.00City of Fort Collins Building Permits page — Solar PV Reinstallation
Solar PV — Energy Storage System (ESS) (flat fee)$65.00City of Fort Collins Building Permits page — Solar PV, Energy Storage System
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Accessory Dwelling Unit (ADU) Permit

Verified

Required for construction of a new attached or detached ADU in Fort Collins. Since February 2025, Colorado state law HB 24-1152 allows ADUs in all Fort Collins zone districts (previously limited to Old Town and select neighborhoods), and prohibits owner-occupancy requirements — ADUs may be rented out separately from the primary home. Fort Collins is home to Colorado State University, making ADUs relevant for rental/student housing demand. All ADUs require a mandatory Basic Development Review before a building permit.

Verified 2026-06-30 · Source

Requirements

  • No new units allowed in the Poudre River 100-year floodplain
  • Property must have (or be allowed to build) a house, duplex, or triplex on the lot
  • Most properties may add one ADU only; some zones (RUL, RF, CC, CCN, CCR, CG, CS, CL, LMN, MMN, HMN, NC, D, HC, E, I, RC) may allow a second detached house
  • Detached ADU size: up to 750 sq ft if main home is under 1,667 sq ft; up to 1,000 sq ft or 45% of main home (whichever is less) if larger; existing accessory buildings may convert up to 800 sq ft
  • Attached ADU size: above-grade up to 750 sq ft or 45% of main home; basement ADU up to 750 sq ft or 100% of that floor
  • Detached ADU height may not exceed the main building or the zone's max height; must sit behind the front wall of the home, at least 5 ft from other buildings, and follow zone setbacks
  • A walkway must connect the ADU's main door to the street, and the ADU's address must be visible from the street
  • ADU needs its own electric meter (Fort Collins Utilities); may require nearby transformer upgrade or trenching payment
  • Utility separations: 10 ft between water/sewer lines, 10 ft between storm drains and other utilities, 6 ft trees to water/sewer, 4 ft shrubs to water/sewer
  • Stormwater quality treatment (rain gardens, permeable pavers) required if the project creates more than 1,000 sq ft of new impervious surface
  • Mandatory Basic Development Review (flat $6,925 fee) precedes the building permit — decision made administratively by Planning Manager or Community Development Director per HB 24-1152 (no public hearing/subjective design review)
  • Building Code requirements: fire-rated separation between units (attached ADUs), separate heating systems (attached ADUs), minimum kitchen/bathroom standards, separate exit doors
  • Short-term rental of ADUs is prohibited, except in Planned Unit Developments (PUDs) where STRs were previously allowed

Required documents

  • RequiredBasic Development Review ApplicationMandatory pre-building-permit zoning/development review covering Planning, Utilities, Fire, and Stormwater departments
  • RequiredResidential Building Permit Application (PDF, 558KB)Building permit application, submitted after Development Review approval
  • RequiredResidential Mechanical Systems Design SubmittalManual J/D/S load calcs for the ADU's mechanical system
  • RequiredResidential Energy Code Compliance FormDemonstrates 2024 IECC/Fort Collins amendments compliance
  • OptionalResidential Demolition Permit (PDF, 441KB)Required if demolishing an existing structure to build the ADU

Fee schedule

Fee typeAmountNotes
Basic Development Review (BDR)$6,925 (flat fee, mandatory for ADU projects)City of Fort Collins ADU page — Step 4: Budget for Fees; also listed on Fee Schedules — Development Review Fees, Planning Services table
Building Permit FeeBased on project value/occupancy — see Residential Building Permit fee entry (R-3 occupancy-based rate)City of Fort Collins ADU page and Fee Schedules page
Utility fees (water, sewer, electric capacity charges)Varies by project — not itemized as a single figure on the ADU pageCity of Fort Collins ADU page — Step 4: Budget for Fees
Transportation fees (Larimer County road impact + City capital expansion)Varies by projectCity of Fort Collins ADU page — Step 4: Budget for Fees
Total estimated ADU development fees (all-in)Approximately $20,000–$25,000City of Fort Collins ADU page — Step 4: Budget for Fees; city's own stated estimate range combining BDR, utility, transportation, and building permit fees

Demolition Permit

Verified

Required for demolishing an existing structure in Fort Collins, whether interior/non-structural, interior structural, partial building, or complete building demolition. Requirements scale with demolition scope (asbestos disclosure/assessment, state approval notice, construction waste management).

