Skip to main content
PermitBase

Grand Junction building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Grand Junction, Colorado.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
200 S. Spruce Street, Grand Junction, CO 81501 (mailing: PO Box 20,000-5005, Grand Junction, CO 81502-5001)
Phone
(970) 244-1631
Office hours
Monday - Friday, 8:00 a.m.-5:00 p.m.; permit issuance after 4:30 p.m. is on a limited basis and no multiple permits are issued after 4:30 p.m. (Source: Mesa County Building Department Fees page)

Published scheduling rules

  • Inspections can be scheduled via the Mesa County Customer Portal, by phone (970-256-1564, IVR system), or by text (text SCHEDULE to 844-987-4628). (Residential Building Permit (New Construction))
  • Inspections are scheduled in the morning during hot weather where possible, to avoid shingle damage and protect inspector safety. (Re-Roofing Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation (Footer/Stem Wall or Monoslab)

    Per Mesa County Residential Inspection Request Guidelines: 100-Footer, 120-Setbacks, 475-UFER (footer/stem wall); or 104-Slab, 120-Setbacks, 475-UFER for monoslab. Engineer-inspected foundations require a letter by frame inspection.

  2. 2

    Underground Utilities

    224-Sewer, 226-Waterline; in-trench 226-Waterline, 340-Gas Piping, 466-Underground where applicable

  3. 3

    Rough-In (Framing, Electrical, Plumbing, Mechanical, Insulation)

    105-Floor Framing (if applicable); 462-Electrical (before insulation); 106-Framing, 222-Plumbing, 346-Venting, 348-Mech Duct, 350-Gas Fireplace (if applicable); 115-Stucco Lath; 108-Insulation

  4. 4

    Gas Appliances

    340-Gas Piping & Test, 342-Boiler/Furnace, 344-Water Heater

  5. 5

    Final

    116-Building, 232-Plumbing, 356-Mechanical, 476-Electrical. Zoning, septic final, and floodplain sign-off (where applicable) are required to be complete before a Certificate of Occupancy is issued.

Applies to: Plumbing Permit

  1. 1

    Underground/In-Slab Plumbing

    220-Underground Plumbing, 470-In Slab Rough-In; 224-Sewer and 226-Waterline for underground utility connections, per Mesa County Residential Inspection Request Guidelines

  2. 2

    Rough-In Plumbing

    222-Plumbing rough-in inspection, typically bundled with framing (106), venting (346), and mechanical duct (348) inspections

  3. 3

    Gas Piping

    340-Gas Piping & Test; 342-Boiler/Furnace; 344-Water Heater

  4. 4

    Final Plumbing

    232-Plumbing final inspection

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Per Mesa County Residential Inspection Request Guidelines: 100-Footer or 104-Slab, 120-Setbacks, 475-UFER

  2. 2

    Rough-In

    Framing (105/106), electrical (462), plumbing (222), mechanical duct (348) as applicable, before insulation/cover

  3. 3

    Final

    116-Building, 232-Plumbing, 356-Mechanical, 476-Electrical final inspections; zoning sign-off required before Certificate of Occupancy

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In Mechanical

    348-Mech Duct rough-in inspection, typically bundled with framing (106), plumbing (222), and venting (346) inspections

  2. 2

    Gas Appliance

    340-Gas Piping & Test; 342-Boiler/Furnace

  3. 3

    Final Mechanical

    356-Mechanical final inspection

Applies to: Residential Addition / Remodel / Alteration Permit

  1. 1

    Foundation/Footer

    Required before concrete pour for addition footings, deck posts, or garage foundations (100-Footer, 120-Setbacks)

  2. 2

    Framing

    106-Framing rough-in inspection; structural connections to the existing structure

  3. 3

    Final

    116-Building final inspection; zoning sign-off required where applicable before Certificate of Occupancy

Applies to: Electrical Permit

  1. 1

    Rough-In Electrical

    462-Electrical inspection required before insulation is installed, per Mesa County Residential Inspection Request Guidelines

  2. 2

    Final Electrical

    476-Electrical final inspection

Applies to: EV Charger / Electric Vehicle Charging Station Permit

  1. 1

    Rough Electrical

    462-Electrical rough-in inspection covering conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    476-Electrical final inspection; new circuit, breaker sizing, and disconnect verified before the charger is energized

Applies to: Fence and Retaining Wall Permit

  1. 1

    Footing

    Required for engineered retaining walls 4 ft+ before backfill; specific inspection-code detail for fences/walls was not separately published on Mesa County's Residential Inspection Request Guidelines and should be confirmed with the Building Department

  2. 2

    Final

    Completed fence/wall verified against approved plans

Applies to: Re-Roofing Permit

  1. 1

    Mid-Roof

    Inspection code 111 — Mid-roof inspection required when 10% to 40% of the roof is complete, covering drip edge, valley flashings, attachment methods, and underlayment

  2. 2

    Final

    Required upon completion of all work; a final building inspection is required prior to solar panel installation or reinstallation on the roof

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    462-Electrical rough-in inspection covering conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    476-Electrical final inspection; a final building inspection (116-Building) is required prior to any solar installation/reinstallation on a reroofed structure

Final inspection only: Demolition Permit

Re-inspection fees

Electrical PermitRe-inspection Fee · Mesa County Building Department Fee Schedule, Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation
Plumbing PermitRe-inspection Fee · Mesa County Building Department Fee Schedule, Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation
Mechanical / HVAC PermitRe-inspection Fee · Mesa County Building Department Fee Schedule, Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation
EV Charger / Electric Vehicle Charging Station PermitRe-inspection Fee · Mesa County Building Department Fee Schedule, Table 1A, Fee #4
$50.00 first re-inspection; $100.00 for additional re-inspection on the same violation

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Grand Junction building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Grand Junction building permits

Get alerts for Grand Junction

We'll email you when Grand Junction's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.