Holyoke building permits

Holyoke, Colorado — as published 2026-07-07.

Reviewed 2026-07-23 · Source

Codes adopted

IMPORTANT SEED-URL CORRECTION: the seed URL provided for this research (https://www.holyoke.org/departments/building/) resolves to the City of Holyoke, MASSACHUSETTS Building Department (413-322-5600, City Hall Annex Room 300, buildcon@holyoke.org) — a completely different municipality. It does NOT describe Phillips County, Colorado's City of Holyoke in any way. The correct and verified official source for City of Holyoke, COLORADO is https://www.cityofholyoke-co.gov (confirmed via web search cross-referencing Phillips County, CO address 407 E. Denver Street, phone 970-854-2266, and Wikipedia/Census records for Holyoke, Colorado). All facts in this file are drawn exclusively from cityofholyoke-co.gov and its linked documents/PDFs, plus direct verification of Colorado statewide electrical/plumbing jurisdiction rules; none are drawn from the Massachusetts site.RE-CHASE 2026-07-23 — GAP CLOSED: Municode's Holyoke, CO library (library.municode.com/co/holyoke), previously returning 401/403 to automated tools, loaded successfully via a live browser session on this pass. The Holyoke Municipal Code, Title 15 - BUILDINGS AND CONSTRUCTION, is codified as Supplement 2, 'Online content updated on December 13, 2024,' 'Codified through Ordinance No. 1-2024, enacted September 17, 2024.' Holyoke has adopted, by reference, as its own local code (each chapter states a certified copy is on file with the city clerk): International Building Code, 2018 edition, incl. appendices C/E/I/J (Sec. 15.04.010); International Residential Code, 2018 edition (Sec. 15.08.010); International Mechanical Code, 2018 edition, incl. appendix A (Sec. 15.12.010); International Fire Code, 2018 edition, incl. appendices B/C/D/I (Sec. 15.16.010); International Energy Conservation Code, 2018 edition (Sec. 15.20.010); International Existing Building Code, 2018 edition (Sec. 15.22.010); 'the most recent edition of the Colorado Plumbing Code as adopted by the state plumbing board' as the city's own Plumbing Code, no fixed year — floats to whatever edition the state plumbing board currently has in effect (Sec. 15.24.010); and the National Electrical Code, 2017 edition, 'as adopted by the state' (Sec. 15.26.010). Quoted directly from the live Municode page.Local modifications on file (2026-07-23 re-chase): IBC 2018 Sec. 101.1 retitled 'Building Code of the City of Holyoke'; Sec. 103 deleted; Sec. 105.2 (Work Exempt from Permit) amended so 'fences not over six feet, three inches high' and 'retaining walls...not over four feet' are REMOVED from the exempt list (i.e., these now DO require a permit; see chapter 17.28 for fencing). IRC 2018 Sec. 101.1 retitled 'Residential Code of the City of Holyoke'; Sec. 104.10.1 (Flood Hazard Areas) deleted; Sec. 105.2 amended — exempt from permit: one-story detached accessory structures ≤120 sq ft; and 'decks not exceeding 120 square feet in area, that are not more than 18 inches above grade at any point, are not attached to a dwelling and do not serve the exit door required by section R311.4'; also exempt: like-for-like window/door replacement with no framing change; Sec. R313 (Automatic Fire Sprinkler Systems) deleted; Sec. N1102.4.1.2 (Testing) deleted. IMC 2018 Sec. 106.2 amended to exempt like-for-like category-one furnace/water-heater and A/C replacement (R-3 occupancies, prior install permitted/inspected/approved) from a new permit, and adds 'Sec. 106.5.2 Fee schedule. Fees for any permit, plan review or inspection required by this code shall be established from time to time by resolution of the city council' (confirms the fee-setting MECHANISM — a standalone council resolution, not a codified table — while the dollar figures themselves remain unpublished online; see the fee-schedule note below). IFC 2018 and IECC 2018 each retitled to the City of Holyoke's name in Sec. 101.1/C101.1 with no other substantive local modification noted.HB22-1362 (Colorado's statewide low-energy/carbon code requirement) and its predecessor HB19-1260 both operate on a 'when a jurisdiction updates its building code, the energy code update must accompany it' trigger — neither is a blanket mandate independent of a local update, and neither contains a population-based exemption threshold. The 2026-07-23 re-chase confirms the IECC edition currently on Holyoke's books is 2018 (not a newer low-energy cycle), but it could NOT establish exactly