Verified 2026-06-30 · Source

Requirements

  • Interior, Non-Structural Demolition: Demolition Permit Application, Construction Waste Management Plan, Asbestos Awareness Disclosure
  • Interior Structural Demolition: same as above plus applicable structural documentation
  • Partial Building Demolition: Demolition Permit Application, Construction Waste Management Plan, asbestos assessment showing clear of asbestos by certified contractor
  • Complete Building Demolition: Demolition Permit Application, Construction Waste Management Plan, State Demolition Approval Notice
  • Homeowner Affidavit required if a homeowner is doing the work

Required documents

  • RequiredDemolition Permit Application (PDF, 387KB)Primary demolition application form
  • RequiredAsbestos Awareness Disclosure (PDF, 161KB)Required for interior demolition scopes
  • RequiredConstruction Waste and Recycling Management Declaration of Responsibility (PDF, 467KB) + Construction Waste Management ReportRequired for all demolition scopes
  • OptionalState Demolition Approval NoticeRequired for complete building demolition, per Colorado state requirements
  • OptionalResidential Demolition Submittal Guide / Commercial Demolition Submittal Guide (PDF, 441KB each)City guidance documents for the applicable demolition scope

Fee schedule

Fee typeAmountNotes
Demolition (Application/Building Permit Fee)$65.00City of Fort Collins Building Permits page — Demolition section: 'Application Fee: $65 (Building Permit Fee)'
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Commercial Tenant Improvement / Remodel Permit

Verified

Required for commercial alterations, change of function/use/occupancy, tenant finish, and vanilla shell/white box/landlord work in Fort Collins. Uses the same tiered valuation-based fee table as residential remodels.

Verified 2026-06-30 · Source

Requirements

  • Covers alterations, change of function/use/occupancy, tenant finish, and vanilla shell/white box/landlord work
  • Change of Occupancy Permit Requirements apply if the use/occupancy classification changes
  • Accessibility upgrades may be required (per Accessibility Upgrades Information guidance) depending on scope
  • Construction Waste and Recycling Declaration of Responsibility + Report required
  • Owner Authorization Form required for commercial/multifamily projects
  • Submit one permit per commercial tenant space or unit

Required documents

  • RequiredCommercial Remodel Permit Application (PDF, 530KB)Primary application for commercial remodels/tenant improvements
  • OptionalCommercial Remodel Submittal Guide (PDF, 919KB)City guidance for commercial remodel/tenant-finish submittals
  • OptionalChange of Occupancy Permit Requirements (PDF, 512KB)Required documentation set if the project changes occupancy classification
  • RequiredOwner Authorization Form (PDF, 374KB)Required for commercial/multifamily projects
  • RequiredConstruction Waste and Recycling Declaration of Responsibility + ReportRequired waste diversion documentation

Fee schedule

Fee typeAmountNotes
Commercial Remodel — valuation-basedUp to $2,000: flat $105.00. $2,000–$25,000: $105 + $15.50 per additional $1,000. $25,000–$50,000: $461.50 + $10.50/$1,000. $50,000–$100,000: $724.00 + $6.50/$1,000. $100,000–$500,000: $1,049.00 + $6/$1,000 (via $60 per $10,000). Above $500,000: $3,449.00 + $5.50/$1,000 (via $55 per $10,000).City of Fort Collins Building Permits page — Remodel and Alteration Permits, Commercial Remodels fee table
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Deck / Covered Patio Permit

Verified

Required for decks, stairs, ramps, landings, and patio/porch covers in Fort Collins (except small decks under 200 sq ft / 30 in. high, which are permit-exempt). Flat-fee Fast-Track/Exterior permit; pre-built structures and commercial projects require a Colorado-licensed structural engineer's stamp.

Verified 2026-07-01 · Source

Requirements

  • Deck/Stairs/Ramp/Landing: site plan, deck plans; commercial structural work must be stamped by a Colorado-registered structural engineer; City-approved specialty products (diamond piers, PWT engineered deck products) usable without a full engineered design if complete product specs are submitted
  • Patio/Porch Cover: commercial projects and pre-built structures must be designed and stamped by a Colorado-licensed structural engineer
  • Small decks are permit-EXEMPT if: area ≤200 sq ft, height ≤30 in. above grade, not attached to the dwelling, and not serving a required exit door
  • Construction Waste and Recycling Management Declaration of Responsibility + Report required for decks
  • Homeowner Affidavit required if homeowner is doing the work

Required documents

  • RequiredBuilding Permit Application (PDF, 619KB)Standard application used for deck and patio cover permits
  • RequiredResidential Deck Guide (PDF, 1MB)City guidance to fill out and include with deck plans
  • OptionalResidential Patio Cover Guide (PDF, 1MB)City guidance for patio/porch cover submittals
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if homeowner is doing the work
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial/multifamily projects