when Title 15's ICC chapters were last substantively enacted/updated: none of the Sec. 15.04.010 through 15.26.010 adoption sections carry an inline '(Ord. No. ___, ____)' legislative-history citation in the Municode text (unlike, e.g., the Mobile Home chapter at Sec. 15.28.010, which cites 'Ord. No. 5-1975'), and the code's front-matter 'codified through Ordinance No. 1-2024' banner reflects the single most-recent ordinance affecting ANY part of the whole Municipal Code, not necessarily Title 15 specifically. Whether HB22-1362 currently binds Holyoke therefore remains genuinely unresolved after this chase — recorded as such, not assumed either way — though it is now pinned down that whatever cycle IS in force is the 2018 ICC family, a materially more precise fact than the prior 'no edition found' state.RE-CHASE 2026-07-23 — GAP CLOSED (supersedes the DORA-vs-city ambiguity flagged in the prior 2026-07-06 pass): Holyoke Municipal Code Title 15 contains the City's OWN codified Electrical Code chapter (Sec. 15.26.010, adopting NEC 2017 'as adopted by the state,' expressly 'to provide for the issuance of permits and collection of fees therefor') and Plumbing Code chapter (Sec. 15.24.010, adopting by reference the state plumbing board's current Colorado Plumbing Code 'as the plumbing code of the CITY... providing for the issuance of permits and collection of fees therefor'). Both are codified as the City's own local ordinances under Title 15 - Buildings and Construction (footnoted to C.R.S. § 31-15-601 et seq., municipal building/fire-regulation power, and C.R.S. § 31-16-202, authority to adopt codes by reference) — not merely descriptive cross-references to a separate state process. This directly corroborates, on a live primary legal source, the City's own Forms & Documents page listing 'wiring' and 'plumbing' among its administered Building Department permit types, and as a home-rule municipality Holyoke has independent authority to run its own electrical/plumbing permitting program regardless of whether DORA's 'no state inspections in these counties' list includes Phillips County — that DORA list concerns default authority over UNINCORPORATED county land, not an incorporated home-rule city's own adopted code. Electrical and plumbing permits in Holyoke are therefore treated in this file as CITY-issued (City of Holyoke Building Department), under Secs. 15.26.010 and 15.24.010 respectively — not State of Colorado (DORA) issued. Remaining open, NOT resolved by the ordinance text: whether the City's own staff performs the physical inspections in-house or engages a state-certified/contract inspector — an operational detail the ordinance does not address.Fee-schedule mechanism CONFIRMED via primary ordinance text (2026-07-23), even though the dollar figures remain unpublished online: IMC Sec. 106.5.2 ('Fees...shall be established from time to time by resolution of the city council'); Zoning Sec. 17.44.050, Building permit—Fee ('A fee for the examination and administration of a building permit shall be payable to the city upon receipt of the application. The fee shall be as set from time to time by action of the city council and set out in the fee schedule.'); and the Mobile Home Regulations chapter, which repeatedly references applicants paying 'a fee in an amount set out in the consolidated fee schedule' (Secs. 15.28.040, 15.28.090). All three confirm Holyoke fees are set by a standalone CITY COUNCIL RESOLUTION establishing a 'consolidated fee schedule' — a document that is NOT part of the codified ordinances Municode publishes and was not located published online after this re-chase: checked the live city_council.php and city_clerk.php pages (no agendas/minutes/resolutions posted), ran a fresh Wayback Machine CDX index of the entire cityofholyoke-co.gov domain (562 archived URLs, filtered for fee/resolution/schedule/budget/council/minutes/agenda — the only hit was an unrelated 'Records Request Fees Schedule.pdf,' a CORA records-request fee document, not a building-permit fee schedule), and a live web search for 'City of Holyoke Colorado fee schedule resolution building permit' (returned only the already-flagged wrong-jurisdiction holyoke.org Massachusetts site plus unrelated other-Colorado-jurisdiction fee schedules). The consolidated fee schedule is confirmed to exist as a real governing document by council resolution, but its actual dollar figures remain genuinely unrecoverable via public online sources as of this pass.

Permit types & fees

Residential Building Permit (New Construction)

Verified

Required for new single-family residential construction within Holyoke city limits, issued by the City of Holyoke Building Department using its general Building Permit Application. RESOLVED 2026-07-23: the city has adopted the International Building Code, 2018 edition and International Residential Code, 2018 edition by reference as its own local code (Holyoke Municipal Code §§15.04.010, 15.08.010, current Supplement 2, Dec. 13, 2024), so review is against a specific, citable current-cycle code adoption, not merely the generic 2003-era Colorado Chapter ICC 'Building Guide' templates (which remain useful submittal aids but are not the code of record).

Verified 2026-07-23 · Source

Requirements

  • Completed City of Holyoke Building Permit Application, including owner, contractor, and (if applicable) architect information
  • Class of Work (New/Addition/Alteration/Repair/Move/Demo) and Type of Work (Residential/Commercial) specified on the application
  • Building dimensions (width x length, total square feet), number of stories, and whether plans are available must be indicated
  • Flood Plain Area status must be disclosed on the application (Yes/No checkbox)
  • Material Cost, Labor Cost, and Total Cost must be disclosed for permit fee and use tax calculation
  • For a genuinely new residence, standalone electrical/plumbing/mechanical permits are not required separately per the application's notice text (they may be covered under the umbrella building permit); this exception does NOT apply to additions, alterations, or repairs
  • Permit becomes null and void if work is not commenced within 180 days of issuance, or is suspended/abandoned for 180 days after commencement
  • Governing code is IBC 2018 / IRC 2018 as locally modified: IBC §101.1 retitled 'Building Code of the City of Holyoke,' §103 deleted, and §105.2 amended so that fences over 6'3" and retaining walls over 4' are NOT exempt from permit (Holyoke Municipal Code §15.04.020)

Required documents

  • RequiredCity of Holyoke Building Permit Application2020 version PDF, available in the Building Department Applications section of the city's Forms & Documents page
  • RequiredSite/floor plansThe city's Colorado Chapter ICC 'Building Guide' templates (for additions specifically) call for two sets of scaled site plans and two sets of scaled floor plans; the general Building Permit Application itself does not enumerate a plan-set requirement beyond checking 'Plans Available: Yes/No', so submittal depth for full new construction should be confirmed directly with the Building Department

Fee schedule

Fee typeAmountNotes
Building Permit FeeNo fee schedule (valuation table, flat rate, or square-footage rate) is published anywhere on the City of Holyoke website or in its downloadable applications; the Building Permit Application's 'For Official Use Only' section is filled in by city staff at issuance rather than computed from a public rate table. CONFIRMED 2026-07-23 via primary ordinance text (Holyoke Municipal Code §17.44.050, Building permit—Fee): 'The fee shall be as set from time to time by action of the city council and set out in the fee schedule' — i.e., a standalone council-resolution 'consolidated fee schedule' governs, not a codified table; that resolution document itself was not found published online after an exhaustive re-chase (live city council/clerk pages, full-domain Wayback CDX, web search). Confirm current fee directly with the Building Department (970-854-2266).
Use TaxA separate Use Tax line appears on the official permit form, confirming a municipal use tax applies to permitted construction, but no rate or formula is published.

Residential Addition / Remodel Permit

Verified

Required for additions, alterations, and repairs to existing residential structures in Holyoke. Unlike new-residence construction, additions and remodels always require standalone electrical/plumbing/mechanical permits where applicable, per the city's own Building Permit Application notice. RESOLVED 2026-07-23: governed by IRC 2018 as locally modified (Holyoke Municipal Code §15.08.010/.020), which carries several exemptions directly relevant to this permit type (see requirements).

Verified 2026-07-23 · Source

Requirements

  • Completed City of Holyoke Building Permit Application with Class of Work marked 'Addition,' 'Alteration,' or 'Repair'
  • Building dimensions and total added/altered square footage disclosed
  • Change of Use From/To fields completed if the project changes the use of the structure
  • Separate electrical, plumbing, and/or mechanical permits required if the scope touches those trades (the new-residence exception does not apply)
  • For additions specifically, the city's Colorado Chapter ICC 'Addition to a Family Residence' Building Guide calls for two sets of scaled site plans and two sets of scaled floor/framing plans, foundation detail selection (engineer-designed or the guide's prescriptive 'Detail A'), smoke alarm interconnection in new and existing bedrooms/hallways, and confirmation that the addition does not block bedroom or basement egress windows
  • Per Holyoke Municipal Code §15.08.020 (IRC 2018 local modification, confirmed 2026-07-23), EXEMPT from a building permit: one-story detached accessory structures ≤120 sq ft; decks ≤120 sq ft that are ≤18 inches above grade, not attached to a dwelling, and do not serve a required exit door; and like-for-like window/door replacement with no framing change. NOT exempt (permit required): fences over 7 feet high; retaining walls over 4 feet