Fee schedule

Fee typeAmountNotes
Deck / Stairs / Ramp / Landing (flat total)$110.00 total ($38.50 Plan Check due at application + $71.50 Building Permit Fee due at issuance)
City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Deck / Stairs / Ramp / Landing accordion, "Fees and Taxes": "Application Fee: $110 total; Show full citation

City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Deck / Stairs / Ramp / Landing accordion, "Fees and Taxes": "Application Fee: $110 total; Plan Check Fee: $38.50 (due when you apply); Building Permit Fee: $71.50 (due when your permit is issued)" (verified 2026-07-01 by expanding the accordion; this content is client-side rendered and not visible to plain HTTP fetch/curl)

Patio / Porch Cover (flat total)$110.00 total ($38.50 Plan Check due at application + $71.50 Building Permit Fee due at issuance)
City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Patio / Porch Cover accordion, "Fees and Taxes": "Application Fee: $110 total; Show full citation

City of Fort Collins Building Permits page, "Apply for a Building Permit" section (#section-3) — Patio / Porch Cover accordion, "Fees and Taxes": "Application Fee: $110 total; Plan Check Fee: $38.50 (due when you apply); Building Permit Fee: $71.50 (due when your permit is issued)" (verified 2026-07-01 by expanding the accordion; this content is client-side rendered and not visible to plain HTTP fetch/curl)

Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

EV Charger / Electric Vehicle Charging Station Permit

Verified

Required for installation of a residential or commercial EV charger in Fort Collins. Residential EV chargers for single-family detached/duplex/townhomes are Fast-Track eligible under the standard Electric permit; commercial and multifamily EV chargers use the valuation-based Remodel/Alteration permit fee table with a dedicated 'EV Charger (Commercial and Multifamily)' line item — both documented directly on the City's Building Permits page (Fast-Track Permits and Remodel and Alteration Permits sections).

Verified 2026-07-20 · Source

Requirements

  • Residential EV chargers for single-family detached, duplex, or townhome properties are eligible for the Fast-Track Electric permit process (same as outlets, panels, wiring, repairs, and lighting)
  • Commercial and multifamily EV charging stations require a Remodel/Alteration permit instead of the Fast-Track Electric permit, and require accessible parking/EV charging compliance documentation
  • Governed by the 2023 NEC (effective Aug. 1, 2023), including Article 625 (Electric Vehicle Power Transfer System), matching the state-adopted electrical code
  • Master Electricians must be licensed by the State of Colorado (Supervisor relationship) AND separately register with the City of Fort Collins Contractor Licensing office
  • 'Energize Electric' inspection step applies for chargers requiring new/upgraded service, tied to Fort Collins Utilities (the City's own municipal electric utility) setting the permanent meter

Required documents

  • RequiredElectric Permit Application (PDF, 432KB)Fast-Track application for residential EV charger installation (single-family detached/duplex/townhomes)
  • OptionalOwner Authorization Form (PDF, 374KB)Required for commercial/multifamily EV charger permits
  • OptionalHomeowner Affidavit (PDF, 469KB)Required if a homeowner is doing the EV charger installation themselves

Fee schedule

Fee typeAmountNotes
EV Charger — Residential (single-family detached/duplex/townhome), Fast-Track Building Permit Fee$65.00City of Fort Collins Building Permits page — Fast-Track Permits, Electric (residential EV chargers are explicitly listed as Fast-Track eligible under the standard Electric permit line item)
EV Charger (Commercial and Multifamily) — valuation-basedUp to $2,000: flat $105.00. $2,000-$25,000: $105 + $15.50 per additional $1,000. $25,000-$50,000: $461.50 + $10.50/$1,000. $50,000-$100,000: $724.00 + $6.50/$1,000. $100,000-$500,000: $1,049.00 + $6/$1,000. Above $500,000: $3,449.00 + $5.50/$1,000.City of Fort Collins Building Permits page — Remodel and Alteration Permits, EV Charger (Commercial and Multifamily) — a dedicated named line item distinct from the general electrical remodel table
Sales TaxCalculated based on total project valuation (materials and labor)City of Fort Collins Sales Tax page

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fort Collins building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-06-30)Later version (2026-08-13) →View current record →All versions →

Permalink: /colorado/larimer-county/fort-collins/as-of/2026-07-20/

Snapshot date: 2026-07-20

Commit: 792da88

Reproducible from PermitBase’s version-controlled dataset, commit 792da88.