Required documents

  • RequiredCity of Holyoke Building Permit Application2020 version PDF
  • OptionalAddition to a Family Residence Building Guide (fill-in-the-blank worksheet)Colorado Chapter ICC template (bilingual English/Spanish, dated 8/30/03) covering foundation, framing, insulation, and site-plan requirements for residential additions; available in English and Spanish on the city's Forms & Documents page

Fee schedule

Fee typeAmountNotes
Building Permit FeeNo published fee schedule; calculated by city staff at issuance based on Material/Labor/Total Cost disclosed on the application. CONFIRMED 2026-07-23: set by standalone city council resolution ('consolidated fee schedule') per Holyoke Municipal Code §17.44.050, which is not published online (exhausted: live council/clerk pages, full Wayback CDX, web search).
Use TaxApplies per the official permit form's fee block; no published rate

Electrical Permit

Verified

Required for wiring/electrical installation, alteration, or repair in Holyoke. RESOLVED 2026-07-23: Holyoke Municipal Code §15.26.010 (Electrical Code) codifies the National Electrical Code, 2017 edition, 'as adopted by the state,' as the City's OWN local electrical code, expressly 'providing for the issuance of permits and collection of fees therefor' under city ordinance authority. This permit type is therefore treated as CITY-issued (City of Holyoke Building Department), consistent with the Forms & Documents page listing 'wiring' among the permit types it administers — the DORA-vs-city ambiguity flagged in the 2026-07-06 pass is now resolved on a live primary legal source rather than left as an open discrepancy.

Verified 2026-07-23 · Source

Requirements

  • Governed by Holyoke Municipal Code §15.26.010, which adopts the National Electrical Code, 2017 edition ('as adopted by the state'), as the city's own Electrical Code, with any state amendments as may be made from time to time; a certified copy is on file with the city clerk
  • Issued by the City of Holyoke Building Department per the ordinance's express grant of authority to issue permits and collect fees under this chapter — not DORA/State Electrical Board issuance, though DORA licensing rules for who may perform electrical work (licensed contractor, or homeowner on owner-occupied non-rental property) likely still govern who may pull the permit
  • No fee schedule is published for this permit type on the city's site; per Holyoke Municipal Code §17.44.050, fees are set by a standalone city council resolution ('consolidated fee schedule'), not a codified table
  • Not separately confirmed by this file: whether the City's own staff performs the physical rough/final inspections in-house or contracts a certified inspector — an operational detail the ordinance text does not address

Required documents

  • RequiredCity of Holyoke Electrical (Wiring) PermitAdministered by the City of Holyoke Building Department per Holyoke Municipal Code §15.26.010 and the city's Forms & Documents page listing of 'wiring' as an administered permit type; a dedicated standalone electrical application form was not located separately from the general Building Permit Application

Fee schedule

Fee typeAmountNotes
Electrical Permit FeeNo fee schedule is published on the City of Holyoke's website. CONFIRMED 2026-07-23 via Holyoke Municipal Code §17.44.050: fees are set by a standalone city council resolution ('consolidated fee schedule'), not a codified table; that resolution was not found published online after an exhaustive re-chase (live council/clerk pages, full Wayback CDX, web search). Confirm current fee directly with the Building Department (970-854-2266).

Plumbing Permit

Verified

Required for plumbing installation, alteration, or repair in Holyoke. RESOLVED 2026-07-23: Holyoke Municipal Code §15.24.010 (Plumbing Code) adopts by reference 'the most recent edition of the Colorado Plumbing Code as adopted by the state plumbing board... as the plumbing code of the CITY,' expressly 'providing for the issuance of permits and collection of fees therefor' under city ordinance authority. This permit type is therefore treated as CITY-issued (City of Holyoke Building Department), consistent with the Forms & Documents page listing 'plumbing' among its administered permit types — the DORA-vs-city ambiguity flagged in the 2026-07-06 pass is now resolved on a live primary legal source.

Verified 2026-07-23 · Source

Requirements

  • Governed by Holyoke Municipal Code §15.24.010, which adopts by reference the CURRENT edition of the Colorado Plumbing Code as set by the state plumbing board (no fixed year — floats with whatever the state board has in effect), as the city's OWN Plumbing Code; a certified copy is on file with the city clerk
  • Issued by the City of Holyoke Building Department per the ordinance's express grant of authority to issue permits and collect fees under this chapter — not DORA/State Plumbing Board issuance, though DORA licensing rules for who may perform plumbing work (licensed Plumbing Contractor, or other qualifying applicant for certain non-licensed-required work) likely still govern who may pull the permit
  • No fee schedule is published for this permit type on the city's site; per Holyoke Municipal Code §17.44.050, fees are set by a standalone city council resolution ('consolidated fee schedule'), not a codified table
  • Not separately confirmed by this file: whether the City's own staff performs the physical rough/final inspections in-house or contracts a certified inspector — an operational detail the ordinance text does not address

Required documents

  • RequiredCity of Holyoke Plumbing PermitAdministered by the City of Holyoke Building Department per Holyoke Municipal Code §15.24.010 and the city's Forms & Documents page listing of 'plumbing' as an administered permit type; a dedicated standalone plumbing application form was not located separately from the general Building Permit Application

Fee schedule

Fee typeAmountNotes
Plumbing Permit FeeNo fee schedule is published on the City of Holyoke's website. CONFIRMED 2026-07-23 via Holyoke Municipal Code §17.44.050: fees are set by a standalone city council resolution ('consolidated fee schedule'), not a codified table; that resolution was not found published online after an exhaustive re-chase (live council/clerk pages, full Wayback CDX, web search). Confirm current fee directly with the Building Department (970-854-2266).

Mechanical / Sheet Metal (HVAC) Permit

Verified

Required for heating, ventilating, and air conditioning equipment installation or replacement in Holyoke, referred to on the city's Forms & Documents page as a 'sheet metal' permit. No evidence was found of a separate state deferral for mechanical/HVAC work (unlike electrical and plumbing, mechanical permitting in Colorado is not centralized through a DORA state board), so this permit type is treated as issued by the City of Holyoke Building Department. RESOLVED 2026-07-23: the adopted mechanical code is now confirmed — International Mechanical Code, 2018 edition (Holyoke Municipal Code §15.12.010).

Verified 2026-07-23 · Source

Requirements

  • Completed City of Holyoke Building Permit Application with the mechanical/HVAC scope described
  • Separate mechanical permit required except where the umbrella new-residence exception applies (new single-family construction only)
  • Governing code CONFIRMED 2026-07-23: International Mechanical Code, 2018 edition, adopted by reference as the city's own Mechanical Code (Holyoke Municipal Code §15.12.010), including appendix A
  • Per §15.12.020 local modification, exempt from a new mechanical permit: replacement/repair of a category-one furnace or water heater of the same BTU rating, and replacement/repair of A/C equipment of the same size/energy source/rating — both only in R-3 occupancies where the initial installation was permitted, inspected, and approved
  • §15.12.020 adds §106.5.2: 'Fees for any permit, plan review or inspection required by this code shall be established from time to time by resolution of the city council' — i.e., a standalone council-resolution fee schedule governs, not a codified table

Required documents

  • RequiredCity of Holyoke Building Permit ApplicationUsed for mechanical/sheet metal permits per the city's Forms & Documents page listing

Fee schedule

Fee typeAmountNotes
Mechanical Permit FeeNo published fee schedule; calculated by city staff at issuance. CONFIRMED 2026-07-23 via Holyoke Municipal Code §15.12.020 (IMC §106.5.2 as locally added): fees are set by a standalone city council resolution ('consolidated fee schedule'), not published online (exhausted: live council/clerk pages, full Wayback CDX, web search). §106.5.3 as locally modified also sets refunds at 50 percent for the relevant paragraphs, with refund requests due within 90 days of the fee payment date.

Re-siding / Re-roofing / Soffit Permit

Verified

Required for re-roofing, re-siding, and soffit replacement work in Holyoke, using the city's own dedicated 2020 Re-siding/Re-roofing/Soffit Permit Application — a distinct standalone form from the general Building Permit Application, unlike many peer jurisdictions in this corpus that fold re-roofs into the general building-permit process.

Verified 2026-07-06 · Source

Requirements

  • Completed Re-siding/Re-roofing/Soffit Permit Application specifying roof type (shingles, shakes, built-up, metal, tile, other) and/or siding type (wood, vinyl, metal, soffit, brick, other)
  • Contractor license Class, Number, and Expiration date must be disclosed on the application
  • Number of layers must be disclosed if roofing material is being overlaid rather than fully torn off
  • Material Cost, Labor Cost, and Total Cost disclosed for permit fee and use tax calculation
  • Permit becomes null and void if work is not commenced within 180 days or is suspended/abandoned for 180 days after commencement

Required documents

  • RequiredCity of Holyoke Re-siding/Re-roofing/Soffit Permit Application2020 version PDF, available on the city's Forms & Documents page

Fee schedule

Fee typeAmountNotes
Re-roof/Re-siding Permit FeeNo published fee schedule; the application's 'For Official Use Only' block (Permit Fee, Use Tax, Total) is completed by city staff at issuance rather than computed from a public rate table
Use TaxSeparate line item on the official application form; no published rate

Deck / Patio Cover / Enclosed Patio Permit

Verified

Required for uncovered decks, patio covers/carports, and enclosing existing patios in Holyoke. The city publishes three distinct Colorado Chapter ICC 'Building Guide' fill-in-the-blank worksheets for these scopes (Uncovered Decks, Patio Covers & Carports, Enclosing a Patio), used alongside the general Building Permit Application. RESOLVED 2026-07-23: the governing code is IRC 2018 (Holyoke Municipal Code §15.08.010), whose locally modified §105.2 exempt list directly covers small uncovered decks — see requirements.

Verified 2026-07-23 · Source

Requirements

  • Completed City of Holyoke Building Permit Application with Class of Work marked appropriately (typically 'New' or 'Addition')
  • For uncovered decks: guardrail height, baluster spacing, footing depth/size, and beam/joist sizing per the city's Uncovered Decks Building Guide worksheet
  • For patio covers/carports: post spacing, beam and rafter sizing, and attachment-to-existing-structure details per the Patio Covers & Carport Building Guide worksheet
  • For enclosing an existing patio: window/door egress and safety glazing requirements, insulation values, and structural connection details per the Enclosing a Patio Building Guide worksheet
  • Two sets of scaled site plans and two sets of scaled construction plans, per the general instructions printed on each Building Guide worksheet
  • CONFIRMED 2026-07-23 (Holyoke Municipal Code §15.08.020, IRC 2018 local modification): an UNCOVERED DECK is exempt from a building permit if it does not exceed 120 sq ft in area, is not more than 18 inches above grade at any point, is not attached to a dwelling, and does not serve a required exit door (IRC §R311.4) — decks exceeding any of those thresholds, or patio covers/carports/enclosures generally, DO require a permit. Retaining walls over 4 feet and fences over 7 feet also require a permit per the same section.

Required documents

  • RequiredCity of Holyoke Building Permit ApplicationGeneral application used for deck/patio cover/enclosure permits
  • OptionalUncovered Decks / Patio Covers & Carport / Enclosing a Patio Building Guide worksheetColorado Chapter ICC fill-in-the-blank template matching the specific scope (deck, patio cover/carport, or patio enclosure); available bilingually for some scopes on the city's Forms & Documents page

Fee schedule

Fee typeAmountNotes
Building Permit FeeNo published fee schedule; calculated by city staff at issuance. CONFIRMED 2026-07-23 via Holyoke Municipal Code §17.44.050: fees are set by a standalone city council resolution ('consolidated fee schedule'), not published online (exhausted: live council/clerk pages, full Wayback CDX, web search).

Rooftop Solar Photovoltaic Permit

Required for rooftop or ground-mounted solar photovoltaic installations within Holyoke city limits. As with every other permit type in this file, the City of Holyoke Building Department publishes no fee schedule (valuation table, flat rate, or square-footage rate) online — the general Building Permit Application's fee block is filled in by city staff at issuance rather than computed from a public rate table, and no separate solar-specific application or fee line exists. Colorado's statewide solar-fee cap (C.R.S. § 24-48.5-113, $500 residential/$1,000 commercial via HB21-1284) applies as a ceiling regardless of the amount the City ultimately assesses.

Reviewed 2026-07-20 · Source

Requirements

  • Completed City of Holyoke Building Permit Application, same general form used for other construction, describing the solar installation's scope, materials cost, and labor cost
  • RESOLVED 2026-07-23: electrical permitting authority is no longer an open ambiguity — Holyoke Municipal Code §15.26.010 codifies the City's OWN Electrical Code (NEC 2017), expressly providing for city issuance of permits and city collection of fees. The solar interconnection's electrical permit is therefore City-issued (City of Holyoke Building Department), not DORA/State Electrical Board-issued, per the electrical-permit entry elsewhere in this file
  • Colorado's statewide C.R.S. § 24-48.5-113 (HB21-1284) caps the aggregate of all fees a local government may charge to install an active solar energy system at $500 for a residential permit and $1,000 for a commercial permit, applying regardless of what the City's staff-calculated fee otherwise comes to
  • Same 180-day permit expiration clause applies as with any other Holyoke building permit

Required documents

  • RequiredCity of Holyoke Building Permit Application2020 version PDF, same general form used for other construction; no separate solar-specific application exists

Fee schedule

Fee typeAmountNotes
Building Permit FeeNo fee schedule (valuation table, flat rate, or square-footage rate) is published anywhere on the City of Holyoke website or in its downloadable applications for any permit type, including solar; the Building Permit Application's 'For Official Use Only' section is filled in by city staff at issuance. Confirm current fee directly with the Building Department (970-854-2266); subject to Colorado's statewide C.R.S. § 24-48.5-113 cap of $500 (residential) / $1,000 (commercial) on the aggregate of all local fees for an active solar energy system.
Use TaxA separate Use Tax line appears on the official permit form, confirming a municipal use tax applies to permitted construction including solar, but no rate or formula is published.

EV Charger / EVSE Permit

Holyoke has no dedicated EV charger or EVSE permit and no distinct fee line item for electric vehicle charging equipment. As with every other permit type in this file, the City of Holyoke Building Department publishes no fee schedule (valuation table, flat rate, or square-footage rate) online -- an EV charger installation would use the same general Building Permit Application used for other construction, with the fee block filled in by city staff at issuance rather than computed from a public rate table. Colorado's HB24-1173 (2024), which mandates expedited/standardized EV-charger permitting, applies only to counties of 20,000+ and municipalities of 10,000+ population -- Holyoke (population roughly 2,000) falls well below that threshold and is not a covered municipality under the statute.

Reviewed 2026-07-20 · Source

Requirements

  • Completed City of Holyoke Building Permit Application, same general form used for other construction, describing the EV charger installation's scope, materials cost, and labor cost
  • RESOLVED 2026-07-23: electrical permit authority in Holyoke is City-issued, not State-issued -- Holyoke Municipal Code §15.26.010 codifies the City's OWN Electrical Code (NEC 2017), expressly providing for city issuance of permits and city collection of fees, corroborating the Forms & Documents page's listing of 'wiring' among city-administered permit types; the charger circuit is therefore inspected under the City's own code, not the Colorado State Electrical Board
  • Holyoke does not meet the 10,000-population municipality threshold that triggers Colorado HB24-1173's mandatory model-code/expedited-review requirement for EV charger permits, so that statute does not apply here
  • Same 180-day permit expiration clause applies as with any other Holyoke building permit

Required documents

  • RequiredCity of Holyoke Building Permit Application2020 version PDF, same general form used for other construction; no separate EV-specific application exists

Fee schedule

Fee typeAmountNotes
Building Permit FeeNo fee schedule (valuation table, flat rate, or square-footage rate) is published anywhere on the City of Holyoke website or in its downloadable applications for any permit type, including EV chargers; the Building Permit Application's 'For Official Use Only' section is filled in by city staff at issuance. Confirm current fee directly with the Building Department (970-854-2266).
Use TaxA separate Use Tax line appears on the official permit form, confirming a municipal use tax applies to permitted construction including EV charger installations, but no rate or formula is published.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holyoke building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-06)View current record →All versions →